The map, week by week

What changed on the map.

Every week we re-check the projects on the map against their sources. This page lists what changed: a new stage reached, a milestone reset, a value revised, a project added. The new position, what it was before, and the source we checked it against, for the last four weeks.

Week of 9 November 2026: 4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised.

Week of 9 November 2026

4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised. 13 records re-checked at source.

Power & Grid · Peterhead, Aberdeenshire → Drax, Yorkshire

Eastern Green Link 2

  • Stage: The link has been under construction since late 2024.was: In construction — major construction phase from Jul 2026
  • Value: £4.3 billionwas: £4.3bn (corpus: gap-11)
  • Next milestone: Construction continues through 2027, and the link is due to start operating in 2029.was: Rattray Estate HDD for the 400kV Peterhead connection — start window (from Aug 2026) has passed; confirm commencement at next cycle

Source: SSEN Transmission and National Grid, EGL2 (6 Nov 2026) →On the map →

Power & Grid · Arnish Moor / Stornoway, Isle of Lewis to Fanellan (near Beauly)

Western Isles HVDC Link (Lewis Hub)

  • Stage: Under construction. SSEN Transmission marked the start of main construction at Arnish Moor, near Stornoway, on 5 November 2026.was: Consented (Nov 2025) - early construction works underway; dedicated delivery vessel secured (Feb 2026)
  • Next milestone: RJ McLeod is carrying out the first major set of construction works, preparing the site for the converter station and substation. SSEN Transmission expects to switch the link on by 2030, subject to approvals.was: Start of Lewis Hub construction / cable installation campaign

Source: SSEN Transmission, Lewis Hub news (6 Nov 2026) →On the map →

Renewables · Outer Firth of Forth / off Angus, east Scotland (~80 km offshore)

Ossian Offshore Wind Farm

  • Next milestone: Scottish Ministers have still to decide whether to approve the offshore application. No decision date has been published.was: Submit Section 36 offshore consent application to Scottish Ministers

Source: Ossian Offshore Wind Farm (SSE/Marubeni/CIP) →On the map →

Week of 2 November 2026

472 projects changed: 398 reached a new stage, 344 milestones updated, 164 values revised, 45 statuses changed, 39 projects added. 856 records re-checked at source.

Applied AI · The Oxford Science Park, Littlemore, Oxford

Ellison Institute of Technology (EIT) Oxford campus

  • Stage: Under construction; Littlemore House topped out February 2026was: Under construction — Littlemore House topped out Feb 2026
  • Value: Not disclosedwas: £890m fresh commitment (Oct 2025) plus £130m University of Oxford alliance
  • Next milestone: Campus buildings set to be in use in 2027was: Campus buildings set to come into use in 2027

Source: Cherwell / Research Professional News →On the map →

Applied AI · Central Laser Facility, Harwell Campus (Rutherford Appleton Laboratory), Oxfordshire

Extreme Photonics Applications Centre (EPAC)

  • Stage: Building completed and handed over 2022; laser construction under way; user access 'coming soon'was: In delivery — building complete (2022); laser installation and commissioning underway
  • Next milestone: First light and laser ramp-up from 2026was: Facility opening / first user science targeted for 2026

Source: STFC Central Laser Facility →On the map →

Applied AI · STFC Daresbury Laboratory, Sci-Tech Daresbury, Cheshire (Liverpool City Region)

Hartree Centre 'Mary Coombs' AI supercomputer

  • Stage: Launched 20 October 2025was: Launched and operational (October 2025)
  • Next milestone: Access for businesses and public sector organisations under the Hartree National Centre for Digital Innovationwas: Industry user ramp-up under the Hartree National Centre for Digital Innovation

Source: UKRI / STFC Hartree Centre →On the map →

Applied AI · National Composites Centre, Bristol

Isambard-AI (Bristol)

  • Stage: Operational (core component of the AI Research Resource; launched July 2025)was: Operational — AIRR flagship
  • Value: Not disclosedwas: £225m
  • Next milestone: Dedicated compute access for Sovereign AI fund portfolio companieswas: Compute access for Sovereign AI fund start-ups via the AIRR (from April 2026)

Source: University of Bristol BriCS (Jun 2026) →On the map →

Applied AI · Exeter

Met Office Next Generation Modelling Systems

  • Next milestone: Operational NWP implementation on the Met Office's next supercomputer, 2027/28was: Operational NWP implementation on the next supercomputer, 2027/28

Source: Met Office →On the map →

Applied AI · Harwell Campus, Oxfordshire

NQCC quantum testbeds (Harwell)

  • Stage: Seven prototype testbeds deployed at Harwell; Phase 1 concluded end of 2025, Phase 2 performance evaluation and benchmarkingwas: Testbeds deploying
  • Next milestone: Phase 2 testbed benchmarking resultswas: 30+ logical qubits target during 2026

Source: NQCC / Infleqtion (Mar 2026) →On the map →

Applied AI · Central Laser Facility, Rutherford Appleton Laboratory, Harwell Campus, Oxfordshire

Vulcan 20-20 laser upgrade (Central Laser Facility)

  • Stage: Under construction; Mace Construct signed main contract, moving from enabling works into main constructionwas: Under construction — ground broken 28 Nov 2025, substructure works under way (Mace); CLF states £85m (pin says £83m — align value)
  • Value: Not disclosedwas: £83m (UKRI)
  • Next milestone: Construction completion expected 2027, then commissioning and scientific operationswas: Completion of the facility building and installation/commissioning of the laser systems

Source: Mace - Mace Construct signs main contract for world-leading Vulcan 20-20 laser facility →On the map →

Aviation · Gatwick Airport, Crawley, West Sussex

London Gatwick Northern Runway

  • Status: Pipelinewas: At tender
  • Stage: Consented (DCO granted September 2025; final legal challenge rejected by Court of Appeal, August 2026); moving into deliverywas: Consented (DCO upheld by Court of Appeal, August 2026); detailed design and delivery phase
  • Value: Not disclosedwas: £2.2bn privately financed (London Gatwick)
  • Next milestone: Construction startwas: Routine dual-runway use expected from 2030; construction start date not yet published

Source: London Gatwick Airport — Northern Runway Plans →On the map →

Battery Storage · Auchteraw, near Fort Augustus, Highland, Scotland, UK

Auchteraw

  • Stage: Operational; fully energised and in operation (reported 3 September 2025)was: Operational (50MW/100MWh; energised September 2025)
  • Next milestone: Ongoing operationwas: No further milestone published; operational since September 2025

Source: Field - largest battery site to date →On the map →

Battery Storage · Near Buncrana (Trillick substation), County Donegal, Ireland

Ballynahone Energy Storage

  • Stage: Third-party planning appeal lodged with An Coimisiún Pleanála 4 Dec 2024; no decision listedwas: Consented by Donegal County Council (November 2024); under appeal to An Coimisiún Pleanála, re-advertised July 2026
  • Next milestone: An Coimisiún Pleanála appeal decisionwas: An Coimisiun Pleanala determination of the appeal

Source: An Coimisiún Pleanála - Case PL05E.321384 →On the map →

Battery Storage · South Kilvington, near Thirsk, North Yorkshire, England, UK

Bellmoor BESS

  • Stage: In planning (application ZB24/02454/HYB submitted to North Yorkshire Council, January 2025)was: In planning

Source: NatPower UK - Bellmoor →On the map →

Battery Storage · Near Berkswell, Solihull/Warwickshire border, West Midlands, England, UK

Berkswell BESS

  • Stage: Under construction since September 2026was: Under construction (200MW/857MWh; BW ESS/Penso Power with AIP Management investment)
  • Next milestone: Commercial operation, expected Q4 2027was: Planning determination and build-out toward ~2026 commissioning

Source: Energy Global - BW ESS and Danske Commodities sign optimisation agreement for 200 MW battery in UK →On the map →

Battery Storage · Bicker Fen, near Bicker/Boston, Lincolnshire, England, UK

Bicker Fen 1 BESS

  • Next milestone: In October 2026, Fidra Energy had yet to confirm the investment decision or a date for the site to start operating. Fidra lists Bicker Fen 1 and 2 as one combined site.was: Final investment decision expected 2026; operations targeted 2028

Source: Fidra Energy - Our Projects →On the map →

Battery Storage · Bicker Fen, near Bicker/Boston, Lincolnshire, England, UK

Bicker Fen 2 BESS

  • Next milestone: In October 2026, Fidra Energy had yet to confirm the investment decision or a date for the site to start operating. Fidra lists Bicker Fen 1 and 2 as one combined site.was: Final investment decision expected 2027; operations targeted 2029

Source: Fidra Energy - Our Projects →On the map →

Battery Storage · Keith, Moray

Blackhillock Phase 2 (Zenobe)

  • Stage: In construction; Phase 2 under way (Phase 1 in commercial operation since early 2025)was: In construction — Phase 2 under way
  • Value: Part of Zenobē's £750m Scottish investment programmewas: Part of Zenobe's £750m+ Scottish programme
  • Next milestone: Final commissioning and energisation Q1 to Q2 2027was: Phase 2 energisation — confirm date against Zenobe

Source: Zenobe Blackhillock project page / NS Energy →On the map →

Battery Storage · Bramford, near Ipswich, Suffolk, England, UK

Bramford BESS

  • Stage: Consented by Mid Suffolk District Council (April 2025)was: Consented
  • Next milestone: Construction; operation targeted for 2029was: Move to construction; operational target 2029

Source: Clearstone Energy →On the map →

Battery Storage · Brinsworth, Rotherham, South Yorkshire, England, UK

Brinsworth BESS

  • Stage: Consented; planning approved unanimously by committee in 2025was: Consented
  • Next milestone: Start of construction; energisation scheduled for mid-2028was: Start of construction; Root-Power gives mid-2028 for energisation

Source: Root-Power project page →On the map →

Battery Storage · Govan (near Ibrox), Glasgow, Scotland, UK

Broomloan Road BESS

  • Stage: In construction; development began in late 2023was: In construction
  • Next milestone: Energisation, scheduled by the developer for mid-2026was: Energisation; the developer's stated mid-2026 date has passed with no energisation announced

Source: Root-Power →On the map →

Battery Storage · Trafford, Greater Manchester

Carrington Storage, Trafford Low Carbon Energy Park

  • Stage: In construction (from autumn 2025); financial close reachedwas: In construction (from autumn 2025)
  • Next milestone: Energisation targeted for late 2027was: Energisation expected late 2027

Source: Statera Energy (Nov 2025) →On the map →

Battery Storage · Great Barr, Walsall, West Midlands, England, UK

Chapel Lane BESS

  • Stage: Allowed by planning inspector; Walsall Council's court challenge dismissed (Sep 2025)was: Consented on appeal; Walsall Council's High Court challenge dismissed September 2025, permission stands
  • Next milestone: Construction startwas: Planning determination and construction

Source: Walsall Council - Court dismisses case against Chapel Lane battery storage facility planning permission →On the map →

Battery Storage · Upminster, Essex (near M25), England, UK

Clay Tye BESS

  • Stage: Operational; energised and launched March 2024was: Operational
  • Next milestone: Continued operationwas: Continued merchant operation

Source: Harmony Energy / FRV →On the map →

Battery Storage · Graveney, near Faversham, Kent, England, UK

Cleve Hill Solar & Storage

  • Stage: Solar (373MWdc) operating since Jul 2025; 150MW/300MWh battery under constructionwas: Solar park operational since July 2025; 150MW battery storage under construction
  • Value: Not disclosedwas: ~£450 million (construction)
  • Next milestone: Battery commercial operation, estimated 2026was: Completion of the 150MW battery storage system; the developer's stated early 2026 completion has passed with no completion announced

Source: Quinbrook - Cleve Hill →On the map →

Battery Storage · Near Lesmahagow / Coalburn, South Lanarkshire, Scotland, UK

Coalburn BESS

  • Stage: Under construction (started 2026, about 18 months)was: Active confirmed: financial close 18 Jun 2026 AND preparatory site works begun per Zenobe; main construction from Jul 2026. Naming fix: Zenobe calls it 'Coalburn' (Alcemi/CIP's is the separate project)
  • Next milestone: Operational in 2027was: Complete construction; expected commercial operation mid-2027

Source: Zenobe - Coalburn project page →On the map →

Battery Storage · Coolkeeragh, Foyle Port, near Londonderry, County Londonderry, Northern Ireland, UK

Coolkeeragh BESS

  • Stage: Consented (2-hour scheme); revised four-hour application submitted to Derry City and Strabane District Council in November 2025was: Consented; revised planning application for a four-hour design submitted November 2025
  • Value: Not disclosedwas: Over £100 million (with Magherafelt)
  • Next milestone: Council decision on the revised application; construction and operation would take about 9 to 12 months if approvedwas: Decision by Derry City and Strabane District Council on the revised four-hour application

Source: ABO Energy project page →On the map →

Battery Storage · Dunsinane, Dundee, Scotland, UK

Dunsinane Battery Storage

  • Stage: Operational; began commercial operations in April 2023was: Operational
  • Next milestone: Continued operation with EDF as trading and optimisation partnerwas: Continued operation with EDF route-to-market

Source: EDF Energy →On the map →

Battery Storage · Eccles, Scottish Borders

Eccles BESS (Zenobe)

  • Stage: Construction largely complete; testing and commissioning to followwas: Construction largely complete — commercial operation was due June 2026
  • Value: Not disclosedwas: £220m
  • Next milestone: Operation expected in 2027was: Confirm whether the site has entered commercial operation. Zenobe's stated June 2026 commercial-operation date has passed and no confirmation of energisation was found on 8 Sep 2026 — if it is live, this entry moves off the active-build list.

Source: Zenobe Eccles project page →On the map →

Battery Storage · Aghada, Cork Harbour, County Cork, Ireland

ESB Aghada BESS (Phase 1)

  • Stage: Operational; launched in 2022 as ESB's first battery storage sitewas: Operational
  • Next milestone: Continued operationwas: Ongoing operation and grid services

Source: ESB press release →On the map →

Battery Storage · Aghada, Cork Harbour, County Cork, Ireland

ESB Aghada BESS (Phase 2)

  • Stage: Operational; officially opened on 15 November 2024was: Operational
  • Value: Part of ESB's investment of up to €300m in battery storage across Dublin and Corkwas: Part of ESB's ~€300m battery investment
  • Next milestone: Continued operation providing fast-acting storage for grid stabilitywas: Ongoing operation and grid/DS3 services

Source: ESB press release →On the map →

Battery Storage · Poolbeg peninsula, Ringsend, Dublin, Ireland

ESB Poolbeg BESS

  • Stage: Operational since late November 2023; officially launched February 2024was: Operational
  • Value: Part of ESB's investment of up to €300m in battery projectswas: Part of ESB's ~€300m battery investment
  • Next milestone: Continued operation providing fast-acting storage for grid stabilitywas: Ongoing EirGrid grid/DS3 system services

Source: ESB press release →On the map →

Battery Storage · Ferrybridge, near Knottingley, West Yorkshire, England, UK

Ferrybridge BESS

  • Stage: Fully operational (March 2026); construction began August 2023was: Operational
  • Next milestone: Ongoing operation supporting grid flexibility and system resiliencewas: Ongoing commercial dispatch and grid balancing

Source: SSE plc →On the map →

Battery Storage · Cuerdley, near Widnes/Warrington, Cheshire, England, UK

Fiddler's Ferry BESS

  • Stage: In construction since early 2024was: In construction
  • Next milestone: Completion and commissioningwas: Commissioning and grid energisation

Source: SSE Renewables →On the map →

Battery Storage · Gorman, near Wilkinstown/Navan, County Meath, Ireland

Gorman BESS

  • Stage: Operational; started up June 2022was: Operational
  • Value: EUR 28 millionwas: ~€28 million
  • Next milestone: Continued DS3 service to EirGrid under a six-year arrangementwas: Continued DS3 frequency-regulation service

Source: Iberdrola →On the map →

Battery Storage · Near Carlisle, Cumbria (location indicative), England, UK

Harker BESS

  • Stage: Consented (planning permission granted October 2023); initial enabling works from August 2026was: Consented / pre-construction
  • Next milestone: Site mobilisation in Q1 2027; energisation expected in 2028; commercial operation expected late 2028 or early 2029was: Main construction mobilisation in Q1 2027; energisation expected in 2028; commercial operation in late 2028 or early 2029

Source: Zenobe - Harker 400MW BESS project page →On the map →

Battery Storage · Harker, near Carlisle, Cumbria, England, UK

Harker BESS (Recurrent Energy)

  • Stage: Consented (Cumberland Council, June 2024)was: Consented
  • Next milestone: Construction anticipated from Q4 2029, subject to grid connection datewas: Construction anticipated from Q4 2029 unless an earlier grid connection date is agreed

Source: Recurrent Energy →On the map →

Battery Storage · Near South Hetton, County Durham, England, UK

Hawthorn Pit BESS (Zenobe)

  • Stage: In planning (application DM/26/01837/FPA being considered by Durham County Council)was: In planning (application submitted)
  • Next milestone: Determination by Durham County Council; earliest construction 2029was: Decision by Durham County Council on application DM/26/01837/FPA. No decision date has been published. Earliest construction start is 2029.

