Projects · Battery Storage
Trafford, Greater Manchester·Under wayBattery Storage
Carrington Storage, Trafford Low Carbon Energy Park
- StageIn construction (from autumn 2025); financial close reached
- Value£235m debt financing
- Next milestoneEnergisation targeted for late 2027
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Energisation targeted for late 20272 November 2026 · previously: Energisation expected late 2027
- Stage: In construction (from autumn 2025); financial close reached2 November 2026 · previously: In construction (from autumn 2025)
- Next milestone: Energisation expected late 202724 September 2026 · previously: Full energisation; Highview LAES Ph1 operational 2026
- Stage: In construction (from autumn 2025)24 September 2026 · previously: Energising 2026
- Value: £235m debt financing24 September 2026 · previously: Not disclosed
More Battery Storage projects
- Swinford BESSNottinghamshire, England, UK
- Withy Place BESSReading, Berkshire, England, UK
- EDF West Burton BESSWest Burton, near Retford, Nottinghamshire, England, UK
- Blackhillock Phase 2 (Zenobe)Keith, Moray
- Eccles BESS (Zenobe)Eccles, Scottish Borders
- Thorpe Marsh BESS (Fidra Energy)Thorpe Marsh (former power station site), near Barnby Dun, Doncaster
- Pillswood BESSCottingham, near Hull, East Riding of Yorkshire, England, UK
- Bumpers BESSBuckinghamshire (near Aylesbury), England, UK
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.