Projects · Battery Storage

Eccles, Scottish Borders·Under wayBattery Storage

Eccles BESS (Zenobe)

  • StageConstruction largely complete; testing and commissioning to follow
  • Next milestoneOperation expected in 2027
  • Last checked1 November 2026
Source: Zenobe Eccles project page →

What has changed on this project, and when

  • Next milestone: Operation expected in 20272 November 2026 · previously: Confirm whether the site has entered commercial operation. Zenobe's stated June 2026 commercial-operation date has passed and no confirmation of energisation was found on 8 Sep 2026, if it is live, this entry moves off the active-build list.
  • Stage: Construction largely complete; testing and commissioning to follow2 November 2026 · previously: Construction largely complete, commercial operation was due June 2026
  • Value: Not disclosed2 November 2026 · previously: £220m