Source: Zenobe - Hawthorn Pit 300MW BESS project page →On the map →

Battery Storage · Kilmarnock (south of the town), East Ayrshire, Scotland, UK

Kilmarnock South BESS

  • Stage: Operational (commercial operations began January 2026)was: Operational (commercial operations began 21 Jan 2026)
  • Next milestone: Ongoing operation, including stability serviceswas: Entry into commercial operation (targeted late 2025/early 2026)

Source: Zenobe - Zenobe powers up Kilmarnock South battery storage project →On the map →

Battery Storage · Lister Drive, Tuebrook, Liverpool, Merseyside, England, UK

Lister Drive

  • Stage: Conditionally acquired by GRID in May 2026 (part of 777MW of new projects)was: Contracted - SPA signed 28 May 2026 (conditional acquisition by GRID); consented with Capacity Market contracts, Gate 2 connection Sep 2029, construction expected from early 2027; STP holds exclusivity on 25% stake
  • Next milestone: Completion of acquisition and financingwas: GRID acquisition and financing then construction

Source: Gresham House Energy Storage Fund - Interim Results for period ended 30 June 2026 (RNS) →On the map →

Battery Storage · Magherafelt, Mid Ulster, County Londonderry, Northern Ireland, UK

Magherafelt BESS

  • Stage: Consented (2-hour scheme); revised 4-hour application submitted to Mid Ulster Council in October 2025was: Consented (2-hour scheme), revised 4-hour application under determination
  • Value: Not disclosedwas: Over £100 million (with Coolkeeragh)
  • Next milestone: Council decision on the revised application; construction and operation would take about 9 to 12 months if approvedwas: Mid Ulster Council decision on the revised 4-hour application, then about 9 to 12 months of construction

Source: ABO Energy →On the map →

Battery Storage · North Yorkshire, England, UK

Monet's Garden

  • Status: Livewas: Pipeline
  • Stage: Under construction; financial close May 2026was: Consented/construction-ready - GRID acquisition completed Dec 2025, £141m senior debt concluded 26 May 2026, 25% STP JV equity completed 8 Jun 2026, construction due to start immediately; Gate 2 connection Jul 2027
  • Next milestone: Target energisation H2 2027was: Deal completion then construction start

Source: Gresham House Energy Storage Fund - Interim Results for period ended 30 June 2026 (RNS) →On the map →

Battery Storage · East Rounton, North Yorkshire, England, UK

Mowbray BESS

  • Stage: In planning (application ZB24/02455/HYB submitted to North Yorkshire Council, January 2025)was: In planning
  • Next milestone: Council determination; construction expected to start in 2026 if approvedwas: Council determination (ZB24/02455/HYB); construction anticipated from 2026

Source: NatPower UK - Mowbray →On the map →

Battery Storage · Mullavilly, near Tandragee, County Armagh, Northern Ireland, UK

Mullavilly BESS

  • Stage: Operational (as at November 2021)was: Operational
  • Next milestone: Ongoing operationwas: Ongoing grid-services optimisation

Source: Gore Street Energy Storage Fund RNS →On the map →

Battery Storage · Pembroke (Pembroke Net Zero Centre), Pembrokeshire, Wales, UK

Pembroke BESS

  • Status: Pipelinewas: At tender
  • Stage: Final investment decision taken December 2025; construction planned from H1 2026was: FID taken (Dec 2025); pre-construction - RWE: construction to start H1 2026, no site mobilisation evidenced
  • Next milestone: Construction; commissioning H2 2028, subject to grid connectionwas: Construction from H1 2026; commissioning H2 2028

Source: RWE - RWE to build its largest battery energy storage facility in the UK →On the map →

Battery Storage · Red Scar Business Park, Preston, Lancashire, England, UK

Red Scar

  • Stage: Operational (49MW); scheduled to be taken offline during Q2 2026 for augmentationwas: Operational but scheduled offline Q2 2026 for augmentation (GRID Q1 2026 RNS); recheck next cycle
  • Next milestone: Augmentation, then return to operationwas: Ongoing operation

Source: Gresham House Energy Storage Fund - Factsheet 31 March 2026 →On the map →

Battery Storage · Rufford, near Ollerton, Nottinghamshire, England, UK

Rufford

  • Stage: Operational (7MW); scheduled to be taken offline during Q2 2026 for augmentationwas: Operational but temporarily offline for augmentation (GRID Q1 2026 RNS); recheck next cycle
  • Next milestone: Augmentation, then return to operationwas: Ongoing operation

Source: Gresham House Energy Storage Fund - Factsheet 31 March 2026 →On the map →

Battery Storage · Salisbury, Wiltshire (adjacent to Salisbury substation), England, UK

Salisbury BESS

  • Stage: Operational since April 2024 (SSE Renewables, 50MW/100MWh)was: Operational since April 2024 (50MW/100MWh, SSE Renewables; Harmony divested the consented site to SSE in Aug 2021)
  • Next milestone: Ongoing operationwas: Start of construction (shovel-ready)

Source: SSE Renewables - Salisbury BESS project page →On the map →

Battery Storage · Lerwick, Shetland, Scotland, UK

Shetland BESS

  • Stage: Main construction complete; electrical installation under way (Jun 2026)was: Main construction complete; electrical installation and cold commissioning imminent (Zenobe, Jun 2026)

Source: Zenobe - Shetland Standby Project page →On the map →

Battery Storage · Quidhampton, near Salisbury, Wiltshire, England, UK

SSE Salisbury BESS

  • Stage: Fully operational since April 2024was: Operational

Source: SSE Renewables →On the map →

Battery Storage · Cushaling, County Offaly, Ireland

Statkraft Cushaling BESS

  • Stage: Operational; officially opened February 2026was: Operational
  • Next milestone: Ongoing operation; annual EUR 25,000 Sustainability Fund to begin in 2026was: Benchmark for further long-duration BESS in Ireland

Source: Statkraft Ireland →On the map →

Battery Storage · Tarbert, County Kerry, Ireland

Statkraft Kelwin-2 BESS

  • Stage: Operational since 2021was: Operational
  • Next milestone: Ongoing operationwas: Ongoing reserves/grid services to EirGrid

Source: Statkraft Ireland →On the map →

Battery Storage · Kilathmoy, Kerry-Limerick border, Ireland

Statkraft Kilathmoy BESS

  • Stage: Operational since April 2020was: Operational
  • Next milestone: Ongoing DS3 System Services to EirGridwas: Ongoing reserves/grid services to EirGrid

Source: Statkraft Ireland →On the map →

Battery Storage · Sundon (beside Sundon National Grid substation), Central Bedfordshire, England, UK

Sundon Storage

  • Stage: Consented Jan 2026; part of Ofgem's LDES scheme, under considerationwas: Consented (Jan 2026) and awarded Ofgem LDES cap-and-floor support in Window 1 (30 Jun 2026); pre-construction, full operation targeted 2030
  • Next milestone: Construction start later this decade; fully operational by 2030was: Construction later this decade; full operation targeted 2030

Source: Statera Energy - Sundon planning approval →On the map →

Battery Storage · Wilton International, Redcar, Tees Valley, England, UK

Teesside GigaPark

  • Stage: Consented (planning consent in place)was: Consented / pre-construction
  • Value: Not disclosedwas: £1 billion
  • Next milestone: Construction start planned 2027; grid connection targeted late 2028 or early 2029was: Construction start planned 2027; grid connection targeted late 2028/early 2029

Source: NatPower UK - Teesside →On the map →

Battery Storage · Thorpe Marsh (former power station site), near Barnby Dun, Doncaster

Thorpe Marsh BESS (Fidra Energy)

  • Stage: Financial close reached (September 2025); construction set to begin immediatelywas: In construction
  • Next milestone: Operational from mid-2027was: Operational mid-2027

Source: National Wealth Fund →On the map →

Battery Storage · Uskmouth, Newport, Wales, UK

Uskmouth BESS

  • Stage: Under construction since November 2023was: In construction
  • Next milestone: Energisation and commercial operation, expected 2026was: Energisation and commercial operation

Source: Quinbrook - Uskmouth →On the map →

Battery Storage · near Wakefield (adjacent to Wakefield B substation), West Yorkshire, England, UK

Wakefield B BESS

  • Stage: Consented on appeal 2 July 2026 (APP/X4725/W/25/3368025); pre-constructionwas: Consented on appeal - Wakefield Council refusal of the 99.9MW Heath scheme overturned by the Planning Inspectorate on 2 July 2026; pre-construction
  • Next milestone: Discharge of conditions and start of construction (permission requires start within three years)was: Planning determination

Source: Planning Inspectorate - Appeal decision, land south of Wakefield B Substation →On the map →

Battery Storage · West Burton, near Retford, Nottinghamshire, England, UK

West Burton C BESS

  • Stage: Financial close reached (17 Jul 2026); construction due to start later in 2026was: Consented; 10-year tolling agreement with Drax signed for 250MW/500MWh (Jan 2026); FID expected by Q3 2026, commercial operation target moved to 2028
  • Value: £231m loan facilitieswas: Not disclosed
  • Next milestone: Construction start; fully operational in 2028was: Final investment decision expected H1 2026; operations targeted Q4 2027

Source: Fidra Energy - Fidra Energy reaches financial close on 500MW West Burton C battery energy storage project →On the map →

Battery Storage · Eaglesham Moor, near Eaglesham, East Renfrewshire, Scotland, UK

Whitelee BESS

  • Stage: Operational since October 2022was: Operational
  • Next milestone: Ongoing operation, providing services to the National Gridwas: Ongoing operation in balancing/frequency markets

Source: ScottishPower Renewables →On the map →

Battery Storage · Wishaw, North Lanarkshire, Scotland, UK

Wishaw BESS

  • Stage: Constructed and connected directly to the transmission system; provides Constraint Management Service to the ESOwas: Operational
  • Next milestone: Continued constraint management serviceswas: Operational, delivering constraint-management services

Source: Zenobe - Wishaw case study →On the map →

Carbon Capture · Connah's Quay, Deeside, Flintshire, Wales

Connah's Quay Low Carbon Power (Uniper, HyNet)

  • Stage: DCO (EN010166) at Secretary of State decision stage; examination completed; decision due 9 Dec 2026was: DCO application (EN010166) in examination - ExA first written questions Feb 2026
  • Next milestone: DCO decision (due 9 Dec 2026)was: Contract award / FID

Source: Planning Inspectorate - Connah's Quay Low Carbon Power (EN010166) →On the map →

Carbon Capture · Drax Power Station, Drax, Selby, North Yorkshire, England

Drax Bioenergy with Carbon Capture (BECCS)

  • Status: Pipelinewas: At tender
  • Stage: £48m UK BECCS impairment taken; development deprioritised, long-term option retained (Feb 2026)was: pipeline (shelved - possible cancellation)
  • Next milestone: Appropriate commercial and regulatory support for carbon removals; no timeline setwas: Government BECCS business model / FID

Source: Drax Group - 2025 Full Year Results (26 Feb 2026) →On the map →

Carbon Capture · Stanlow Manufacturing Complex, Ellesmere Port, Cheshire, England

EET Hydrogen Production Plant 1 (HPP1, Stanlow)

  • Stage: ENKA lump sum turnkey EPC contract signed 15 Jan 2025; initial work under Limited Notice to Proceedwas: Consented; pre-construction/pre-FID - ENKA UK appointed EPC contractor under a conditional contract with a Limited Notice to Proceed phase (signed Jan 2025), FID still not taken; HyNet T&S backbone (Eni Liverpool Bay) reached financial close but HPP1's own FID remains pending
  • Next milestone: Full Notice to Proceed, then 39-month buildwas: FID / start of construction

Source: ENKA - Low Carbon Hydrogen Production Plant (HPP1) →On the map →

Carbon Capture · Immingham / South Killingholme, North East Lincolnshire, England

Humber Zero (VPI Immingham & Phillips 66 Humber Refinery Capture)

  • Stage: In development (phase one planned); potential initial emitter for Viking CCSwas: In development; anchor emitter for Viking CCS

Source: Humber Zero (VPI / Phillips 66) →On the map →

Carbon Capture · Ince, Ellesmere Port, Cheshire, England

Ince Bioenergy with Carbon Capture (Evero Energy, HyNet)

  • Stage: Planning application for InBECCS submitted (reported Jul 2026); on DESNZ Track-1 expansion Project Negotiation Listwas: Planning application for InBECCS submitted May 2026; in T1x negotiations (selected Aug 2025); targeting 2029 retrofit
  • Next milestone: Planning decisionwas: Contract award / FID

Source: Bioenergy Insight - Evero submits application for UK-first BECCS facility under GGR business model →On the map →

Carbon Capture · Keadby, near Scunthorpe, North Lincolnshire, England

Keadby 3 Carbon Capture Power Station (SSE Thermal & Equinor)

  • Stage: Development consent granted (7 Dec 2022); in active developmentwas: Development consent granted; awaiting business model / FID

Source: SSE Thermal / Equinor →On the map →

Carbon Capture · Depleted North & South Morecambe gas fields, East Irish Sea (offshore, operated from Barrow-in-Furness)

Morecambe Net Zero (MNZ) CO2 Storage (Spirit Energy)

  • Stage: Carbon storage licence CS010 entered Assess Phase (Jun 2026)was: Carbon storage licence CS010 - Assess Phase (Jun 2026)
  • Value: ~£5bn further construction and operations investment (developer estimate)was: ~£5bn additional investment potential (developer estimate)
  • Next milestone: Storage permit application; injection once gas production ends (end of decade)was: Storage permit application; injection once gas production ceases (~end of decade)

Source: Centrica / Spirit Energy (via World Pipelines) →On the map →

Carbon Capture · Padeswood, near Mold, Flintshire, Wales

Padeswood Cement Works Carbon Capture (HyNet)

  • Status: Pipelinewas: Live
  • Stage: Final contracts signed, marking FID (Sep 2025); construction expected shortlywas: FID taken (Sep 2025); contracts signed, construction starting
  • Value: Not disclosedwas: Part of UK's £9.4bn CCUS programme (project value not separately disclosed)
  • Next milestone: Construction startwas: Construction ramp-up; operations later this decade

Source: Heidelberg Materials / GOV.UK (DESNZ) →On the map →

Carbon Capture · Deeside Industrial Park, Deeside, Flintshire, Wales

Parc Adfer Energy from Waste Carbon Capture (Enfinium, HyNet)

  • Stage: Standby project for the HyNet carbon network (Aug 2025)was: In HyNet Track-1 expansion negotiations (standby)
  • Next milestone: Connection to HyNet should capacity become availablewas: Progression to priority / contract award

Source: GOV.UK (DESNZ) - 2,800 skilled jobs / HyNet expansion →On the map →

Carbon Capture · Tunstead / Buxton area, Derbyshire (with works in Staffordshire), England

Peak Cluster (Cement & Lime Carbon Capture)

  • Stage: Pipeline DCO (EN0710001) at pre-application; scoping opinion published 19 Feb 2026was: In development / pre-FID - National Wealth Fund equity investment secured (Mar 2026) and 'major milestone' reached Jun 2026; feeding MNZ storage which is in CS010 Assess Phase
  • Value: Not disclosedwas: ~£2bn+ investment programme; ~13,000 jobs safeguarded (developer estimate)
  • Next milestone: DCO application expected Mar 2028was: Pipeline consenting / FID alongside MNZ store

Source: Planning Inspectorate - Peak Cluster CCS Pipeline (EN0710001) →On the map →

Carbon Capture · Boddam, near Peterhead, Aberdeenshire, Scotland

Peterhead Carbon Capture Power Station (SSE Thermal & Equinor)

  • Stage: Section 36 application submitted; additional upstream emissions assessments completedwas: Section 36 application under determination, additional upstream emissions assessments complete, pre-construction
  • Value: Not disclosedwas: ~£2.2bn expected spend over 25 years (developer estimate)

Source: SSE Thermal - Peterhead Carbon Capture Power Station →On the map →

Carbon Capture · Ince Marshes, Protos energy hub, Ellesmere Port, Cheshire, England

Protos Energy Recovery Facility Carbon Capture (HyNet)

  • Stage: Under construction since Nov 2025; piling well under way, moving into civils phase (Aug 2026)was: Contracts signed; construction starting
  • Value: Not disclosedwas: Part of UK's £9.4bn CCUS programme (project value not separately disclosed)
  • Next milestone: Civils: pile cropping and reinforced concrete foundationswas: Construction; commissioning later this decade

Source: Protos - Community Newsletter August 2026 →On the map →

Carbon Capture · Runcorn Energy Recovery Facility, Weston Point, Runcorn, Cheshire, England

Runcorn Carbon Capture Project (Viridor, HyNet)

  • Stage: Standby project in HyNet expansion negotiations (list published Aug 2025)was: Standby project for HyNet expansion as of October 2026
  • Next milestone: Progression to priority / contract awardwas: No contract or final investment decision date published as of October 2026

Source: GOV.UK (DESNZ) HyNet expansion project negotiation list (updated 1 October 2026) →On the map →

Carbon Capture · Stanlow, Ellesmere Port, Cheshire, England

Silver Birch Direct Air Capture (Climeworks, HyNet)

  • Stage: Standby project for the HyNet carbon network (Aug 2025)was: Standby project for the HyNet carbon network
  • Next milestone: Connection to HyNet should capacity become availablewas: No date published for a decision on joining the network as of October 2026

Source: GOV.UK (DESNZ) - 2,800 skilled jobs / HyNet expansion →On the map →

Carbon Capture · Immingham to Theddlethorpe, Lincolnshire (storage in offshore Viking depleted gas fields)

Viking CCS CO2 Transport & Storage (Harbour Energy / bp)

  • Stage: Onshore pipeline DCO secured Apr 2025; FEED completed Q1 2025; development funding approved (Jul 2026); pre-FIDwas: DCO granted Apr 2025; DESNZ Viking CCUS Development Fund grant agreed (CMA SAU report 15 Apr 2026); pre-FID
  • Next milestone: FID, targeted in this Parliament, subject to project readiness and affordabilitywas: Government business-model agreement / FID

Source: Energy-pedia - Viking CCS development funding approved →On the map →

Data Centres · Cruiserath Road, Mulhuddart, Dublin 15

AWS Mulhuddart campus (three data centres)

  • Stage: Permission granted with revised conditions on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-constructionwas: Permission granted on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction
  • Next milestone: Construction startwas: Execute PPA; construction start

Source: An Coimisiún Pleanála →On the map →

Data Centres · Former Premier Periclase site, Drogheda, Co. Louth

CORE Sustainability Campus, Drogheda

  • Stage: Louth County Council application (ref 2460674) under third-party appeal by An Taisce, lodged 24 Jul 2025 (PL15.323134); no decision shown, due date of 26 Nov 2025 passedwas: Planning granted by Louth County Council (Jun 2025, ref 2460674); under third-party appeal to An Coimisiún Pleanála (An Taisce, lodged 24 Jul 2025), appeal undecided; 32MW phase 1
  • Value: Not disclosedwas: €600m-€1bn (10 years)
  • Next milestone: An Coimisiún Pleanála appeal decisionwas: Planning determination

Source: An Coimisiún Pleanála - Case PL15.323134 →On the map →

Data Centres · Culham Science Centre, near Abingdon, Oxfordshire

Culham AI Growth Zone

  • Stage: Announced as first AI Growth Zone (Jan 2025); private-sector partner still being sought (Mar 2026)was: Designated (Apr 2025); Strategic Investment Partner procurement underway
  • Next milestone: Agreement of public-private partnership with a private-sector partnerwas: Selection of Strategic Investment Partner

Source: South Oxfordshire and Vale - Statement of Common Ground for Culham Campus (LPA59 AS11) →On the map →

Data Centres · Ballymakaily, Lucan, Co. Dublin

EdgeConneX Lucan (Ballymakaily, two buildings)

  • Stage: Planning granted on appeal by An Coimisiún Pleanála, overturning South Dublin County Council's refusal; pre-constructionwas: Planning granted on appeal (Aug 2025); pre-construction
  • Next milestone: Construction start; corporate renewable PPA required before operationwas: Construction start

Source: Ballymakaily, two buildings — developer/operator record · reported TheJournal.ie →On the map →

Data Centres · Ennis, Co. Clare, Ireland

Ennis campus (Art Data Centres)

  • Stage: Works set to commence after the High Court found in the developer's favour in judicial review proceedings (March 2026)was: Build starting (judicial review dismissed March 2026; leave to appeal refused June 2026)

Source: RTÉ (Mar 2026) / Irish Times (Jun 2026) →On the map →

Data Centres · Blanchardstown, Dublin 15

Equinix DB7x, Blanchardstown

  • Stage: Construction began (announced 20 March 2026)was: Under construction (from Mar 2026)
  • Next milestone: Retail capacity available from early 2028was: Availability (early 2028)

Source: Equinix press release (20 March 2026) →On the map →

Data Centres · South Mimms, Hertsmere, Hertfordshire

Equinix DC01UK / Hertfordshire Campus, South Mimms

  • Stage: 85-acre site acquired, permitted for data centre development (Oct 2025)was: Outline planning permission granted (January 2025); pre-construction
  • Next milestone: Construction startwas: Detailed planning approvals and groundbreaking. No construction start date has been published.

