Projects · Battery Storage

Coolkeeragh, Foyle Port, near Londonderry, County Londonderry, Northern Ireland, UK·In developmentBattery Storage

Coolkeeragh BESS

  • StageConsented (2-hour scheme); revised four-hour application submitted to Derry City and Strabane District Council in November 2025
  • Next milestoneCouncil decision on the revised application; construction and operation would take about 9 to 12 months if approved
  • Last checked1 November 2026
Source: ABO Energy project page →

What has changed on this project, and when

  • Next milestone: Council decision on the revised application; construction and operation would take about 9 to 12 months if approved2 November 2026 · previously: Decision by Derry City and Strabane District Council on the revised four-hour application
  • Stage: Consented (2-hour scheme); revised four-hour application submitted to Derry City and Strabane District Council in November 20252 November 2026 · previously: Consented; revised planning application for a four-hour design submitted November 2025
  • Value: Not disclosed2 November 2026 · previously: Over £100 million (with Magherafelt)
  • Next milestone: Decision by Derry City and Strabane District Council on the revised four-hour application6 October 2026 · previously: Progression toward construction/financial close
  • Stage: Consented; revised planning application for a four-hour design submitted November 20256 October 2026 · previously: Consented