Source: Equinix press release (30 October 2025) · Hertsmere Borough Council →On the map →

Data Centres · Nutmeg Lane, Poplar, Tower Hamlets, East London

Global Switch London South, Docklands

  • Status: Pipelinewas: At tender
  • Stage: Planning approved; Global Switch says London South 'is being developed'; no construction or completion date publishedwas: Planning approved (Feb 2024); pre-construction — no evidence of site works; completion targeted ~2027
  • Next milestone: Construction start (date not published)was: Completion (~2027)

Source: Global Switch - London data centres →On the map →

Data Centres · Former RAF Elsham Wolds, near Brigg, North Lincolnshire

Greystoke Elsham Tech Park, North Lincolnshire

  • Stage: Planning approved by North Lincolnshire councillors (reported Mar 2026); construction expected from 2027, first phase to open 2029was: Planning approved Mar 2026; construction planned to begin 2027, open 2029; no judicial review surfaced
  • Value: Up to £10bnwas: £7.5-10bn

Source: Data Centre Review - North Lincolnshire approves plans for major AI data centre campus →On the map →

Data Centres · Peel Waters / TraffordCity, Salford, Greater Manchester

Halo West data centre, Peel Waters, Salford

  • Stage: Unanimous approval by Salford City Council planning committee (reported 7 March 2025); pre-constructionwas: Planning approved (Feb 2025); pre-construction

Source: Peel Waters →On the map →

Data Centres · Naas Enterprise Park, Naas, Co. Kildare

Herbata 'grid-free' data campus, Naas

  • Stage: Under appeal to An Coimisiún Pleanála (first and third party appeals lodged 16 September 2025); decision not yet madewas: Planning granted (Aug 2025); under appeal
  • Value: Not disclosedwas: €3bn
  • Next milestone: An Coimisiún Pleanála decision, originally due by 28 January 2026was: An Coimisiún Pleanála decision on appeals lodged September 2025, originally due by 28 January 2026

Source: An Coimisiún Pleanála, RTÉ →On the map →

Data Centres · Kao Data campus, Harlow, Essex

Kao Data Harlow campus expansion (KLON-03/04)

  • Status: Pipelinewas: Live
  • Stage: KLON-03 (17.6MW) announced Mar 2025; two further buildings planned (Sep 2025); Nebius 22MW ten-year lease signedwas: KLON-03 under construction; further phases in planning
  • Value: Not disclosedwas: £1.7bn (Nebius UK deployment)
  • Next milestone: Construction of KLON-03 and planning for further buildingswas: KLON-03 energisation; KLON-04 consent

Source: Kao Data — developer/operator record · reported DatacenterDynamics →On the map →

Data Centres · Little Island, Cork Harbour, Co. Cork

Little Island data centre (former Mitsui Denman site), Cork

  • Stage: Building 1 fully constructed, fit-out outstanding (Mar 2025); grid connection agreement issued 18 Jul 2024; permission extended to 2027was: Building 1 shell complete — awaiting grid connection/fit-out; permission extended to 2027
  • Next milestone: Fit-out of building 1; second buildingwas: Fit-out; second building

Source: Irish Examiner - Little Island data centre permission extension →On the map →

Data Centres · Skelton Grange, Stourton, Leeds, West Yorkshire

Microsoft data campus, Skelton Grange, Leeds

  • Stage: Hybrid planning unanimously approved by Leeds City Council (Apr 2026); pre-constructionwas: Planning approved Apr 2026; construction now expected to begin early 2027
  • Value: £4bn (reported)was: £4bn
  • Next milestone: Construction start, likely within 12 to 18 months of approvalwas: Construction start

Source: Construction Enquirer - Go-ahead for Microsoft's £4bn Leeds data hub push →On the map →

Data Centres · Trawsfynydd, Gwynedd (former nuclear power station) with a second base at Prosperity Parc, Anglesey, North Wales

North Wales AI Growth Zone (Trawsfynydd / Anglesey)

  • Stage: Announced (13 Nov 2025); securing investment partnerwas: Designated (Nov 2025); securing investment partner
  • Value: Not disclosedwas: Up to £100bn (programme-wide AIGZ figure)
  • Next milestone: Confirmation of investment partner, then construction startwas: Confirmation of investment partner / construction start

Source: GOV.UK (DSIT) →On the map →

Data Centres · Cambois, near Blyth, Northumberland

QTS Cambois campus (Blackstone)

  • Status: Livewas: At tender
  • Stage: First phase (first two of up to ten buildings) approved by Strategic Planning Committee; enabling works well under way (December 2025)was: Consented; Phase 1 reserved matters approved, enabling works
  • Value: £10bnwas: Up to £10bn (Northumberland County Council)
  • Next milestone: Construction of the first data centre buildingswas: Construction of the first data centre building during 2026

Source: Northumberland County Council →On the map →

Data Centres · Rochfortbridge, Co. Westmeath

Red Admiral data campus, Rochfortbridge

  • Stage: Westmeath County Council application (ref 2560344) under third-party appeal to An Coimisiún Pleanála (PL25M.501550), lodged 17 Jun 2026; no decision shownwas: Granted 3 Jun 2026; stalled — 10 third-party appeals lodged with An Coimisiun Pleanala (one ruled invalid); decision awaited
  • Value: Not disclosedwas: €1bn

Source: An Coimisiún Pleanála - Case PL25M.501550 →On the map →

Data Centres · Slough Trading Estate, Slough, Berkshire

SEGRO Slough Trading Estate data centre

  • Stage: Pre-let signed in H1 2026 for a multistorey powered shell data centre; Slough Simplified Planning Zone pre-approves data centre developmentwas: Pre-let signed March 2026; consented under the estate's Simplified Planning Zone
  • Next milestone: Delivery in two phases as power becomes available; no completion date publishedwas: No completion date published as of October 2026

Source: SEGRO results for the six months to 30 June 2026 →On the map →

Defence Infrastructure · AWE Aldermaston, Berkshire

AWE Future Materials Campus, Aldermaston

  • Stage: Summer 2026 community consultation closed 19 Jul 2026was: PIN/market engagement for construction supply chain launched; summer 2026 public consultation; no civils partners appointed yet
  • Next milestone: Outline planning application to West Berkshire District Council (winter 2026); decision expected 2027was: No date published for appointing construction partners as of October 2026

Source: AWE Citizen Space - Future Materials Campus Summer 2026 →On the map →

Defence Infrastructure · BAE Systems Glascoed, near Usk, Monmouthshire

BAE Systems munitions expansion (Glascoed)

  • Stage: Expansion under way; new explosive filling facility at Glascoed due to become operational summer 2025 (April 2025)was: In construction / commissioning
  • Value: More than £150m invested in UK munitions facilities since 2022 (BAE Systems)was: >£150m since 2022 (BAE Systems)
  • Next milestone: Initial phase of expanded industrial capacity expected by end of 2026was: Initial expanded industrial capacity by end of 2026

Source: BAE Systems announcement · reported Joint Forces News →On the map →

Defence Infrastructure · Devonport Royal Dockyard, Plymouth

Devonport 10 Dock & submarine support infrastructure

  • Stage: £750m four-year infrastructure contract signed (November 2023); construction phase ramping upwas: In construction
  • Value: £750m over four years (MOD Submarine Delivery Agency / Babcock)was: £750m (MOD Submarine Delivery Agency / Babcock)
  • Next milestone: Dock and support infrastructure for Attack submarine deep maintenance projects later this decadewas: 10 Dock ready for Attack-class deep maintenance later this decade

Source: Babcock International Group →On the map →

Defence Infrastructure · Queen's Island, Belfast, Northern Ireland

Harland & Wolff Belfast shipyard modernisation (Navantia UK / Fleet Solid Support)

  • Stage: Belfast modernisation under way; over £98.5m invested (May 2026); new fabrication systems due fully operational Jul 2026was: Modernisation underway (~£100m invested at Jan 2026 one-year mark); note first FSS fabrication shifted to Cadiz as Belfast not yet ready
  • Value: Over £98.5m invested in Belfast (May 2026)was: ~£90m modernisation (FSS programme facilities budget ~£78m)
  • Next milestone: Belfast FSS middle mega-block build and final assemblywas: Completion of phase-one hull-building upgrades ahead of FSS block construction

Source: FW-MAG - Navantia UK marks progress towards build of new Fleet Solid Support ships →On the map →

Defence Infrastructure · HM Naval Base Portsmouth, Hampshire

HMNB Portsmouth infrastructure upgrades (Project Royal Oak)

  • Stage: Civil works under way, including piling and foundations for a new tower crane over 70m tall (May 2026)was: Crane civil works underway ahead of later-2026 installation; Project Royal Oak formally funded in Dec 2025 Defence Investment Plan (£26bn naval bases)
  • Value: Not disclosedwas: Part of £26bn Project Royal Oak across three naval bases (site value not disclosed)
  • Next milestone: Tower crane installation (later 2026)was: Tower crane installation later in 2026; Fountain Lake Jetty rebuild commencement

Source: KBS Maritime - Civil works begin on major lifting infrastructure investment at Portsmouth Naval Base →On the map →

Defence Infrastructure · MBDA Lostock site, Bolton, Greater Manchester

MBDA missile manufacturing expansion, Bolton

  • Status: Pipelinewas: Live
  • Stage: £200m Bolton expansion announced; footprint to more than double by 2028, creating 700 jobswas: Active - committed site expansion in delivery
  • Next milestone: Expanded Bolton facilities by 2028was: Expanded Bolton facilities operational by 2028

Source: reporting MBDA · reported Defence Online →On the map →

Defence Infrastructure · RAF Lakenheath, Suffolk

RAF Lakenheath US Air Force infrastructure upgrade

  • Status: Pipelinewas: Live
  • Stage: Reported $4.2bn USAF investment plan for UK bases, with Lakenheath apparently the largest recipient (Jun 2026)was: Rolling construction continuing; USAF announced ~$4.2bn further UK-bases investment June 2026 (scope expansion)
  • Next milestone: Delivery of weapons storage, accommodation and security upgradeswas: Completion of surety and support facilities supporting F-35A operations

Source: The Aviationist - U.S. Air Force plans major investment into UK bases →On the map →

Defence Infrastructure · Rolls-Royce Submarines, Raynesway, Derby

Rolls-Royce Raynesway site doubling, Derby

  • Stage: In construction: ground broken on new manufacturing facility (3 July 2026)was: In construction
  • Value: Not disclosedwas: Underpinned by £9bn MOD Unity contract (Jan 2025)
  • Next milestone: Build-out of the new manufacturing facility as part of the programme to double the Raynesway sitewas: New manufacturing facility build-out following July 2026 groundbreak

Source: Rolls-Royce →On the map →

Defence Infrastructure · Babcock Rosyth dockyard, Fife

Rosyth contingent submarine dock (£340m)

  • Status: Pipelinewas: At tender
  • Stage: Preliminary plans approved; industry engaged to start scheme design (December 2025)was: Committed; scheme design
  • Value: Not disclosedwas: £340m (MOD, via written parliamentary answer)
  • Next milestone: Contingent docking facility timed to coincide with HMS Dreadnought's exit from Barrow; final costs to be negotiated after the design phasewas: Contingent docking facility timed to coincide with HMS Dreadnought's exit from Barrow; final costs set after the design phase

Source: UK Parliament — written answer (Defence Procurement Minister) · reported UK Defence Journal →On the map →

Defence Infrastructure · Brightside Lane, Sheffield, South Yorkshire

Sheffield Forgemasters recapitalisation (13,000-tonne open die forge)

  • Stage: Construction well underway (July 2026): Forge foundations completed with steelwork assembly from April 2026; Machine Shop steelwork erectedwas: Active - steelwork/frame assembly underway
  • Next milestone: Completion of building frames and envelopeswas: Building framework completed and external cladding underway by end of 2026

Source: Sheffield Forgemasters →On the map →

Digital & Telecoms · Newgale, Pembrokeshire, Wales (Irish end: Kilmore Quay, Co. Wexford)

Beaufort subsea cable (AWS + Vodafone) – Wales landing

  • Stage: Planning application lodged with Pembrokeshire Coast National Park for the Newgale landing (reported June 2026); awaiting approvalswas: Detailed planning applications submitted Jun 2026 to Pembrokeshire Coast National Park Authority (Newgale landing, Kilmore Quay, Bude branch); awaiting determination
  • Next milestone: Planning approvals then marine installationwas: Consent approvals then marine installation

Source: AWS + Vodafone — developer/operator record · reported ISPreview →On the map →

Digital & Telecoms · UK-wide city footprints (pin: CityFibre HQ, Bedford Street, London)

CityFibre full-fibre build & Project Gigabit lots

  • Stage: Building under nine remaining Project Gigabit contracts after re-scoping agreed with BDUK (May 2026)was: In construction (network build to 2030)
  • Value: Not disclosedwas: £2.3bn financing round (CityFibre, Jul 2025)
  • Next milestone: Further 300,000 premises to be delivered across the nine Project Gigabit contracts by 2030; BDUK in talks with other suppliers for premises CityFibre will no longer servewas: Re-scoped Project Gigabit build-out and £800m M&A accordion consolidation through 2026–2030

Source: CityFibre →On the map →

Digital & Telecoms · Wembley Stadium, Wembley, London, England

EE 5G Standalone at Wembley Stadium

  • Stage: Permanent 5G Standalone network completed (February 2025); first public use 26 February 2025was: Live
  • Next milestone: Continued operation at stadium eventswas: Continued EE 5G SA densification nationally

Source: EE Newsroom →On the map →

Digital & Telecoms · Tullyneasky West, near Rosscarbery/Clonakilty, Co. Cork, Ireland

Fastnet subsea cable (AWS) – Cork landing station

  • Stage: Cable landing station permission granted on third-party appeal by An Coimisiún Pleanála, 14 Aug 2026was: Landing-station planning granted April 2026 but under appeal at An Coimisiún Pleanála (lodged May 2026, decision pending); MARA installation consent application MAC250018 submitted 11 Dec 2025 (status Applied); no construction start; RFS target 2028
  • Next milestone: Construction startwas: Maritime Area Consent and construction start; target ready-for-service 2028

Source: An Coimisiún Pleanála - Case PL88.501307 →On the map →

Digital & Telecoms · Goonhilly Downs, Lizard Peninsula, Cornwall, England

Goonhilly Earth Station

  • Stage: Active; acquired by Intuitive Machines (completion announced 3 August 2026)was: Active; owned by Intuitive Machines since August 2026
  • Value: Not disclosedwas: AGILE grant £1.6m; acquisition value not disclosed
  • Next milestone: Continued operation under Intuitive Machines ownershipwas: Delivery of the AGILE LunaNet interface unit

Source: Intuitive Machines / GOV.UK (AGILE) →On the map →

Digital & Telecoms · UK landing: Dumpton Gap, Broadstairs, Kent

IOEMA subsea cable (UK–NL–DE–DK–NO)

  • Status: Pipelinewas: At tender
  • Stage: Planned; intensified commercial phase to secure anchor customers ahead of contracts-in-force (May 2026)was: Pre-construction; seeking anchor customers ahead of contract-in-force
  • Value: Not disclosedwas: Not published (IOEMA Fibre Ltd consortium incl. Eurofiber, Arelion, Colt, EXA)
  • Next milestone: Contracts-in-force; ready for service expected Q1 2029was: Contract-in-force and supply contract; ready for service targeted Q1 2029

Source: IOEMA Fibre press release (via SubTel Forum) · Submarine Networks →On the map →

Digital & Telecoms · Dublin Bay, Ireland (UK end: Anglesey, North Wales)

Microsoft SOBR1 subsea cable – Dublin/Anglesey

  • Stage: MARA survey licence LIC230016 (Dublin Port landfall) determined 28 Jun 2024, now expiredwas: Marine-survey licence LIC230016 (Dublin Port landfall) determined by MARA 28 Jun 2024; installation/occupation consent not yet on MARA register; pre-construction
  • Next milestone: Maritime usage licence application for installation, if pursuedwas: Survey and installation consents

Source: Maritime Area Regulatory Authority - LIC230016, Microsoft Ireland Operations Ltd →On the map →

Digital & Telecoms · Portmarnock/Malahide, Co. Dublin, Ireland (UK end: Abergele, North Wales)

Microsoft SOBR2 subsea cable – Dublin/Abergele

  • Stage: MARA survey licence LIC230018 (Portmarnock landfall) determined 3 Jul 2024, expired 2 Jul 2026was: Marine-survey licence LIC230018 (Portmarnock landfall) determined by MARA 3 Jul 2024; installation/occupation consent not yet on MARA register; pre-construction
  • Next milestone: Maritime usage licence application for installation, if pursuedwas: Survey and installation consents

Source: Maritime Area Regulatory Authority - LIC230018, Microsoft Ireland Operations Ltd →On the map →

Digital & Telecoms · Kilmore Quay, Co. Wexford, Ireland (UK end: Newgale, Pembrokeshire)

Microsoft Tuskar subsea cable – Wexford/Pembrokeshire

  • Stage: MARA survey licence LIC230017 (Kilmore Quay landfall) determined 1 Jul 2024, now expiredwas: Marine-survey licence LIC230017 (Kilmore Quay landfall) determined by MARA 1 Jul 2024; route surveys carried out; installation consent not yet on MARA register; pre-construction
  • Next milestone: Maritime usage licence application for installation, if pursuedwas: Survey completion then route/install consents

Source: Maritime Area Regulatory Authority - LIC230017, Microsoft Ireland Operations Ltd →On the map →

Digital & Telecoms · Nationwide rural Ireland (pin: NBI HQ, Citywest, Dublin 24)

National Broadband Plan (NBI rollout), Ireland

  • Stage: In construction; final phase of the main build, over 500,000 premises passed (July 2026)was: In construction — final phase
  • Value: Not disclosedwas: c.€2.7bn state investment (C&AG-audited NBP subsidy)
  • Next milestone: Main infrastructure rollout completion by end of 2026was: Main fibre build completion due end-2026

Source: National Broadband Ireland →On the map →

Digital & Telecoms · Cardiff, Wales

Ogi full-fibre build – South Wales

  • Stage: FTTP network covers more than 118,000 premises in South Wales (Jun 2026)was: Building
  • Value: £200m initial backing (Infracapital) plus £45m Cardiff Capital Region financingwas: Not disclosed (£200m+ raised)
  • Next milestone: Further rollout across South Waleswas: Continued Wales-wide expansion

Source: ISPreview - Financial chief of Wales-focused full fibre broadband ISP Ogi to step down →On the map →

Digital & Telecoms · Galashiels, Scottish Borders, Scotland

Project Gigabit Borders & East Lothian – GoFibre

  • Stage: Contract awarded to GoFibre; contract concluded 1 October 2024was: Building
  • Next milestone: Network buildwas: Build in Kelso and Galashiels

Source: GOV.UK / GoFibre, Find a Tender, ISPreview →On the map →

Digital & Telecoms · Matlock, Derbyshire, England

Project Gigabit Derbyshire – Connect Fibre

  • Stage: In build; Connect Fibre says work has already begunwas: In delivery but formally descoped Jul 2026 (-5,775 premises, now 12,876 premises / £34.65m); build stalled at ~1,200 built (~9%) since early 2026
  • Value: Not disclosedwas: £35.0m
  • Next milestone: Continued build and first connections across Derbyshirewas: Continued build

Source: Connect Fibre - Project Gigabit (BDUK) →On the map →

Digital & Telecoms · Blandford Forum, Dorset, England

Project Gigabit Dorset & South Somerset – Wessex Internet

  • Stage: Network build running from 2024 through to 2029was: Building
  • Value: Not disclosedwas: £33.5m

Source: Wessex Internet / ISPreview →On the map →

Digital & Telecoms · Cirencester, Gloucestershire, England

Project Gigabit East Gloucestershire – Gigaclear

  • Stage: Contract signed with Gigaclear in February 2024; first premises expected to have access in 2024was: Early build

Source: GOV.UK / ISPreview →On the map →

Digital & Telecoms · Huntly, Aberdeenshire, Scotland

Project Gigabit North East Scotland – GoFibre

  • Stage: Build under way since Jan 2026was: Build under way — started Feb 2026, first premises live May 2026 (upgrade from 'mobilising')
  • Value: Not disclosedwas: £105m
  • Next milestone: Continued build across North East Scotland, including Montrose, Laurencekirk and St Cyruswas: Ramp-up across Aberdeenshire

Source: GoFibre - Project Gigabit Northeast →On the map →

Digital & Telecoms · Rural Northern Ireland (pin: Fibrus HQ, Belfast)

Project Gigabit Northern Ireland (Fibrus)

  • Stage: £34.6m Project Gigabit contract awarded to Fibrus (December 2025); work began immediatelywas: In delivery
  • Value: £34.6m contract (UK government funded)was: £34.6m public subsidy (DfE NI / BDUK)
  • Next milestone: Gigabit-capable build-out to over 9,000 rural premiseswas: Build-out through 2026–27; further NI Project Gigabit tranches expected

Source: ISPreview (Fibrus / NI Department for the Economy award) →On the map →

Digital & Telecoms · Newbury, West Berkshire, England

Project Gigabit Openreach Call-Off 1

  • Stage: Call-off 1 signed 28 Jun 2024; contract values and premises updated Jul 2026was: In delivery (~47% built per BDUK June 2026 data); small contract variation Feb 2026
  • Value: £159.3mwas: £159.2m
  • Next milestone: Build and connection of 60,180 contracted premiseswas: Continued multi-region build

Source: GOV.UK (BDUK) - Project Gigabit framework agreement: Openreach →On the map →

Digital & Telecoms · Nantwich, Cheshire, England

Project Gigabit Openreach Call-Off 8 (Cheshire)

  • Stage: Call-off 8 (Cheshire) signed 26 Feb 2026was: Contract live; build not yet reported (0 premises built in BDUK June 2026 data) — wording should be 'contract live, build starting' rather than 'building'
  • Next milestone: Build across Cheshirewas: Continued build across Cheshire

Source: GOV.UK (BDUK) - Project Gigabit framework agreement: Openreach →On the map →

Digital & Telecoms · Baltasound, Unst, Shetland, Scotland

SaxaVord ground station, Unst

  • Stage: Two antennas operating at Baltasound Teleport (installed 2021 and 2024); third in final preparations for deploymentwas: Two antennas operating at Baltasound; third being prepared
  • Next milestone: Deployment of the third antenna; no date publishedwas: No date published for the third antenna as of October 2026

Source: SaxaVord Spaceport →On the map →

Digital & Telecoms · Isle of Islay, Argyll and Bute, Scotland

Shared Rural Network – Islay not-spot removal

  • Stage: Live; publicly funded 4G total not-spot mast near Kilchoman, built by EEwas: Live
  • Value: Not disclosed (within £1.3bn SRN programme)was: Not disclosed (within SRN £1bn+ envelope)
  • Next milestone: Further TNS and EAS sites across rural Scotlandwas: Further Scottish rural mast upgrades under SRN

Source: Shared Rural Network — developer/operator record · reported Computer Weekly →On the map →

Digital & Telecoms · Southampton, Hampshire, England

Toob full-fibre build – Southampton/Solent

  • Stage: Own full-fibre network covers an estimated 256,500 premises (September 2025); 33 towns added via CityFibrewas: Building/expanding
  • Next milestone: Build toward 300,000 premises on own networkwas: Expansion beyond the Solent

Source: ISPreview →On the map →

Digital & Telecoms · Bakewell, Derbyshire, England

Virgin Media O2 5G Standalone – Bakewell (500th location)

  • Stage: Live; Bakewell became the 500th 5G Standalone location (15 September 2025)was: Live
  • Value: Not disclosed (within ~£700m 2025 Mobile Transformation Plan)was: Not disclosed (within ~£700m 2025 network plan)
  • Next milestone: Continued 5G Standalone rollout and small cells in dense urban areaswas: Continued VMO2 5G SA expansion and small-cell densification

Source: Virgin Media O2 Newsroom →On the map →

Digital & Telecoms · UK-wide rollout (pin: registered HQ, Newbury, Berkshire)

VodafoneThree £11bn network integration & 5G SA rollout

  • Stage: In deployment; Ericsson began rolling out VodafoneThree's 5G Core network (September 2026)was: In deployment
  • Value: £11 billion investment (VodafoneThree)was: £11bn over 8 years (VodafoneThree)
  • Next milestone: Continued 5G Standalone expansion towards 99% UK population coverage by 2030was: Continued mast integration and 5G SA expansion; 90% population coverage target by end of year 3

Source: VodafoneThree - Ericsson and VodafoneThree begin rollout of 5G Core network →On the map →

Gas & Critical Minerals · Plymouth, Devon, England

Altilium ACT3 EV battery recycling refinery

  • Value: £18.5m grant funding (April 2026)was: £30m planned investment (June 2025); £18.5m DRIVE35 grant (April 2026)

Source: Altilium →On the map →

Gas & Critical Minerals · Holford Brinefield, between Lach Dennis and Middlewich, Cheshire, England

Keuper Gas Storage Project (hydrogen conversion)

  • Stage: Consenting; seeking a material change to the 2017 DCO for hydrogen storage, consultation held 9 October to 20 November 2025; early site works done 2021 to 2022was: Hydrogen material-change application (consenting); early works done
  • Next milestone: Planning Inspectorate examination and Secretary of State decision; full construction expected to start in 2028, subject to consentwas: Determination of hydrogen material-change application; construction from ~2028

Source: Keuper Gas Storage Project (KGSP) / Costain →On the map →

Gas & Critical Minerals · Pool, between Camborne and Redruth, Cornwall

South Crofty tin mine (Cornish Metals)

  • Stage: In development: shaft refurbishment, dewatering and processing facility construction under way (June 2026)was: In construction
  • Value: £500m NPV (Mining Weekly, June 2026)was: £500m NPV at current tin prices (Mining Weekly, Jun 2026)
  • Next milestone: Winder mechanical installation in H2 2026; commercial production targeted by mid-2028was: Winder mechanical installation H2 2026; commercial production targeted mid-2028

Source: Cornish Metals — developer record (RNS) · reported Mining Weekly →On the map →

Gas & Critical Minerals · Cahiracon, Co. Clare (Shannon Estuary), Ireland

Strategic Gas Emergency Reserve — FSRU (Ireland)

  • Status: Pipelinewas: At tender
  • Stage: Government approved development (March 2025); Cahiracon chosen as preferred site; moving into pre-construction work (site investigations, marine surveys, FEED)was: Site selected (November 2025); FEED, surveys and planning preparation
  • Next milestone: Environmental assessment, planning application and final business case, then detailed design and construction subject to planning approvalwas: Planning applications and final business case, followed by FSRU procurement

Source: Gas Networks Ireland / gov.ie →On the map →

Gas & Critical Minerals · St Dennis, Cornwall

Trelavour lithium (Cornish Lithium)

  • Status: Pipelinewas: Live
  • Stage: DCO pre-application stage; s46 notification received 4 March 2026was: Demo plant producing; full-scale DCO application awaited
  • Value: Not disclosedwas: £800m+ GVA projected
  • Next milestone: DCO application expected to be submitted November 2026was: Full-scale DCO application (PINS BC0310001) — the stated summer 2026 window has passed and submission was NOT confirmed on 8 Sep 2026. Watch item.

Source: Cornish Lithium / PINS BC0310001 →On the map →

Gas & Critical Minerals · Drakelands, Hemerdon, near Plympton, Devon, England

Tungsten West — Hemerdon (Drakelands) mine restart

  • Stage: Construction under way; fine gravity circuit targeted Q3 and coarse circuit Q4 2026was: Restart / commissioning works (gravity circuits Q3-Q4 2026)
  • Value: £44.3m equity raise (Q1 2026); US$25m bridge loan (Q2 2026)was: >US$300m prior infrastructure spend; £44.3m 2026 equity raise + US$25m bridge loan
  • Next milestone: Full commissioning from Q1 2027; steady-state production H2 2027was: Full commissioning Q1 2027; steady-state production H2 2027

Source: Tungsten West - Project →On the map →

Gas & Critical Minerals · United Downs Industrial Estate, near Redruth, Cornwall, England

United Downs geothermal power & lithium (GEL / Cornish Lithium)

  • Stage: Operating; commissioned and exporting power since early 2026, with a lithium carbonate demonstration plantwas: Operating (power) / demonstration (lithium); new boreholes consented 2026
  • Value: ~£50m estimated total development costwas: ~£50m geothermal development
  • Next milestone: Scale-up of lithium extraction; further Cornwall geothermal sites at Manhay and Penhallow, both permittedwas: Scale-up of brine lithium extraction; further Cornwall geothermal sites (Manhay, Penhallow)

Source: GEL / Cornish Lithium — developer/operator record · reported ThinkGeoEnergy →On the map →

Gas & Critical Minerals · Former Eastgate cement works, Weardale, County Durham, England

Weardale Lithium demonstration plant

  • Stage: Planning granted for two-phase development at Eastgate; DRIVE35 Scale-Up feasibility funding announced Apr 2026was: Planning granted Feb 2025; DRIVE35 Scale-Up grant awarded Apr 2026; construction start not yet confirmed
  • Value: Not disclosedwas: ~£1bn projected regional economic activity
  • Next milestone: Feasibility study to map brinefield and de-risk wellfield scale-upwas: Commercial production targeted late 2026

Source: energy-pedia - Weardale Lithium secures DRIVE35 Scale-Up funding →On the map →

Health & Education Estates · Steeton with Eastburn, near Keighley, West Yorkshire

Airedale General Hospital rebuild (NHP Wave 1)

  • Status: Pipelinewas: At tender
  • Stage: Pre-construction; construction contract signed with GRAHAM on 30 July 2026 (Hospital 2.0 Alliance)was: Pre-construction (construction partner contract signed 30 July 2026)
  • Value: Not disclosedwas: £1bn+ (NHP Wave 1; H2A allocation May 2026)
  • Next milestone: Construction start (dates not yet published)was: Detailed design and approvals to follow the July 2026 contract; construction dates not yet published

Source: Airedale NHS Foundation Trust · GRAHAM · Building Better Healthcare →On the map →

Health & Education Estates · Becket Primary School, Derby

Becket Primary School rebuild (SRP)

  • Stage: Operational; new school building completed for the September 2026 school yearwas: Operational (new school building open September 2026)

Source: Derby City Council →On the map →

Health & Education Estates · Fulham Palace Road, Hammersmith, London

Charing Cross & Hammersmith Hospitals rebuild

  • Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035 to 2038)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5 billion to £2 billion
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · St Stephen's Hospital campus, Sarsfield Court, Glanmire, Co. Cork

Cork Elective Hospital

  • Stage: Pre-planning at Sarsfield Court, Glanmire; HSE planning application held up by access road issue (Jan 2026)was: Detailed design underway; surveys and site investigations complete; planning application expected to be lodged in 2026 (timeline slipped - shovel-ready now targeted for 2030 per Minister for Health, May 2026)
  • Next milestone: HSE planning application once access road resolved; shovel-ready not expected until 2030was: Planning and business case

Source: Irish Examiner - Jennifer Carroll MacNeill faces defining year on hospitals, overcrowding and agency spend →On the map →

Health & Education Estates · Derriford, Plymouth

Derriford Emergency Care Hospital

  • Stage: In construction; Emergency Care Building topped out (reported September 2026)was: NHP Wave 1 - in construction; Emergency Care Building topped out (reported September 2026)
  • Value: £247m (Emergency Care Building)was: Not disclosed

Source: University Hospitals Plymouth NHS Trust →On the map →

Health & Education Estates · Williams Avenue, Dorchester

Dorset County Hospital redevelopment

  • Stage: NHP Wave 0, already under construction (January 2025 plan)was: NHP Wave 0 - under construction
  • Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Completion of the redevelopmentwas: New Emergency Department and Critical Care Unit, topped out in July 2026, expected to open in 2027

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Kings Drive, Eastbourne, East Sussex

Eastbourne DGH & Conquest Hospital redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2037 to 2039)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Junction 7 M3, near Basingstoke, Hampshire

Hampshire Hospitals new acute hospital

  • Stage: NHP Wave 3; NHP funding committed to buy land at M3 J7; final site not decidedwas: NHP Wave 3 - committed (trust expects construction 2037-2039); site at M3 Junction 7 near Basingstoke purchased March 2026 with ringfenced NHP funds (land to remain farmed until needed)
  • Next milestone: Construction start 2037-39was: Programme business case / land assembly

Source: Hampshire Together - A funding commitment from New Hospital Programme to purchase land →On the map →

Health & Education Estates · Lowestoft Road, Gorleston-on-Sea, Great Yarmouth, Norfolk

James Paget University Hospital replacement

  • Stage: Hybrid planning application 06/25/1043/O validated Dec 2025, undecidedwas: NHP Wave 1 (RAAC) - pre-construction; Strategic Outline Case approved, OBC in development
  • Next milestone: Planning decision (due by 31 Dec 2026), then reserved matterswas: Construction start c.2027-28

Source: Great Yarmouth Borough Council - planning application 06/25/1043/O →On the map →

Health & Education Estates · Rothwell Road, Kettering, Northamptonshire

Kettering General Hospital redevelopment

  • Stage: Rockingham Wing maternity extension paused on cost (Oct 2026); energy centre under constructionwas: NHP Wave 2 - committed (construction start 2030-2035); enabling works underway - new energy centre under construction (completion targeted 2027), main scheme development resumes 2029/30
  • Next milestone: Business case assessment of maternity options (new build or Rockingham Wing extension); energy centre completion expected end 2027was: Business case / construction start early 2030s

Source: Kettering General Hospital - Update on future maternity, neonatal and gynaecology facilities →On the map →

Health & Education Estates · Standing Way, Eaglestone, Milton Keynes

Milton Keynes University Hospital redevelopment

  • Stage: NHP Wave 1; construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 - pre-construction
  • Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Construction startwas: Formal contract signing with Morgan Sindall, then construction start in 2027 to 2028

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · St James's Hospital campus, Dublin 8

National Children's Hospital, Dublin

  • Stage: In construction; completion and validation phase (over 2,850 of 5,728 rooms validated, March 2026); substantial completion will miss end-April deadlinewas: In construction — completion/validation phase
  • Value: €1.6bn incurred by NPHDB to end of February 2026 (including VAT)was: €1.6bn incurred to Feb 2026; final cost above €2.24bn approved budget (RTE/Oireachtas)
  • Next milestone: New substantial completion date awaited, followed by c.7-month commissioning before openingwas: Substantial completion and handover of keys; opening c.7 months later

Source: NPHDB — Oireachtas committee evidence (official record) →On the map →

Health & Education Estates · St Vincent's University Hospital campus, Elm Park, Dublin 4

National Maternity Hospital relocation to Elm Park

  • Stage: Preparatory works under way at St Vincent's; working with preferred bidders, main contract not awarded; final business case under review (Oct 2026)was: Enabling works underway at St Vincent's campus; main contract not awarded; new financial safeguards applied
  • Next milestone: Government approval of final business case and main contract awardwas: Main construction contract

Source: HSE - New National Maternity Hospital at the St Vincent's University Hospital campus →On the map →

Health & Education Estates · Leighton, Crewe, Cheshire

New Leighton Hospital, Crewe (NHP Wave 1)

  • Stage: Planning permission received June 2026; contractor appointment scheduled for summer 2026was: Planning approved (June 2026); pre-construction
  • Next milestone: Enabling works to begin on site summer 2027; main construction from 2028; opening 2032/33was: Enabling works to begin on site in summer 2027; main construction 2028; opening 2032/33

Source: Mid Cheshire Hospitals NHS Foundation Trust →On the map →

Health & Education Estates · Northern Meadows, Whitchurch, Cardiff

New Velindre Cancer Centre, Cardiff

  • Stage: Structure topped out (November 2025); internal fit-out startingwas: In construction — fit-out
  • Value: Not disclosedwas: PPP via Acorn consortium — construction value not published (widely reported c.£400m programme)

Source: Sacyr (Acorn consortium) →On the map →

Health & Education Estates · Delaunays Road, Crumpsall, Manchester

North Manchester General Hospital rebuild

  • Stage: NHP Wave 1; construction partner Bovis appointed (August 2026)was: NHP Wave 1, contractor appointed, pre-construction
  • Value: Up to £1.5bn reconstruction investment over nine yearswas: Not disclosed
  • Next milestone: Outpatient Centre construction start in 2027 subject to approvals, opening 2029; full hospital projected to open in 2035was: Outpatient Centre construction start 2027 subject to approvals, opening 2029, full hospital opening 2035

Source: Manchester University NHS FT, GOV.UK (DHSC) New Hospital Programme plan for implementation →On the map →

Health & Education Estates · Queen's Medical Centre, Derby Road, Nottingham

Nottingham Hospitals (QMC & City) redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035-2039)
  • Value: £2bn or more (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Pear Tree Infant and Nursery School, Derby

Pear Tree Infant & Nursery School rebuild (SRP)

  • Stage: Under construction; topping out reached (March 2026), school expected to open to pupils September 2026was: Under construction
  • Next milestone: Pupils move into the new school, then the former infant school is demolished and replaced with a playing fieldwas: Demolition of the old infant school after pupils move in, full scheme completion January 2027

Source: Derby City Council →On the map →

Health & Education Estates · Hamstel Road, Harlow, Essex

Princess Alexandra Hospital replacement

  • Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn (NHP cost band)
  • Next milestone: Construction startwas: Outline and full business cases, with construction start expected 2032 to 2034

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · London Road, Reading, Berkshire

Royal Berkshire Hospital redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2037 to 2039
  • Value: £2bn or more (DHSC estimate, January 2025)was: £2 billion or more (government cost band)
  • Next milestone: Construction startwas: Construction due to start between 2037 and 2039

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Ashton Road, Lancaster, Lancashire

Royal Lancaster Infirmary redevelopment

  • Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2035 to 2038
  • Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: £1 billion to £1.5 billion (government cost band)
  • Next milestone: Construction startwas: Construction due to start between 2035 and 2038

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Royal Sussex County Hospital, Brighton

Sussex Cancer Centre, Brighton (NHP)

  • Stage: £250m funding confirmed (January 2026); above-ground works planned to start on site summer 2026was: In construction
  • Value: £250m (New Hospital Programme)was: c.£250m (DHSC New Hospital Programme)
  • Next milestone: Opening 2029was: Above-ground works from summer 2026; opening 2029

Source: University Hospitals Sussex NHS Foundation Trust →On the map →

Health & Education Estates · Lawes Bridge, Torquay, Devon

Torbay Hospital redevelopment

  • Stage: New Hospital Programme Wave 2 scheme; construction start window 2032 to 2034 (NHP plan, Jan 2025)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £501m to £1bn (NHP cost band)was: Not disclosed
  • Next milestone: Construction start 2032 to 2034was: Business case / construction start early 2030s

Source: GOV.UK (DHSC) - New Hospital Programme: plan for implementation →On the map →

Health & Education Estates · Vicarage Road, Watford, Hertfordshire

Watford General Hospital redevelopment

  • Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn estimated cost (DHSC, January 2025)

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Whipps Cross Road, Leytonstone, London

Whipps Cross University Hospital rebuild

  • Stage: Planning approved (refs 211245, 211244); construction now estimated to begin 2032-34 after NHP reviewwas: Enabling milestone - multi-storey car park opened Nov 2025; main scheme uncontracted
  • Next milestone: Construction start 2032-34; completion 2036-38was: Business case / construction start early 2030s

Source: Barts Health NHS Trust - Whipps Cross redevelopment →On the map →

Heat & Industrial · St Fergus, Aberdeenshire

Acorn / Scottish Cluster

  • Status: Pipelinewas: At tender
  • Stage: Development stage, pre-FID; c.£200m UK development funding announced in Spending Review Jun 2025was: Pre-FID (Storegga's 30% stake offered for sale since December 2025)
  • Value: c.£200m development fundingwas: £200m committed
  • Next milestone: FID, targeted within this Parliamentwas: FID; new owner for Storegga's stake

Source: The Acorn Project - UK government confirms support for Acorn in Spending Review →On the map →

Heat & Industrial · Bristol (Temple Quarter / Bedminster / Redcliffe), England

Bristol City Leap Heat Network (Vattenfall)

  • Stage: Operating with 35 buildings connected; £13.5m Green Heat Network Fund award (May 2026) for the next phase; Bath Road Energy Centre approvedwas: Active construction / pipe-laying; Bath Road Energy Centre approved by Bristol City Council (February 2026)
  • Value: £13.5m Green Heat Network Fund grant (May 2026)was: £21.3m Green Heat Network Fund grant (May 2025) and a further £13.5m (May 2026); part of a >£100m programme
  • Next milestone: Construction of the Temple Quarter network joining the Temple, Old Market and Redcliffe networks; up to four more connections within the next yearwas: Construction of the 13MW Bath Road Energy Centre and the Temple Quarter network linking the Temple, Old Market and Redcliffe networks

Source: Bristol City Leap news, 20 May 2026 →On the map →

Heat & Industrial · Cardiff Bay / Butetown, Cardiff, Wales

Cardiff Heat Network

  • Stage: First heat delivered to Cardiff and Vale College (November 2025); further buildings to connect in phaseswas: Operational / phased connections underway
  • Next milestone: Phased customer connections; funding options being explored for a possible Phase 2 city centre expansionwas: Phased customer connections; exploring funding for Phase 2 city-centre expansion

Source: Cardiff Newsroom – Cardiff Heat Network delivers first low-carbon heat →On the map →

Heat & Industrial · City of London (Square Mile and fringes of adjacent boroughs)

City of London heat network (Square Mile concession)

  • Stage: In procurement (tender notice published 16 December 2025; final tenders due 22 June 2026)was: In procurement (tender notice December 2025; award decision due 5 November 2026)
  • Next milestone: Award decision estimated 5 November 2026; development agreement start 26 November 2026was: Development partner award decision 5 November 2026; development agreement programmed to start 26 November 2026

Source: Find a Tender (City of London Corporation); City of London Corporation →On the map →

Heat & Industrial · Belvedere, London Borough of Bexley, England

Cory Riverside 2 Energy-from-Waste & Riverside Heat Network

  • Stage: Riverside 2 under construction; Riverside Heat Network proposedwas: Under construction (EfW); heat network in development
  • Value: Not disclosedwas: Riverside 2 estimated at £500m+
  • Next milestone: Riverside 2 completion and heat network deliverywas: Riverside 2 commissioning (2026) and heat-network connection

Source: Cory Group – Riverside Heat Network →On the map →

Heat & Industrial · Derby city centre, Derbyshire, England

Derby Energy Network (1Energy)

  • Stage: In development; £23m Green Heat Network Fund grant awarded (January 2025)was: Pre-construction; consenting
  • Value: £23m Green Heat Network Fund grant plus over £100m 1Energy investmentwas: £23m Green Heat Network Fund grant (Jan 2025) plus £100m+ private investment
  • Next milestone: Planning consent and start of energy centre and network construction; heat on for Phase 1 customers planned for April 2029was: Planning consent and start of construction; the developer's programme dates of April 2026 and July 2026 have passed with neither announced. Heat supply to first customers targeted for April 2029

Source: 1Energy – Derby Energy Network →On the map →

Heat & Industrial · Queen Elizabeth Olympic Park, Stratford, East London, England

East London Energy Network Extension (Bring Energy)

  • Stage: £8.8m Green Heat Network Fund award (May 2025) to extend the Pudding Mill Lane networkwas: Development / committed pre-construction
  • Next milestone: Heat supply rolling out between 2027 and 2030was: Heat supply rollout 2027–2030

Source: Triple Point / GHNF – largest GHNF announcement to date →On the map →

Heat & Industrial · Gateshead town centre / Baltic Quarter, Tyne and Wear, England

Gateshead District Energy Scheme (mine water heat)

  • Stage: Operational since March 2023was: Operational and expanding
  • Value: Grant of almost £6m; scheme funded by the Heat Network Investment Project and Gateshead Councilwas: ~£6m Heat Networks Investment Project grant plus council funding
  • Next milestone: Connection of 270 privately owned homes, a new conference centre and a hotel developmentwas: Connection of 270 privately owned homes, a new conference centre and hotel development

Source: Mining Remediation Authority – Gateshead mine water energy scheme →On the map →

Heat & Industrial · Liverpool Bay / NW England

HyNet North West

  • Stage: Financial close reached (April 2025); project in construction phasewas: In construction — T&S 25% complete
  • Value: Not disclosedwas: £2bn+ approved
  • Next milestone: Completion of construction and start of CO2 storage operationswas: Douglas CCS platform installation — sources now disagree. Eni/HyNet material still refers to installation later in 2026, while project documentation describes the jacket, piles and topsides going in over roughly two months commencing Q2 2027. Treat the 2026 date as unsafe until Eni confirms.

Source: HyNet / Eni / Energy Voice →On the map →

Heat & Industrial · Leeds city centre / South Bank, West Yorkshire, England

Leeds PIPES District Heat Network (expansion)

  • Status: Pipelinewas: Live
  • Stage: Leeds PIPES operating; Hemiko appointed (March 2026) to develop a new city centre network, starting with a South Bank phasewas: Operational network, next city centre and South Bank phase in pre-construction with Hemiko

Source: Leeds City Council news →On the map →

Heat & Industrial · Manchester city centre (Civic Quarter), England

Manchester Civic Quarter Heat Network

  • Stage: Supplying low-carbon heat to first customer, Manchester Central; G99 and G100 compliance achievedwas: Operational / commissioning further connections
  • Next milestone: Connection of several more major civic buildings over the coming weekswas: Connection of several more civic buildings over coming weeks following G99/G100 commissioning

Source: Vital Energi press release – network begins delivering low-carbon heat →On the map →

Heat & Industrial · Kingston upon Thames, Greater London, England

Royal Borough of Kingston upon Thames Heat Network (Hogsmill)

  • Status: At tenderwas: Pipeline
  • Stage: Development-partner tender notice published 30 Apr 2026 (updated 15 May 2026); procurement under waywas: Development-partner tender launched May 2026 (contract award due Jun 2027)
  • Value: £360m ex VAT estimated contract value (£432m inc VAT); reference scheme £33m; GHNF grant est. £11mwas: ~£10–12m development-partner contract (wider network reported at ~£432m)

Source: Find a Tender - Procurement of a Development Partner for Kingston Potential Zone Area →On the map →

Heat & Industrial · Sheffield city centre, South Yorkshire, England

Sheffield Zonal Heat Network (Advanced Zoning Programme)

  • Value: £1.0m ex VAT (£1.2m inc VAT) development-partner contractwas: £1.0m (ex VAT) development-partner contract
  • Next milestone: Contract award; planned contract period 18 Aug 2026 to 17 Aug 2028was: Formal tender publication; contract period Aug 2026–Aug 2028

Source: Find a Tender - OCDS record, Heat Network Development Partner for the Sheffield AZP Opportunity Area →On the map →

Heat & Industrial · Worthing town centre, West Sussex, England

Worthing Heat Network (Hemiko)

  • Stage: Construction continuing: western arm towards Pavilion Theatre, early Sep to October half term 2026; Splashpoint connection pipework 15 Jun to 22 Julwas: Phase 1 complete (late 2025); Phase 2 preparatory works starting
  • Value: Not disclosedwas: £7m+ Public Sector Decarbonisation Scheme grant; £40m Hemiko investment (phase 1); ~£500m total by 2050
  • Next milestone: Further works on other sections later in 2026, planned around Christmas tradingwas: Hemiko aimed to finish phase 2 before the 2026 school summer holidays; completion unreported as of October 2026

Source: Worthing Heat Network - Next phase of Worthing Heat Network construction to continue this autumn →On the map →

Housing & Development · Aberfeldy Street area, Poplar, LB Tower Hamlets, London E14

Aberfeldy Village

  • Stage: Next phase (277 homes) granted planning permission by the Deputy Mayor on call-in, 26 January 2024, overturning Tower Hamlets' refusalwas: Later phases consented / progressing after Phases 1-3
  • Next milestone: Delivery of the approved 277-home phasewas: Delivery of the next approved 277-home phase

Source: Poplar HARCA / EcoWorld London — developer record (GLA approval) · reported Housing Today →On the map →

Housing & Development · South Acton, LB Ealing, West London W3

Acton Gardens (South Acton)

  • Stage: 2,098 homes completed (2012 to 2024); demolition and vacant possession of later phases under way, with demolition notices in October 2025 and February 2026was: Multiple later phases in demolition/construction
  • Next milestone: Construction of later phases and decanting of northern phases (subject to cabinet approval)was: Construction of the 1,000th affordable home and northern-site phase

Source: Ealing Council →On the map →

Housing & Development · Roehampton, LB Wandsworth, Southwest London SW15

Alton Estate (Alton Renewal Plan)

  • Stage: Block A planning approved March 2026; first demolition works from spring 2026was: Active council-led phased renewal; Block A planning approved March 2026

Source: Wandsworth Borough Council →On the map →

Housing & Development · Walworth, LB Southwark, London SE17

Aylesbury Estate

  • Stage: 321 homes under construction; council and Notting Hill Genesis agreed in principle (March 2026) that NHG completes three sites and the council seeks new partners for the restwas: Current phases on site; council seeking new partners for later phases (March 2026)
  • Next milestone: Phase 2B (640 homes) awaiting final planning permission; council to seek new development partnerswas: Phase 2B awaiting final planning permission as of March 2026

Source: Southwark Council (March 2026) →On the map →

Housing & Development · Barking Riverside, Barking & Dagenham, east London

Barking Riverside, London

  • Stage: In construction (phased); more than 3,000 homes delivered; revised outline consent for up to 20,000 homes (March 2026)was: In construction (phased)
  • Value: £170m+ Homes England infrastructure funding to datewas: £170m+ Homes England infrastructure funding; multi-£bn GDV (Barking Riverside Ltd)
  • Next milestone: Further phases under the revised 20,000-home outline consentwas: Next phases progress under the March 2026 20,000-home outline consent

Source: LB Barking & Dagenham planning consent · Barking Riverside Ltd (L&Q/GLA) · reported Construction Enquirer →On the map →

Housing & Development · Beam Park, Rainham, LB Havering / LB Barking & Dagenham, London RM13

Beam Park

  • Stage: 1,158 homes completed across the first two phases; Phase B (405 homes) approved June 2026was: Active construction; rail station funding being assembled 2026
  • Next milestone: Phase B construction expected to start in early 2027was: Confirmation of Beam Park station funding; Phase B construction start in early 2027

Source: Vistry Group →On the map →

Housing & Development · Bicester, Cherwell, Oxfordshire

Bicester Garden Town

  • Stage: Delivering large-scale housing and community infrastructure across Elmsbrook, Kingsmere and Graven Hillwas: Under construction - multiple neighbourhoods in delivery
  • Next milestone: Continued housing delivery; town-centre projects subject to fundingwas: Continued Kingsmere/Graven Hill build-out; town-centre regeneration

Source: Cherwell District Council - Bicester Garden Town →On the map →

Housing & Development · Poplar (Robin Hood Gardens), LB Tower Hamlets, London E14

Blackwall Reach

  • Stage: Phased regeneration; more than 600 homes built; final Robin Hood Gardens building demolished May 2025was: Active construction (multi-phase)
  • Value: Not disclosedwas: £300m+
  • Next milestone: Delivery of remaining phaseswas: Phase 4 GLA proposal / remaining phases

Source: Sanctuary →On the map →

Housing & Development · Filton Airfield, north Bristol

Brabazon (Filton Airfield), Bristol

  • Stage: In construction; some 300 homes occupied (March 2026)was: In construction
  • Value: Not disclosedwas: Not formally published — YTL private investment; arena and station under construction
  • Next milestone: Aviva Arena and other main elements due to start operating in 2028was: Bristol Brabazon station opening autumn 2026 (Network Rail); final new town locations due from government by end of 2026

Source: Construction Management (CIOB) / Brabazon (YTL) →On the map →

Housing & Development · Norbiton, RB Kingston upon Thames, London KT1

Cambridge Road Estate, Kingston

  • Stage: Phase 1 under construction; first families moved in May 2026; Block C approved by the Building Safety Regulator April 2026was: Phase 1 under construction with first homes occupied; Phase 2 reserved matters application submitted
  • Next milestone: Block C construction (due to start June 2026) and completion of Phase 2 detailed designswas: Block C construction, scheduled by the project to start in June 2026 after Building Safety Regulator approval; decision on the Phase 2 reserved matters application (25/02075/ARM)

Source: Kingston Council / Countryside →On the map →

Housing & Development · Rotherhithe peninsula, LB Southwark, London

Canada Water

  • Status: Pipelinewas: At tender
  • Stage: Phase one complete; revised masterplan approved by Deputy Mayor of London, Mar 2026was: Between phases - phase 1 complete; revised masterplan approved Mar 2026; next phase starts on site from 2027
  • Next milestone: Next phase to start on site from 2027was: Phase two construction from 2027

Source: Construction Enquirer - Go-ahead for revised Canada Water masterplan →On the map →

Housing & Development · Chilmington Green, southwest of Ashford, Kent

Chilmington Green

  • Stage: Administrators appointed to Hodson Developments (Ashford) Ltd and five associated companies (council update 4 Aug 2026); BDW and Jarvis Homes not affected; council and KCC taking legal advice on developers' section 106 obligationswas: Administrators appointed to Hodson Developments (Ashford) Ltd (council update 1 Jul 2026); BDW and Jarvis Homes phases stated unaffected; councils taking legal advice on s106 obligations
  • Next milestone: Council and KCC to secure developer obligations, subject to the effects of the administrationwas: Continued phased housing delivery, further schools, village centre

Source: Ashford Borough Council - Chilmington Green update →On the map →

Housing & Development · Church Street ward, City of Westminster, London NW8

Church Street

  • Stage: Ground broken on Site A (430 homes), the first construction phase (February 2026)was: Site A construction underway (started Feb 2026)

Source: Westminster City Council →On the map →

Housing & Development · Deptford, LB Lewisham, Southeast London SE8

Convoys Wharf

  • Stage: Plot 8 piling complete and work started on Plot 22; reserved matters approved for Plots 08, 15 and 22 (outline consent 2015)was: Active construction (early plots / piling underway)
  • Value: Not disclosedwas: ~£1bn
  • Next milestone: Further reserved matters applications on a rolling basiswas: Rolling reserved matters applications for subsequent plots

Source: Convoys Wharf (developer) →On the map →

Housing & Development · Cranbrook, near Exeter, East Devon

Cranbrook

  • Stage: Resolution to grant planning permission for first phase of Cranbrook expansion, up to 1,435 homes (April 2026)was: Under construction; expansion phase newly consented
  • Next milestone: Start of delivery of first expansion phasewas: Start of first expansion phase following April 2026 permission

Source: East Devon News / East Devon District Council →On the map →

Housing & Development · East Cullompton, Mid Devon, Devon

Culm Garden Village

  • Stage: Masterplan SPD adopted April 2023; Strategic Design Code and Phasing & Delivery Strategy approved for public consultation (September 2026)was: Plan-making / pre-construction (SPD adopted 2023)
  • Next milestone: Public consultation on the Strategic Design Code and Phasing & Delivery Strategywas: Phasing & Delivery Strategy and Strategic Design Code

Source: Culm Garden Village (Mid Devon District Council) →On the map →

Housing & Development · Dunton Hills, near West Horndon, Brentwood, Essex

Dunton Hills Garden Village

  • Stage: Brentwood Borough Council resolved to grant planning permission in principle (29 November 2023)was: Resolution to grant outline permission (November 2023), ahead of s106
  • Next milestone: Issue of planning permissionwas: Completion of s106 / issue of outline permission

Source: CEG / Housing Today →On the map →

Housing & Development · Earls Court, RB Kensington & Chelsea / Hammersmith & Fulham, London

Earls Court Development

  • Stage: Both boroughs resolved to grant planning permission (H&F 26 Nov 2025, RBKC 16 Dec 2025)was: Fully consented Dec 2025; 2026 start targeted but no Tier 1 confirmation of works underway - re-check soon
  • Next milestone: Early construction works expected to begin in 2026was: Phase one determination and construction start in 2026

Source: Earls Court Development Company - Stage set for £10bn transformation of Earls Court →On the map →

Housing & Development · Ebbsfleet Central, by Ebbsfleet International station, Kent

Ebbsfleet Garden City — Ebbsfleet Central

  • Stage: In tender: Ebbsfleet Central Phase 1a enabling infrastructure, two lots (tenders due 16 February 2026)was: In tender (enabling infrastructure)
  • Value: £95–115m indicative value across two lots (Phase 1a enabling infrastructure)was: £95–115m Phase 1 enabling works (EDC tender, Jan 2026); wider multi-£bn programme
  • Next milestone: Preferred bidders to be appointed under a pre-construction services agreement; construction scheduled from April 2028, completion expected May 2030was: Infrastructure contract awards following Feb 2026 tender deadline; works from April 2028

Source: Ebbsfleet Development Corporation →On the map →

Housing & Development · Festival Gardens, Otterspool riverside, south Liverpool

Festival Gardens

  • Next milestone: Phase 1 planning application expected late 2026, pending Cabinet approval; build to begin spring 2027was: Phase 1 planning application late 2026; construction anticipated spring 2027

Source: Urban Splash →On the map →

Housing & Development · Former Irish Glass Bottle site, Ringsend/Poolbeg, Dublin 4

Glass Bottle (Poolbeg West SDZ), Dublin

  • Stage: In construction (phased); first block, Lime House (212 apartments), completed late 2025was: In construction (phased)
  • Value: €3.5–€4bn GDV (Bisnow, April 2026)was: €3.5–€4bn GDV (Bisnow site report, Apr 2026)
  • Next milestone: Further buildings with 675 homes to finish in 2026; another 586 homes due to start construction in 2026was: 675 homes completing 2026; planning application for 1,510 further apartments lodged June 2026

Source: Pembroke Beach consortium — developer record (Poolbeg West SDZ) · reported Bisnow →On the map →

Housing & Development · Beresford Avenue, Alperton, LB Brent, London HA0

Grand Union, Alperton

  • Stage: Under construction; medical centre and workspace being built, Community Information Centre completewas: Multi-phase construction and occupation ongoing
  • Next milestone: Continued delivery of remaining homes and facilitieswas: Continued phased delivery of remaining blocks

Source: Brent Council →On the map →

Housing & Development · North Greenwich / Greenwich Peninsula, RB Greenwich, London

Greenwich Peninsula

  • Stage: Mace appointed to a 10-year build framework covering 21 projects, including Lower Riverside and Meridian Quays plots; work set to start immediatelywas: Multiple plots under construction
  • Value: About £2bn capital value (Mace framework)was: Circa £8bn; £2bn Mace framework
  • Next milestone: Construction of framework plots at Lower Riverside and Meridian Quayswas: Completion of current tower phase through 2026

Source: Knight Dragon — developer record · reported Housing Today →On the map →

Housing & Development · Tottenham Hale, LB Haringey, London N17

Hale Wharf / Tottenham Hale

  • Stage: 503-home regeneration with new pedestrian bridge delivered; won Best Regeneration Initiative at the 2025 Housebuilder Awardswas: Hale Wharf complete (September 2024); district regeneration active
  • Value: £200 millionwas: Not disclosed
  • Next milestone: No further phases statedwas: No further Hale Wharf phases; wider Tottenham Hale regeneration continues

Source: Muse Places / Haringey Council →On the map →

Housing & Development · Handforth (north of the A34/Wilmslow), Cheshire East

Handforth Garden Village

  • Status: Livewas: Pipeline
  • Stage: Work started on new gateway entrance, implementing the existing planning consent (August 2026)was: Initial works started on site (August 2026); main infrastructure works to follow
  • Value: Not disclosedwas: £57.9m (delivery allocation)
  • Next milestone: Council decision on MADE's application to vary the 2023 planning consentwas: Council decision on the variation application (26/2366/VOC) submitted in June 2026. No decision date has been published.

Source: Cheshire East Council →On the map →

Housing & Development · Heyford Park (former RAF Upper Heyford), Cherwell, Oxfordshire

Heyford Park New Town

  • Status: Pipelinewas: Live
  • Stage: Not taken forward as a New Town at this stage (March 2026); deemed a credible development opportunitywas: Not taken forward as a New Town (Mar 2026), existing development continues
  • Next milestone: Possible support through existing housing programmeswas: Cherwell decision on Dorchester Living application for about 9,000 homes

Source: GOV.UK, Cherwell District Council →On the map →

Housing & Development · Tottenham (west of the High Road / White Hart Lane), LB Haringey, London N17

High Road West, Tottenham

  • Stage: Cabinet agreed to appoint a contractor for Phase 1A (61 council homes), to be delivered by the councilwas: Phase 1A contractor appointment approved, council delivering
  • Value: Not disclosedwas: ~£2.5bn (end value)
  • Next milestone: Phase 1A completion expected in 2028was: Phase 1A completion (61 council homes) expected in 2028

Source: Haringey Council, Lendlease →On the map →

Housing & Development · Kidbrooke, RB Greenwich, London

Kidbrooke Village

  • Stage: Homes on sale across several phases, including homes ready to move inwas: Later phases in construction and sales
  • Next milestone: Continued sales of current phaseswas: Consent and start of revised next phase (Meridian Gate)

Source: Berkeley Group →On the map →

Housing & Development · Central Docks, north of Pier Head, Liverpool waterfront

Liverpool Waters (Central Docks)

  • Stage: £71m infrastructure works under way after groundbreaking marked October 2025was: Infrastructure works under construction (groundbreaking Oct 2025)
  • Value: £81m Central Docks infrastructure packagewas: £5.5bn masterplan; £81m Central Docks package
  • Next milestone: Completion of Central Docks infrastructure and Central Park by late spring 2028was: Central Docks infrastructure and Central Park completion by 2028

Source: GOV.UK (MHCLG / Homes England) →On the map →

Housing & Development · Long Marston, near Stratford-upon-Avon, Warwickshire

Long Marston Airfield Garden Village

  • Status: Pipelinewas: Live
  • Stage: Phase 1 outline (400 homes) and reserved matters granted; Phase 1A and 1B applications under consideration; Phase 2 outline application (3,100 homes) submittedwas: Phase 1 under construction; Phase 2 outline submitted
  • Next milestone: Determination of Phase 1A, Phase 1B and Phase 2 applicationswas: Determination of Phase 1B and Phase 2 applications

Source: Stratford-on-Avon District Council (Long Marston Airfield SPD) →On the map →

Housing & Development · Marlcombe, near Honiton, East Devon

Marlcombe New Town

  • Stage: Not one of the seven priority areas in the Draft New Towns Programme (23 Mar 2026); East Devon District Council Cabinet endorsed governance and partnership arrangements for delivery on 1 Apr 2026was: Dropped from the government's new towns programme (22 Mar 2026, retained only as a 'reasonable alternative'); East Devon District Council is continuing Marlcombe as a locally-led new community of up to 25,000 people through the emerging East Devon Local Plan 2020-2042 (post-Regulation 19)
  • Next milestone: Locally led development corporation overseen jointly with Devon County Council, if approved by both councils; further reports to Cabinet later in 2026was: Final location confirmation

Source: Devon Air Radio - East Devon pushes forward with Marlcombe new community →On the map →

Housing & Development · Mayfield, Manchester (adjacent to Piccadilly station)

Mayfield

  • Status: Pipelinewas: At tender
  • Stage: Resolution to grant detailed consent for the first 879 homes, but Landsec does not expect to start construction before late 2027 (May 2026), seeking easing of affordable housing and CIL requirementswas: First 897 homes consented but Landsec has deferred residential starts to 2027 at the earliest, citing insufficient returns
  • Value: Not disclosedwas: £1.4bn
  • Next milestone: Start on site of first residential plots, not before late 2027was: First 880 homes plus transport hub to start on site in 2026

Source: Construction Enquirer - Landsec flags more delays on major housing starts →On the map →

Housing & Development · Near Yarnfield and Cold Meece, north of Stafford, Staffordshire

Meecebrook Garden Community

  • Stage: Garden Community proposals (status secured 2019); evidence base for new Local Plan 2025 to 2045 in preparationwas: Emerging strategic allocation in Stafford Local Plan (plan-making)
  • Next milestone: Progression of the new Local Plan 2025 to 2045was: Progression of the new Local Plan (Reg 18/19 consultation)

Source: Stafford Borough Council (Meecebrook) →On the map →

Housing & Development · Edmonton, LB Enfield (Lee Valley), London

Meridian Water

  • Stage: Meridian One A construction completed (301 homes), Mar 2026; 273 affordable homes completed across the project to date; Vistry to return to site later in 2026 for c.700 homeswas: Next-phase works underway, but Enfield signalled a shift away from its master-developer role (Mar 2026 delivery review) - monitor

Source: Enfield Council - Final residents move into Meridian One A as construction is completed →On the map →

Housing & Development · Middlewood Locks, Salford (near Salford Central)

Middlewood Locks

  • Stage: 1,306 homes delivered; National Housing Bank funding for the 909-home Phase 4 agreed July 2026was: Around half delivered, 909-home Phase 4 funded July 2026, start on site targeted early 2027
  • Next milestone: Start on site of the 909-home Phase 4, hoped for early 2027, with first homes available for occupation in 2030was: Start on site of the 909-home Phase 4 targeted for early 2027, first occupations 2030

Source: Scarborough Group — developer/operator record · reported Construction Enquirer →On the map →

Housing & Development · Milton Keynes, Buckinghamshire

Milton Keynes (Renewed Town)

  • Stage: One of seven proposed new towns in Draft New Towns Programme (23 Mar 2026, about 40,000 homes); consultation closed 19 May 2026was: Pre-construction / planning; proposed as one of seven new towns in the government's New Towns Draft Programme (22 Mar 2026); consultation closed 19 May 2026; SEA published; final programme adoption expected later in 2026
  • Next milestone: Government to confirm final new town locations and adopt the programme, due later in 2026was: Final location confirmation

Source: GOV.UK (MHCLG) - New towns draft programme (consultation) →On the map →

Housing & Development · New Islington / Ancoats, Manchester (M4)

New Islington / Ancoats

  • Stage: Final phase (two blocks, 60 apartments) consented March 2020; Urban Splash discharging conditions, start targeted first half of 2026 (January 2026)was: Largely built out; final Urban Splash phase and This City blocks progressing
  • Next milestone: Start on site of Urban Splash's final 60-apartment New Islington phasewas: Start of Urban Splash's final New Islington phase

Source: Manchester City Council — developer/operator record · reported Place North West →On the map →

Housing & Development · Northstowe (near Longstanton), Cambridgeshire

Northstowe

  • Stage: Homes England and Vistry conditional contract agreed to deliver 1,000 homes in Phase 3B, adding to existing homes at Northstowewas: Under construction - phase 1 nearly complete, phases 2 & 3 commenced
  • Next milestone: First planning application expected before the end of 2026, building from 2027, first residents from 2028was: Vistry Phase 3B (1,000 homes): first planning application expected before the end of 2026, building from 2027, first residents from 2028

Source: Northstowe (Urban&Civic/Homes England) →On the map →

Housing & Development · Old Oak, around Old Oak Common station, west London

Old Oak (OPDC) £12bn regeneration, London

  • Stage: In procurement: OPDC search for joint venture development partner launched (May 2026)was: In procurement (JV partner search)
  • Value: c.£12bn development value (OPDC, May 2026)was: c.£12bn development value (OPDC partner search, May 2026)

Source: reporting OPDC procurement launch · reported BDC Magazine →On the map →

Housing & Development · Westenhanger, near Hythe/Folkestone, Kent

Otterpool Park

  • Stage: Awaiting formal planning sign-off pending Section 106; first 300-home phase planned near Westenhanger station (Jun 2026)was: Strategic infrastructure approved May 2026; first-homes location confirmed; housebuilding not started
  • Next milestone: Submission of replacement Section 106 agreement; planning committee hoped by end 2026was: New Section 106 agreement Sept 2026; committee decision by end 2026

Source: KentOnline - Confirmed: where and when construction of new Kent town is set to start →On the map →

Housing & Development · Plymouth / Devonport, Devon

Plymouth New Town (Devonport)

  • Stage: Not selected as a new town at this stage (23 Mar 2026); government to give Plymouth its own bespoke financial support package insteadwas: Not selected as a new town (gov.uk 22 Mar 2026); government instead offering Plymouth a bespoke housing and regeneration support package, with detail expected summer 2026; council and Homes England progressing a City Centre Vision targeting 10,000 homes
  • Next milestone: Detailed announcement of Plymouth's bespoke support package (promised summer 2026)was: Final location confirmation

Source: Plymouth City Council - Government backs Plymouth as priority for future housing and regeneration support →On the map →

Housing & Development · Poplar Riverside (Leven Road / Ailsa Street), LB Tower Hamlets, London E14

Poplar Riverside / Ailsa Wharf

  • Stage: 20-acre former gasworks being transformed into a mixed-use neighbourhood (Heron Wharf, Planning Permission of the Year 2020)was: Active construction and sales; Housing Zone build-out

Source: Berkeley Group →On the map →

Housing & Development · Purfleet-on-Thames, Thurrock, Essex (Thames Gateway)

Purfleet-on-Thames

  • Stage: Council proposed reviving scheme with Muse Places as preferred partner (cabinet report, Mar 2026); development agreement negotiations to followwas: Preferred developer appointed March 2026; negotiating development agreement
  • Next milestone: Development agreement to return to cabinet for approvalwas: Full development agreement with Muse Places

Source: Your Thurrock - Council set to resurrect Purfleet-on-Thames regeneration scheme →On the map →

Housing & Development · Royal Docks, LB Newham, East London E16

Royal Docks / Royal Albert Dock

  • Status: At tenderwas: Live
  • Stage: Royal Albert Dock Master Development Partner procurement under way; Mayor approved lease amendment recommendations 15 Apr 2026was: RAD main plot still in developer procurement; £113m funding (Jul 2026) unlocks office-to-student conversion; other Royal Docks plots progressing
  • Value: Not disclosedwas: £2bn+ (five-year plan)
  • Next milestone: Appointment of preferred Royal Albert Dock development partner, anticipated Autumn 2026was: Royal Albert Dock development partner appointment Autumn 2026

Source: Greater London Authority - MD3495 Royal Albert Dock lease amendments →On the map →

Housing & Development · North of the A40, near Eynsham, West Oxfordshire

Salt Cross Garden Village

  • Stage: Area Action Plan formally adopted by West Oxfordshire District Council on 25 Feb 2026was: Pre-construction / consenting - Area Action Plan adopted
  • Next milestone: Planning applications for the garden village, guided by the adopted Area Action Planwas: Submission of developer planning applications

Source: West Oxfordshire District Council - Salt Cross Garden Village (planning policy) →On the map →

Housing & Development · Sherford, south-east of Plymouth, Devon

Sherford

  • Stage: Under construction; Phase 3 homes being readied for occupation; Phase 3a/b service connection works 23 to 28 Oct 2026was: Under construction (Phase 3 underway)
  • Value: Not disclosedwas: ~£1bn total
  • Next milestone: Decision on Sherford Sports Pavilion reserved matters application (submitted Sep 2026)was: Continued Phase 3 delivery plus care home and local centre

Source: Sherford - Monthly update October →On the map →

Housing & Development · South Kilburn, LB Brent, London NW6

South Kilburn

  • Stage: Phased 15-year programme for 2,400 homes ongoing; single delivery partner due to launch June 2025 for remaining siteswas: Several phases complete/under construction; delivery partner procurement

Source: Brent Council →On the map →

Housing & Development · Southall (former gasworks), LB Ealing, West London UB2

Southall Waterside / The Green Quarter

  • Stage: Revised masterplan approved January 2026; more than 1,200 homes completedwas: Revised masterplan approved January 2026; Quarter Yards homes on sale
  • Value: Not disclosedwas: Over £1bn
  • Next milestone: Delivery of later phases under the revised masterplanwas: Quarter Yards homes due to complete in 2027

Source: Berkeley Group →On the map →

Housing & Development · Durdar / south Carlisle, Cumbria

St Cuthbert's Garden Village

  • Stage: Plan-making: draft Local Plan due for independent Government Examination later in 2026; Executive chose a Locally Led New Town Development Corporation as delivery vehicle (17 Feb 2026)was: Plan-making: St Cuthbert's Local Plan (Reg 19 draft Mar 2025) awaiting independent examination expected later in 2026 (adoption no longer expected July 2026); Locally Led New Town Development Corporation selected as preferred delivery vehicle Feb 2026, targeted operational summer 2027
  • Next milestone: Independent examination of the Local Plan; development corporation could be operational by summer 2027, subject to Secretary of State approval and an Act of Parliamentwas: Local plan adoption targeted July 2026

Source: Cumberland Council - Driving forward St Cuthbert's Garden Village, Carlisle →On the map →

Housing & Development · Stockport Town Centre West, Stockport

Stockport Mayoral Development Corporation (Town Centre West)

  • Stage: Parliament approved MDC expansion to 410 acres, Feb 2026; housing target raised to 8,000 homes by 2040; 1,200 homes complete or on sitewas: Several sites in construction; Stockport 8 consented; MDC expansion approved
  • Value: Not disclosedwas: £350m (Stockport 8)
  • Next milestone: About 1,500 homes due to start on site in 2026; Stockport 8 (1,300 homes) next major projectwas: Delivery of Stockport 8 and newly expanded MDC sites

Source: Place North West - Parliament approves Stockport MDC expansion →On the map →

Housing & Development · Tempsford, Central Bedfordshire

Tempsford New Town

  • Stage: One of seven proposed new towns in Draft New Towns Programme (23 Mar 2026; over 40,000 homes at Tempsford); consultation closed 19 May 2026was: Confirmed among government's seven priority new towns (Mar 2026, up to 40,000 homes); still pre-construction
  • Next milestone: Government decision on final new town locationswas: Final location confirmation following SEA

Source: GOV.UK (MHCLG) - New towns draft programme (consultation) →On the map →

Housing & Development · Colchester-Tendring border, east of Colchester, Essex

Tendring Colchester Borders Garden Community

  • Stage: Phase 1 of A1331 link road opened (reported 5 Oct 2026); hybrid application for up to 7,750 homes under considerationwas: Enabling infrastructure under construction/delivered: first phase of the A1331 link road (over one mile of new dual carriageway from a new A133 roundabout, with three junctions providing Garden Community access) opened on schedule 29 June 2026 after an 18-month build; Phase 2 (A133-A120, £65m confirmed Mar 2026) to complete by mid-2030; Rapid Transit System works underway; hybrid application for 7,750 homes validated 1 April 2026, decision expected Summer 2027
  • Value: Not disclosedwas: £65m Homes England funding for A1331 link road
  • Next milestone: Planning decision by TCBGC Joint Committee expected summer 2027was: Decision expected Summer 2027 by TCBGC Joint Committee

Source: Tendring Colchester Borders Garden Community - A1331 Link Road Milestone →On the map →

Housing & Development · Thamesmead, RB Greenwich (Thames riverside), London

Thamesmead Waterfront

  • Stage: Selected by Government as one of seven New Towns (March 2026)was: New Town designation secured; masterplanning / pre-construction
  • Value: Not disclosedwas: Circa £3.5bn+ (reported)
  • Next milestone: Community engagement and joint work with the GLA, TfL, Peabody and Lendlease; DLR extensionwas: Community engagement and DLR extension to unlock delivery

Source: Royal Borough of Greenwich →On the map →

Housing & Development · Trafford Waters, Barton (beside the Trafford Centre), Trafford

Trafford Waters

  • Stage: Under construction; 85-bed care home open; 83-home Pearson Place topped out 2025, due to complete early 2026was: Under construction; care home open; further phases in design
  • Next milestone: Plans for the next residential developments to be progressed in 2026was: Designs for the next residential phases being progressed in 2026; no planning decision date published as of October 2026

Source: Peel Waters →On the map →

Housing & Development · Former Deenethorpe Airfield, near Corby, North Northamptonshire

Tresham Garden Village

  • Stage: Updated Masterplan and Delivery Strategy agreed July 2019; planning application delayed pending viability workwas: Pre-application; Masterplan & Delivery Strategy approved 2019
  • Next milestone: Submission of a planning applicationwas: Submission of outline planning application

Source: North Northamptonshire Council (Tresham Garden Village) →On the map →

Housing & Development · Collyhurst / Red Bank, north Manchester

Victoria North, Manchester

  • Stage: In construction (phased); Collyhurst Phase 1: 35 of 274 homes completedwas: In construction (phased)
  • Value: Not disclosedwas: £4bn programme (FEC / Manchester City Council)
  • Next milestone: Collyhurst Phase 1 completions through 2026; detailed design and planning for c.550-home Phase 2 to follow consultationwas: Collyhurst Phase 1 completions through 2026; Phase 2 planning submission after consultation

Source: Manchester City Council →On the map →

Housing & Development · North of Waterbeach (former barracks), Cambridgeshire

Waterbeach New Town

  • Stage: Western parcel first phase of infrastructure works under way (outline Sep 2019); eastern parcel outline consent Dec 2024was: Western parcel under construction; eastern parcel has outline consent
  • Next milestone: Planning application for relocated Waterbeach stationwas: Relocation of Waterbeach railway station; reserved-matters

Source: Greater Cambridge Shared Planning - Waterbeach New Town →On the map →

Housing & Development · Welborne, north of Fareham, Hampshire

Welborne Garden Village

  • Stage: M27 J10 improvement scheme for Welborne opening in phases ahead of schedule, first phase from 14 Sep 2026 (Hampshire CC, 3 Sep 2026); occupation capped at 1,160 homes until J10 is fully operationalwas: First phase approved and under construction; M27 J10 works underway
  • Next milestone: J10 eastbound and westbound on-slips to open in autumn 2026, giving full M27 accesswas: Improved M27 junction 10 due to open in 2026; no exact date published as of October 2026

Source: Hampshire County Council - Mid-September phased opening for M27 J10 improvement scheme →On the map →

Housing & Development · Wembley Park, LB Brent, London

Wembley Park

  • Stage: 85-acre estate; reserved matters application for Plot NW04 (358-bed hotel and civic square) submitted June 2026was: Multiple plots complete and occupied; development ongoing
  • Next milestone: Brent Council decision on NW04 expected towards the end of 2026was: NW04 planning decision expected by end of 2026

Source: Quintain Ltd →On the map →

Housing & Development · Worcestershire Parkway (near Norton), Wychavon, Worcestershire

Worcestershire Parkway New Town

  • Stage: Not selected: 'Wychavon Town' (10,000-15,000 homes) listed as one of six reasonable alternatives in the New Towns Draft Programme (23 Mar 2026), not taken forward as a proposed new townwas: Dropped from the government's new towns programme: 'Wychavon Town' was among the six Taskforce locations not taken forward in the New Towns Draft Programme (22 Mar 2026), retained only as a 'reasonable alternative'; Wychavon District Council and promoter Summix have said they intend to press on with plans for the settlement outside the national programme
  • Next milestone: Government to confirm final new town locations and adopt the programme, due later in 2026was: Final location confirmation

Source: GOV.UK - New Towns Draft Programme (consultation) →On the map →

Hydrogen · Aldbrough gas storage site, ~2.5 km SE of Aldbrough village, East Riding of Yorkshire, England

Aldbrough Hydrogen Pathfinder

  • Stage: Consented (planning consent granted May 2025); shortlisted in HAR2 and in due diligence with DESNZwas: Consented (planning granted May 2025); HAR2 due-diligence with DESNZ

Source: SSE Thermal →On the map →

Hydrogen · Bardon Hill, Coalville, Leicestershire, England

Bardon Hill Hydrogen (Hygen)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Barrow-in-Furness, Cumbria, England

Barrow Green Hydrogen (Carlton Power)

  • Stage: Final investment decision reached (May 2026); moving from award into executionwas: Final investment decision reached (May 2026); construction phase
  • Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed

Source: Plug Power / Carlton Power →On the map →

Hydrogen · Binn Ecopark, near Glenfarg, Perth & Kinross, Scotland

Binn Ecopark Hydrogen Facility

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Bradford, West Yorkshire, England

Bradford Low Carbon Hydrogen

  • Status: Pipelinewas: Live
  • Stage: HAR1 contract signed (July 2025); site development continuingwas: In construction / financial close reached (2025)
  • Value: Not disclosedwas: HAR1 revenue support (Low Carbon Hydrogen Agreement); per-project value undisclosed
  • Next milestone: Financial close and start of constructionwas: Complete construction and commission (2026–2027)

Source: GOV.UK – Jobs unlocked as first wave of hydrogen projects sign contracts (Jul 2025) →On the map →

Hydrogen · Creca, near Annan, Dumfries & Galloway, Scotland

Creca Hydrogen Facility (Green Cat)

  • Next milestone: HAR2 due diligence and funding decisionwas: Planning decision by Dumfries and Galloway Council; HAR2 due diligence toward a Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · NE England to Humber & East Midlands

East Coast Hydrogen network

  • Next milestone: The energy regulator Ofgem is paying for the detailed design and early planning work (as of November 2026). In June 2025, National Gas said it aims to have the first hydrogen flowing in the early 2030s.was: Feasibility/engineering; alignment with Project Union

Source: East Coast Hydrogen →On the map →

Hydrogen · Fawley, Hampshire, England

Fawley Green Hydrogen (Hynamics / EDF)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Grangemouth, Falkirk, Scotland

Grangemouth Green Hydrogen (RWE)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Northfleet, Kent, England

Green Hydrogen 3 (HYRO, Northfleet)

  • Stage: HAR1-funded; ITM Power contracted Dec 2025 to supply 12.5 MW electrolyser systems for HYRO's project at Kimberly-Clark's Northfleet plant, Gravesendwas: Enabling works complete; full construction from April 2026
  • Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
  • Next milestone: Construction and commissioning; operational by end of 2027was: Complete construction and commission

Source: ITM Power - 12.5 MW contract with Octopus Energy Generation →On the map →

Hydrogen · St Helens, Merseyside, England

Grenian Hydrogen St Helens

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Buckhaven and Denbeath, Levenmouth, Fife, Scotland

H100 Fife green hydrogen network (SGN)

  • Stage: Site fully built, power connected and testing under way (5 October 2026); no hydrogen production yetwas: Network and production site built; site testing under way; no homes yet on hydrogen
  • Value: Not disclosedwas: Ofgem-funded (network innovation); total not fully disclosed

Source: SGN — H100 Fife →On the map →

Hydrogen · Harper Lane, Radlett/Shenley, Hertfordshire, England

Harper Lane Hydrogen (Hygen)

  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Hartlebury, Worcestershire, England

Hartlebury Green Hydrogen (Carlton Power)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · South Killingholme, North Lincolnshire, England

Humber H2ub (Uniper, Killingholme)

  • Stage: HAR2 shortlisted (7 Apr 2025); still listed on the government shortlist pagewas: HAR2 shortlisted; planning permission granted Mar 2026; ITM selected for 120MW electrolyser; FID conditional on HAR2 contract
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and contract decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK - Hydrogen Allocation Round 2 (HAR2): shortlisted projects →On the map →

Hydrogen · Bridgend, Wales

HyBont (Hygen, Bridgend)

  • Stage: Development; acquired by Hygen (January 2026), concluding the HAR1 contract signature processwas: Development (acquired by Hygen Jan 2026, HAR1 contract signature concluded)
  • Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
  • Next milestone: Detailed feasibility study of the sitewas: Detailed site feasibility study, then financial close

Source: Hygen Energy, H2 Tech →On the map →

Hydrogen · Kemsley, near Sittingbourne, Kent, England

Lhyfe Kemsley Green Hydrogen

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Wallsend, North Tyneside, England

Lhyfe Wallsend Green Hydrogen

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Magor, Monmouthshire, Wales

Magor Net Zero Hydrogen

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Pembroke, Pembrokeshire, Wales

Pembroke Green Hydrogen 1 (RWE)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Teesside → Humber → East Midlands

Project Union: East Coast (National Gas)

  • Status: Pipelinewas: Live
  • Stage: Front end engineering and design (two-year FEED programme); surveys underway on the Humber Section; DCO application(s) to followwas: Front end engineering design (FEED); DCO consenting to follow
  • Value: £57m FEED funding (Ofgem, 2025/26 prices)was: £164m development funding

Source: National Gas →On the map →

Hydrogen · St Austell, Cornwall, England

St Austell Green Hydrogen (Four Zeros)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Strathallan, near Auchterarder, Perth & Kinross, Scotland

Strathallan Hydrogen Facility

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Redcar / Teesside, England

Tees Green Hydrogen Phase 2 (EDF)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Teesside, England

Teesside Green Hydrogen (MorGen Energy)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Tyseley, Birmingham, West Midlands, England

Tyseley 10MW Green Hydrogen (Motive Fuels)

  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Walsall, West Midlands, England

Walsall Green Hydrogen (Carlton Power)

  • Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
  • Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
  • Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement

Source: GOV.UK – HAR2 shortlisted projects →On the map →

Hydrogen · Milford Haven, Pembrokeshire, Wales

West Wales Hydrogen (Milford Haven)

  • Status: Pipelinewas: Live
  • Stage: Final investment decision reached (11 March 2026); construction expected to begin in 2026was: Final investment decision March 2026; construction expected in 2026
  • Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
  • Next milestone: Commissioning by early 2028was: Commissioning expected by early 2028

Source: Trafigura press release (March 2026) →On the map →

Nuclear · Somerset

Hinkley Point C

  • Stage: In construction (second reactor lifted into place, June 2026; fish return tunnel dig finished, October 2026)was: In construction (Unit 1 fit-out under way; Unit 1 expected online 2030)
  • Value: Not disclosedwas: £35bn estimated cost (EDF results, February 2026); CfD £92.50/MWh (2012 prices)
  • Next milestone: Construction continueswas: Unit 1 expected to come online in 2030 (EDF, February 2026)

Source: EDF Hinkley Point C / New Civil Engineer (Feb 2026) →On the map →

Nuclear · Suffolk

Sizewell C

  • Stage: In construction (two years since formal construction began, January 2026)was: In construction (major civils; two years into construction, January 2026)
  • Next milestone: First trains to site and new public visitor centre in 2026was: Civil engineering programme continues; first trains to site and visitor centre opening in 2026

Source: Sizewell C Ltd →On the map →

Power & Grid · Beauly (near Inverness) - Blackhillock (Moray) - New Deer - Peterhead (Aberdeenshire)

Beauly to Blackhillock to New Deer to Peterhead 400kV

  • Stage: Consenting; Section 37 application referred to a public local inquiry after Highland and Moray council objections; inquiry sessions scheduled 18 to 27 August 2026was: Consenting; Section 37 application (October 2025) at public inquiry after council objections

Source: Highland Council / SSEN Transmission →On the map →

Power & Grid · Bramford (Suffolk) to Twinstead (Essex), via the Stour Valley

Bramford to Twinstead Reinforcement

  • Stage: Consent granted September 2024; main construction compound set-up begun near Leavenheathwas: In construction
  • Next milestone: Overhead line construction by Balfour Beatty, then underground cable workswas: Main construction along the route, programmed by National Grid for 2026 to 2029

Source: National Grid - Bramford to Twinstead →On the map →

Power & Grid · Brinsworth (South Yorkshire) - Chesterfield - High Marnham (Nottinghamshire)

Brinsworth to High Marnham Uprating

  • Stage: Consented; planning permission granted for all three substations (High Marnham June 2026, Long Lane and near Chesterfield July 2026)was: Consented - planning permission granted for all three substations
  • Next milestone: Start of construction; no dates publishedwas: Start of substation construction; no dates published

Source: National Grid news release, 24 August 2026 →On the map →

Power & Grid · Ballyadam converter station, Carrigtwohill, Co. Cork (subsea to Brittany, France)

Celtic Interconnector

  • Stage: In construction (Step 6); HVDC subsea cable burial and protection in Irish waters completed (Sep 2026)was: In construction (Step 6); AC route complete, DC route Phase 2 ~70%; commissioning now expected spring 2028
  • Value: Not disclosed (€530.7m EU Connecting Europe Facility grant awarded)was: ≈€1bn+ project, incl. €530.7m EU Connecting Europe Facility grant (EirGrid)
  • Next milestone: Commissioning expected Q4 2028was: Energisation revised to spring 2028; remaining subsea cable installation through 2026-27

Source: EirGrid - Celtic Interconnector →On the map →

Power & Grid · New Creag Dhubh substation to Glen Lochy near Dalmally, Argyll

Creag Dhubh to Dalmally 275kV Overhead Line

  • Stage: In construction; first of 47 towers assembled, Creag Dhubh substation construction reaching the halfway markwas: In construction
  • Next milestone: Electrical installation work at the substation by Siemens Energy; continued tower assembly along the 13.3 km routewas: Transformer installation and commissioning at Creag Dhubh substation; erection of the remaining towers on the 47-tower, 13.3km route

Source: SSEN Transmission - First tower completed on Creag Dhubh-Dalmally →On the map →

Power & Grid · Creag Dhubh (near Dalmally) to Inveraray, Argyll & Bute

Creag Dhubh to Inveraray 275kV Overhead Line

  • Stage: In construction; first steel lattice tower assembled, over 4km of access tracks built (Mar 2026)was: In construction (first tower erected Mar 2026)
  • Next milestone: Complete tower assembly along the route, then commissioning (date not published)was: Tower erection and stringing ongoing across the Argyll & Kintyre reinforcement

Source: SSEN Transmission - First tower erected on new Creag Dhubh - Inveraray line →On the map →

Power & Grid · Bonnybridge - Cumbernauld - Wishaw corridor, Falkirk & North Lanarkshire

Denny to Wishaw Network Upgrade

  • Stage: Consenting; three Section 37 applications submitted to Scottish Ministers, plus Cumbernauld substation extension planning application to North Lanarkshire Council (page dated 26 Jun 2026)was: Consultation complete (final information events Feb 2026); preparing to submit consent applications
  • Next milestone: Determination of Section 37 and planning applicationswas: EIA / Section 37 consent application

Source: SP Energy Networks - Denny to Wishaw Latest News →On the map →

Power & Grid · Torness/Branxton, East Lothian to Hawthorn Pit, County Durham

Eastern Green Link 1

  • Stage: Under construction; main foundation piling complete at Murton converter station and Hawthorn Pit substation (Sep 2026)was: In construction
  • Value: Not disclosedwas: £2.5bn (Ofgem-approved funding, Nov 2024)
  • Next milestone: Next phase of construction at both siteswas: Full operation targeted 2029

Source: Eastern Green Link 1 - Main foundation piling works completed →On the map →

Power & Grid · Westfield converter station, near Ballingry, Fife (Scotland) to Norfolk (England)

Eastern Green Link 4 (EGL4)

  • Status: Pipelinewas: At tender
  • Stage: Consenting; Fife Council planning applications submitted Dec 2025; EGL4 CPO 2026 made, awaiting confirmationwas: Pre-application / consenting; DCO submission targeted Aug 2026 (Ofgem investment approval Dec 2025, supply-chain contracts signed, but construction not started)
  • Value: Not disclosedwas: ~£3bn total EGL4 contracts awarded (2026)

Source: SP Energy Networks - Eastern Green Link 4 →On the map →

Power & Grid · Grimsby West substation (NE Lincolnshire) to Walpole (Norfolk)

Grimsby to Walpole

  • Stage: Pre-application; Stage 2 consultation held 11 June to 6 August 2025was: Pre-application (post Stage 2 and targeted consultation)
  • Next milestone: DCO application expected summer 2027; decision expected 2028; construction 2029, fully operational 2033was: DCO application planned for summer 2027; decision expected 2028; construction 2029 to 2033

Source: National Grid - Grimsby to Walpole →On the map →

Power & Grid · Shurton/Bridgwater (Somerset) to Seabank, Avonmouth (South Gloucestershire)

Hinkley Connection Project

  • Stage: Northern section energised; land restoration under way; 13 T-pylons still to be energisedwas: In construction - final energisation and restoration
  • Next milestone: Energising remaining T-pylons via planned outages at Huntspillwas: Energising remaining 13 T-pylons via planned Huntspill outages

Source: National Grid - Hinkley Connection Project →On the map →

Power & Grid · Between Kendoon and Tongland, Dumfries & Galloway

Kendoon to Tongland Reinforcement (KTR)

  • Stage: Consent granted by Scottish Ministers (Feb 2025)was: Section 37 consent GRANTED by Scottish Ministers Feb 2025 - pre-construction / delivery preparation
  • Next milestone: Start of construction (date not published)was: Scottish Ministers' consent decision

Source: SP Energy Networks - KTR Latest News →On the map →

Power & Grid · Dunstown substation, Co. Kildare to Woodland substation, Co. Meath

Kildare-Meath Grid Upgrade (Woodland-Dunstown)

  • Stage: Step 6: construction, energisation and benefit sharing; planning permission granted by An Bord Pleanála in March 2025was: Construction, energisation and benefit sharing
  • Next milestone: Ongoing construction; community benefit fund consultation with local groupswas: Ongoing construction; community benefit fund consultations

Source: EirGrid - Kildare-Meath Grid Upgrade →On the map →

Power & Grid · New Coolnabacky 400/110kV substation, near Portlaoise, Co. Laois

Laois-Kilkenny Reinforcement

  • Stage: Step 6: construction, energisation and benefit sharing; 110kV GIS commissioning ongoing and 400kV GIS electrical installation under way at Coolnabacky (March 2026 update)was: Construction and energisation

Source: EirGrid - Laois Kilkenny Reinforcement →On the map →

Power & Grid · Walberswick, Suffolk landfall (multi-purpose interconnector to the Netherlands)

LionLink

  • Stage: Consultation closed (March 2026 update)was: Pre-application - statutory consultation held Jan 2026; DCO not yet submitted
  • Next milestone: Application for development consent (no date published)was: DCO application expected 2026; operational target 2032

Source: National Grid Ventures - LionLink: About →On the map →

Power & Grid · Kilroot, Co. Antrim (near Carrickfergus) to Hunterston, Ayrshire

LirIC (Northern Ireland to Scotland)

  • Stage: Development; Ofgem cap and floor award in principle, Northern Ireland transmission licence granted in 2024was: Development (licensing / consenting pre-construction)
  • Next milestone: Consents and construction; commissioning targeted for 2032was: Progress toward final consents; targeting commissioning 2032

Source: Transmission Investment - LirIC →On the map →

Power & Grid · Greater Dublin Area (Ireland) to Bodelwyddan, Denbighshire (North Wales)

MaresConnect

  • Stage: Development; proposed interconnector, Irish converter station location under technical reviewwas: Consenting / development (Ofgem licence granted)
  • Value: €860m (stated private capital investment)was: €860m (stated investment)
  • Next milestone: Finalisation of Irish converter station siting; consent submissionswas: Finalisation of Irish converter siting; consent submissions

Source: MaresConnect Interconnector →On the map →

Power & Grid · Isle of Grain, Kent (UK) to Wilhelmshaven, Lower Saxony (Germany)

NeuConnect (Great Britain to Germany)

  • Stage: In construction; offshore cabling works continuing between the UK and Germany (2025 to 2026 milestone)was: Construction (cabling and converter installation)
  • Value: Not disclosedwas: £2.4bn / €2.8bn (stated investment)
  • Next milestone: System-wide testing, commissioning and trial operations begin 2027; commercial operations 2028was: Testing and commissioning begins 2027; commercial operation 2028

Source: NeuConnect Interconnector →On the map →

Power & Grid · Ballina, Co. Mayo to Ballaghaderreen, Co. Roscommon

North Connacht 110kV Project

  • Stage: Step 6: construction, energisation and benefit sharing; main underground cabling contract awarded and construction begunwas: Construction (main works underway)
  • Next milestone: Substation and overhead line works due to conclude in 2026; main underground cabling to conclude in 2028was: Main construction to conclude in 2028, substation and overhead line works in 2026

Source: EirGrid - North Connacht 110kV Project →On the map →

Power & Grid · Birkhill Wood (near Hull, East Yorkshire) to High Marnham (Nottinghamshire)

North Humber to High Marnham

  • Stage: DCO application received 16 October 2026; acceptance decision due by 13 November 2026was: Pre-application (pre-DCO)
  • Next milestone: Planning Inspectorate decision on accepting the application for examinationwas: DCO application submission expected later in 2026, construction from 2028 if consented, fully operational 2031

Source: Planning Inspectorate (EN020034), National Grid →On the map →

Power & Grid · Pelham-Rye House-Waltham Cross-Brimsdown-Tottenham-Hackney (Hertfordshire and North London)

North London Reinforcement

  • Stage: In construction; reconductoring ongoing on all five sections, enabling works complete from Waltham Cross to Hackneywas: In construction
  • Next milestone: Completion of reconductoring and demobilisation (dates TBC)was: Main construction 2026 to 2029, testing and commissioning 2029 to 2030, fully operational from 2030

Source: National Grid - North London Reinforcement →On the map →

Power & Grid · Woodland substation, Co. Meath to Turleenan, Co. Tyrone

North-South Interconnector

  • Stage: Step 6: construction, energisation and benefit sharing; full planning consent in Ireland and Northern Irelandwas: Construction, energisation and benefit sharing
  • Next milestone: Landowner agreements under the revised compensation proposal issued in March 2026, and access arrangements for constructionwas: Landowner access/compensation agreements ahead of main civil works

Source: EirGrid - North South 400kV Interconnector →On the map →

Power & Grid · Norfolk–Suffolk–Essex

Norwich to Tilbury

  • Status: Pipelinewas: At tender
  • Stage: Examination closed; recommendation stage in progresswas: In examination — examination closed 10 Aug 2026
  • Value: Not disclosedwas: Multi-billion (corpus: gap-11)
  • Next milestone: Examining Authority recommendation due by 10 November 2026; Secretary of State decision within three months of receiving itwas: Examining Authority recommendation due within three months of the 10 Aug 2026 close; Secretary of State (DESNZ) decision a further three months after that. No decision date has been published.

Source: Planning Inspectorate EN020027; Diss Mercury (Aug 2026) →On the map →

Power & Grid · Finstown, Orkney to Dounreay West, Caithness (via the Pentland Firth)

Orkney Link (Orkney to Caithness 220kV Subsea Connection)

  • Stage: In construction; full delivery across multiple sites, Warebeth landfall drilling complete and Finstown foundation pours completewas: In construction (year 2 of delivery)
  • Next milestone: Erection of remaining building frames at Finstown and installation of the underground land cablewas: Onshore cable pulling and jointing from autumn 2026, Finstown to Warebeth installation due 2027, energisation targeted for 2028

Source: SSEN Transmission - One year of delivery on Orkney Link →On the map →

Power & Grid · Pentir to Trawsfynydd, Gwynedd/Eryri (Snowdonia), North Wales; Glaslyn Estuary crossing at Porthmadog

Pentir to Trawsfynydd Reinforcement

  • Stage: Trawsfynydd substation works approved subject to conditions by Eryri National Park Authority (15 Jul 2026)was: Planning applications submitted; Pentir Substation cables approved by Cyngor Gwynedd, remaining applications awaiting LPA decisions; DESNZ consent application still to come 2026
  • Next milestone: Remaining planning decisions; construction startwas: Planning decisions; construction due to begin summer 2026; operational by 2030

Source: Public Notice Portal - Eryri National Park Authority decision NP5/73/287V →On the map →

Power & Grid · Dublin (incl. Dublin Bay marine section)

Powering Up Dublin — Carrickmines–Poolbeg

  • Status: Pipelinewas: At tender
  • Stage: Consenting; onshore planning application submitted to Dún Laoghaire-Rathdown County Council; marine surveys in Dublin Bay from spring 2026 to summer 2027was: In procurement and consenting (planning application due by autumn 2026)
  • Next milestone: Planning decision on the onshore section; offshore licences and planning permission for the Dublin Bay sectionwas: Onshore construction contract award and planning application to Dún Laoghaire-Rathdown County Council, 2026

Source: EirGrid — Powering Up Dublin →On the map →

Power & Grid · Dublin, Ireland

Powering Up Dublin — Finglas–North Wall

  • Status: Pipelinewas: Live
  • Stage: Best Performing Option for the route published (January 2025); community benefit fund being establishedwas: Construction commencing 2026
  • Next milestone: Planning consent and constructionwas: Inchicore–Poolbeg micro-tunnel route consultation 2026

Source: EirGrid — Powering Up Dublin →On the map →

Power & Grid · Tonn Nua / Maritime Area A off Cork, Waterford & Wexford; landfall options at Garryvoe (Cork)

Powering Up Offshore - South Coast

  • Stage: Step 4: location determination; Step 4a 12-week consultation on landfall and route options running 15 September to 8 Decemberwas: Location determination; Step 4a consultation on emerging best performing options open 15 September to 8 December 2026
  • Next milestone: Step 4a consultation closes 8 December; project update with survey outcomes planned for autumn 2026was: The Step 4a consultation closes on 8 December 2026.

Source: EirGrid - Powering Up Offshore South Coast →On the map →

Power & Grid · Sizewell area (Suffolk) to Richborough / Minster Marshes (Kent)

Sea Link

  • Stage: Development consent granted by the Secretary of State on 30 October 2026was: Recommendation with Secretary of State; decision due 30 October 2026
  • Next milestone: Construction startwas: Secretary of State decision due by 30 October 2026

Source: Planning Inspectorate - Sea Link (EN020026) →On the map →

Power & Grid · Fort Augustus to Skye (Edinbane, Broadford, Ardmore)

Skye Reinforcement

  • Status: Pipelinewas: Live
  • Stage: Consented; Section 37 consent granted by the Scottish Government, project moving to the delivery phasewas: Consented (Jun 2025) - mobilising into construction
  • Value: Not disclosedwas: ~£690m (reported by New Civil Engineer)
  • Next milestone: Delivery, including replacement of Broadford and Edinbane substationswas: Main construction ramp-up; Broadford/Edinbane substation works

Source: SSEN Transmission - Skye upgrade granted consent →On the map →

Power & Grid · Spittal (Caithness) - Loch Buidhe (Sutherland) - Beauly (Highland)

Spittal to Loch Buidhe to Beauly 400kV

  • Stage: Consenting; Section 37 application (ECU00006008, received 14 Aug 2025) referred to DPEAwas: Consenting - Section 37 application under consideration (ECU00006008, received 14 Aug 2025); public local inquiry reported
  • Next milestone: DPEA process and report, then Scottish Ministers' decisionwas: Ministerial determination (within 52 weeks of submission)

Source: Scottish Government Energy Consents Unit - Spittal to Loch Buidhe to Beauly 400 kV OHL Connection →On the map →

Power & Grid · Landfall south of Harwich with converter east of Ardleigh, Essex (UK) to Niederlangen, Germany

Tarchon (Great Britain to Germany)

  • Stage: Pre-application with the Planning Inspectorate (applicant Tarchon Energy Limited)was: Pre-application / consenting; non-statutory consultation 3 Jul-13 Aug 2026 ahead of DCO
  • Next milestone: DCO application expected July 2028was: Summer 2026 non-statutory consultation; DCO application ~Jan 2028

Source: Planning Inspectorate - Tarchon Interconnector (EN0210009) →On the map →

Power & Grid · Tealing (near Dundee) to Kincardine, via a new Conland substation near Glenrothes, Fife

Tealing to Kincardine Upgrade Project (TKUP)

  • Stage: Consenting in parts; Westfield applications with Fife Council (Dec 2025); Conland application in preparation; Mossmorran consultation closed 17 Jul 2026was: Post-consultation - EIA and planning applications in preparation
  • Next milestone: Conland and Mossmorran planning applications; Section 37 applications for overhead line changeswas: EIA and planning / Section 37 applications

Source: SP Energy Networks - Tealing to Kincardine Upgrade Project →On the map →

Power & Grid · Kilmarnock South substation to Monkton/Grangestone, Ayrshire (subsea HVDC to Wales)

Western Link 2 (WL2)

  • Stage: Development; consultation on initial preferred routes closed 28 November 2025, detailed plans being prepared ahead of planning submissionwas: Detailed design / pre-planning
  • Next milestone: Planning permission in principle applications to East Ayrshire and South Ayrshire councils; construction anticipated to start in 2030was: Planning-permission-in-principle applications to Ayrshire councils (construction targeted ~2030)

Source: SP Energy Networks - Western Link 2 →On the map →

Power & Grid · Shipton (near York) to Monk Fryston, plus Osbaldwick substation, North/West Yorkshire

Yorkshire GREEN (Green Energy Enablement)

  • Stage: Preparatory works began in autumn 2024was: In construction
  • Value: Not disclosedwas: ~£524m (reported by T&D World)
  • Next milestone: Construction completion expected by 2028was: Completion targeted by 2028

Source: National Grid - Yorkshire GREEN →On the map →

Rail · Old Oak Common, west London (London–Birmingham route)

HS2 Phase One (Old Oak Common–Birmingham, Euston tunnel)

  • Stage: In construction (tunnelling machines working towards Euston; government reset, May 2026)was: In construction
  • Value: £87.7bn to £102.7bn revised estimate (May 2026)was: £87.7bn–£102.7bn revised estimate (DfT reset, May 2026)
  • Next milestone: First services Old Oak Common to Birmingham Curzon Street between 2036 and 2039was: Euston tunnel drives continue through 2026; first services Old Oak Common–Curzon Street 2036–2039

Source: Department for Transport (GOV.UK) / HS2 Ltd →On the map →

Rail · Huddersfield, West Yorkshire (York–Manchester route)

Transpennine Route Upgrade

  • Stage: In construction (track, signalling and Huddersfield station works; Huddersfield closed 19 September to 4 October 2026)was: In construction
  • Value: Not disclosedwas: up to £11.5bn reported programme envelope (DfT/Network Rail; £100m TRU programme partner let 2026)
  • Next milestone: 38-day Huddersfield station closure, reopening Monday 1 February 2027; main Huddersfield station upgrades due by early 2027was: 38-day Huddersfield station closure from 24 December 2026 to 31 January 2027, reopening 1 February 2027; Huddersfield station upgrade completes early 2027

Source: Network Rail Media Centre →On the map →

Renewables · Firth of Forth

Berwick Bank

  • Status: Pipelinewas: At tender
  • Stage: Offshore array consented (July 2025); 20-year CfD secured for Berwick Bank B (1.4GW) in AR7 (January 2026)was: Consented + CfD secured — pre-construction
  • Value: Not disclosedwas: Multi-billion
  • Next milestone: Final investment decision on Berwick Bank B expected in 2027was: FID expected 2027 (SSE, 14 January 2026)

Source: SSE (Jan 2026) / Fugro (May 2026) →On the map →

Renewables · Celtic Sea (off S Wales / SW England)

Celtic Sea Round 5 — Ocean Winds PDA

  • Status: Pipelinewas: At tender
  • Stage: Agreement for lease entered with The Crown Estate (announced 3 March 2026)was: Agreement for lease signed Mar 2026
  • Value: Round could deliver £1.4bn boost to UK economywas: Round could add £1.4bn to UK economy
  • Next milestone: Site surveys, environmental impact assessment, public engagement and planning consentswas: Development/consenting phase

Source: The Crown Estate / Find a Tender ocds-h6vhtk-05e3e2 →On the map →

Renewables · Off Yorkshire (base: Port of Nigg)

Dogger Bank C

  • Stage: In construction; Dogger Bank B turbine installation ongoing, C offshore installation due to begin 2027 (Aug 2026)was: In construction (foundations complete; turbine installation to follow Dogger Bank B)
  • Value: Part of £9bn complexwas: Part of ~£11bn complex
  • Next milestone: Dogger Bank C offshore installation begins 2027; wind farm complete mid-2028was: Dogger Bank B turbine installation to around Q2 2027; Dogger Bank C turbines to follow

Source: Dogger Bank Wind Farm - Up to 180 new offshore wind jobs created at Scotland's Maraen Port of Nigg →On the map →

Renewables · North Sea, c.100-150km off the Yorkshire/NE England coast (offshore array)

Dogger Bank South (East & West)

  • Status: Pipelinewas: At tender
  • Stage: Development consent granted for both projects (14 May 2026); CfDs secured in AR7 (January 2026); pre-FIDwas: Consented, CfD secured, pre-FID
  • Value: Not disclosedwas: Multi-£bn; AR7 CfDs at £91.20/MWh, 2024 prices (gov.uk AR7 results)

Source: RWE; DESNZ (Contracts for Difference Allocation Round 7 results) →On the map →

Renewables · Off Suffolk (array sits just beyond map edge; pin at its western extent)

East Anglia THREE

  • Stage: In construction; all 95 foundations installed, turbine installation under way (August 2026)was: In construction — all 95 foundations in (Aug 2026)
  • Next milestone: Turbine installation completion; fully operational by end of 2026was: Turbine installation completion; commercial operations target Q4 2026

Source: offshorewind.biz (17 Aug 2026) / Iberdrola →On the map →

Renewables · Near Sutton-on-Trent / Tuxford, Newark area, Nottinghamshire

Great North Road Solar and Biodiversity Park

  • Stage: Approved by the Energy Secretary on 27 October 2026was: Examination closed (28 April 2026); awaiting Examining Authority recommendation and Secretary of State decision
  • Next milestone: As of November 2026, the Planning Inspectorate lists the project as past the decision stage, with no date yet for building work to start.was: Close of examination, then recommendation to Secretary of State

Source: Planning Inspectorate (EN010162) →On the map →

Renewables · Off Arbroath, Angus (onshore: Cockenzie)

Inch Cape

  • Stage: In construction: monopile and transition piece installation complete; second export cable installed, final rock placement to come (Sep 2026)was: In construction — cables complete
  • Value: Not disclosedwas: ≈£3.5bn (confirm at cycle)
  • Next milestone: First power expected end of 2026; full commercial operation 2027was: First power late 2026; full operations 2027

Source: Inch Cape - Inch Cape successfully completes second offshore export cable →On the map →

Renewables · North Sea, c.50-80km off the Norfolk coast (offshore array)

Norfolk Vanguard (East & West)

  • Status: Pipelinewas: At tender
  • Stage: CfDs secured in Allocation Round 7 for Norfolk Vanguard East and Westwas: CfD secured — pre-construction
  • Value: AR7 CfDs at £91.20/MWh (2024 prices)was: Multi-£bn; AR7 CfDs at £91.20/MWh, 2024 prices (gov.uk AR7 results)
  • Next milestone: First CfD delivery year 2028/29 (East Unit A 2029/30)was: First CfD delivery year 2028/29

Source: DESNZ — Contracts for Difference Allocation Round 7 results →On the map →

Renewables · Off Waterford, Ireland

Tonn Nua (Helvic Head)

  • Status: Pipelinewas: At tender
  • Stage: Provisional winner of the State's second offshore wind auction (Helvick Head Offshore Wind DAC, ESB and Ørsted), November 2025was: Awarded — pre-development
  • Next milestone: Maritime Area Consent and development consentwas: Maritime Area Consent under determination by MARA (report recommending approval dated 5 March 2026), then development consent under the SC DMAP regime; construction expected from 2032

Source: gov.ie (9 Dec 2025) · MARA MAC report (5 Mar 2026) →On the map →

Storage · Loch Lochy, Great Glen, Highland

Coire Glas (SSE)

  • Status: Pipelinewas: At tender
  • Stage: In development; included on Ofgem's cap and floor minded-to list (June 2026); pre-FIDwas: Cap-and-floor minded-to — pre-FID
  • Value: Not disclosedwas: Over £1.5bn capital investment to construct (SSE)
  • Next milestone: Ofgem final cap and floor decision, then SSE final investment decision (no dates published)was: Ofgem Window 1 final decision expected autumn 2026, then SSE FID. No FID date has been published.

Source: SSE Renewables / Ofgem LDES Window 1 (26 Jun 2026) →On the map →

Storage · Silvermines, Co. Tipperary, Ireland

Silvermines Hydro (SIGA)

  • Status: Pipelinewas: At tender
  • Stage: In permit granting procedure (ABP permit granting process notification 27 Feb 2025); draft Concept for Public Participation 2nd edition Sep 2026was: Pre-application — An Coimisiún Pleanála case due to be decided by 24 Sep 2026
  • Value: Not disclosedwas: Not verified — see conflict note
  • Next milestone: Statutory permit application to An Coimisiún Pleanálawas: An Coimisiún Pleanála pre-application decision, reported as due by 24 Sep 2026

Source: Silvermines Hydro - Permit granting documents →On the map →

Transport · River Thames east of Gravesend (Kent) and Tilbury (Essex)

Lower Thames Crossing

  • Status: Pipelinewas: At tender
  • Stage: Tunnels delivery partner appointed (Bouygues Travaux Publics and Murphy joint venture); tunnelling machine selected; construction to begin in 2026was: Spared in the July 2026 spending cuts; enabling works under way; tunnel-boring machine contractor appointed July 2026; tunnelling from autumn 2028
  • Value: Not disclosedwas: c.£9bn–£10bn reported estimate (DfT funding decision, Jun 2025)
  • Next milestone: Construction start; opening early 2030swas: Tunnel-boring machine build and delivery ahead of the autumn 2028 tunnel drive; opening early-to-mid 2030s

Source: National Highways →On the map →

Water & Workforce · Clonshaugh, North Dublin, Ireland

Greater Dublin Drainage (Uisce Éireann)

  • Stage: In procurement; EPA wastewater discharge licence granted (30 September 2026), completing primary statutory consentingwas: In procurement (PQQ launched February 2026); EPA wastewater discharge licence granted (reported 30 September 2026)
  • Value: Not disclosedwas: ≈€1.3bn

Source: Uisce Éireann news release, 30 September 2026 →On the map →

Water & Workforce · Cumbria → Greater Manchester

HARP — Haweswater Aqueduct (United Utilities)

  • Stage: Planning permissions confirmed; site investigation and enabling works; main construction expected to begin in 2026was: Main construction from 2026
  • Value: c.£3bn estimated construction costwas: £3bn
  • Next milestone: Main tunnel replacement constructionwas: Main construction expected to start in 2026, following site investigation and enabling works

Source: United Utilities →On the map →

Water & Workforce · N Lincolnshire → Essex

Strategic Pipeline Alliance (Anglian Water)

  • Value: Not disclosedwas: Multi-£bn programme
  • Next milestone: Remaining first-phase sections; full 320km first phase in supply before the end of the decadewas: Remaining first-phase sections; full 320km phase in supply before 2030

Source: Anglian Water (Mar 2026) →On the map →

Water & Workforce · Parteen Basin, Co. Tipperary → Peamount, Dublin

Water Supply Project — Shannon to Dublin (Uisce Éireann)

  • Status: Pipelinewas: At tender
  • Stage: Consenting (An Coimisiún Pleanála decision deferred from 2 July 2026)was: Consenting — decision deferred to 2027
  • Value: €4.6bn to €5.9bn estimated costwas: €4.6–5.9bn
  • Next milestone: An Coimisiún Pleanála decision before 2 July 2027was: ACP decision before 2 Jul 2027

Source: RTÉ (7 Jul 2026) / Irish Examiner / The Journal / water.ie →On the map →

Water & Workforce · Abingdon, Oxfordshire

White Horse Reservoir (formerly SESRO)

  • Status: Pipelinewas: At tender
  • Stage: Consenting (statutory consultation 28 October 2025 to 13 January 2026; DCO application planned later in 2026)was: Consenting (RAPID gate 3 passed May 2026; DCO application late 2026)
  • Value: Not disclosedwas: ≈£7bn
  • Next milestone: DCO application later in 2026; main construction forecast to begin 2029 if consented; operating from 2040was: DCO application expected November 2026; construction start forecast 2029; in use by 2040

Source: Thames Water SRO · Water Magazine (13 May 2026) →On the map →

How this works: each week's published map is compared with the one before, record by record, using a permanent ID for every project. A project re-checked with nothing new to report is not listed. Every change links to the source we checked. How we verify →

Follow

Follow a sector or a project.

Choose what you care about. We email you on a Monday, only when something you follow has changed. One click in any email stops it.

Sectors

Projects

Press “Follow this project” on any change above to add it here.

Ask us

Email a specialist.

Tell us what you're bidding for, or which sector you're watching. We'll reply with the report that covers it, or scope a piece of work.

Email us →