31 projects changed: 27 reached a new stage, 23 milestones updated, 24 values revised, 3 statuses changed.
Hydrogen · Aldbrough gas storage site, ~2.5 km SE of Aldbrough village, East Riding of Yorkshire, England
Aldbrough Hydrogen Pathfinder
- Stage: Consented (planning consent granted May 2025); shortlisted in HAR2 and in due diligence with DESNZwas: Consented (planning granted May 2025); HAR2 due-diligence with DESNZ
Hydrogen · Aldbrough, East Riding of Yorkshire, England
Aldbrough Hydrogen Pathfinder (SSE / Equinor)
- Stage: Planning consent granted (May 2025); shortlisted for HAR2 and in due diligence with DESNZwas: Consented (planning approved May 2025); pre-construction
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
Hydrogen · Bardon Hill, Coalville, Leicestershire, England
Bardon Hill Hydrogen (Hygen)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Barrow-in-Furness, Cumbria, England
Barrow Green Hydrogen (Carlton Power)
- Stage: Final investment decision reached (May 2026); moving from award into executionwas: Final investment decision reached (May 2026); construction phase
- Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
Hydrogen · Binn Ecopark, near Glenfarg, Perth & Kinross, Scotland
Binn Ecopark Hydrogen Facility
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Bradford, West Yorkshire, England
Bradford Low Carbon Hydrogen
- Status: Pipelinewas: Live
- Stage: HAR1 contract signed (July 2025); site development continuingwas: In construction / financial close reached (2025)
- Value: Not disclosedwas: HAR1 revenue support (Low Carbon Hydrogen Agreement); per-project value undisclosed
- Next milestone: Financial close and start of constructionwas: Complete construction and commission (2026–2027)
Hydrogen · Creca, near Annan, Dumfries & Galloway, Scotland
Creca Hydrogen Facility (Green Cat)
- Next milestone: HAR2 due diligence and funding decisionwas: Planning decision by Dumfries and Galloway Council; HAR2 due diligence toward a Low Carbon Hydrogen Agreement
Hydrogen · NE England to Humber & East Midlands
East Coast Hydrogen network
- Next milestone: The energy regulator Ofgem is paying for the detailed design and early planning work (as of November 2026). In June 2025, National Gas said it aims to have the first hydrogen flowing in the early 2030s.was: Feasibility/engineering; alignment with Project Union
Hydrogen · Fawley, Hampshire, England
Fawley Green Hydrogen (Hynamics / EDF)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Grangemouth, Falkirk, Scotland
Grangemouth Green Hydrogen (RWE)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Northfleet, Kent, England
Green Hydrogen 3 (HYRO, Northfleet)
- Stage: HAR1-funded; ITM Power contracted Dec 2025 to supply 12.5 MW electrolyser systems for HYRO's project at Kimberly-Clark's Northfleet plant, Gravesendwas: Enabling works complete; full construction from April 2026
- Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
- Next milestone: Construction and commissioning; operational by end of 2027was: Complete construction and commission
Hydrogen · St Helens, Merseyside, England
Grenian Hydrogen St Helens
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Buckhaven and Denbeath, Levenmouth, Fife, Scotland
H100 Fife green hydrogen network (SGN)
- Stage: Site fully built, power connected and testing under way (5 October 2026); no hydrogen production yetwas: Network and production site built; site testing under way; no homes yet on hydrogen
- Value: Not disclosedwas: Ofgem-funded (network innovation); total not fully disclosed
Hydrogen · Harper Lane, Radlett/Shenley, Hertfordshire, England
Harper Lane Hydrogen (Hygen)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Hartlebury, Worcestershire, England
Hartlebury Green Hydrogen (Carlton Power)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · South Killingholme, North Lincolnshire, England
Humber H2ub (Uniper, Killingholme)
- Stage: HAR2 shortlisted (7 Apr 2025); still listed on the government shortlist pagewas: HAR2 shortlisted; planning permission granted Mar 2026; ITM selected for 120MW electrolyser; FID conditional on HAR2 contract
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and contract decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Bridgend, Wales
HyBont (Hygen, Bridgend)
- Stage: Development; acquired by Hygen (January 2026), concluding the HAR1 contract signature processwas: Development (acquired by Hygen Jan 2026, HAR1 contract signature concluded)
- Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
- Next milestone: Detailed feasibility study of the sitewas: Detailed site feasibility study, then financial close
Hydrogen · High Marnham, near Newark, Nottinghamshire, England
HyMarnham (JG Pears / GeoPura)
- Stage: Construction started (by July 2025); electrolyser systems being commissionedwas: In construction (started ahead of July 2025 wave)
- Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
Hydrogen · Cheshire / Merseyside — Stanlow to industrial offtakers across NW England, England
HyNet North West Hydrogen Pipeline (Cadent)
- Stage: DCO application paused by Cadent until the government timeline is clear (27 Nov 2025)was: DCO pre-application, paused by Cadent until the government timeline is clear
Hydrogen · Kemsley, near Sittingbourne, Kent, England
Lhyfe Kemsley Green Hydrogen
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Wallsend, North Tyneside, England
Lhyfe Wallsend Green Hydrogen
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Magor, Monmouthshire, Wales
Magor Net Zero Hydrogen
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Pembroke, Pembrokeshire, Wales
Pembroke Green Hydrogen 1 (RWE)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Teesside → Humber → East Midlands
Project Union: East Coast (National Gas)
- Status: Pipelinewas: Live
- Stage: Front end engineering and design (two-year FEED programme); surveys underway on the Humber Section; DCO application(s) to followwas: Front end engineering design (FEED); DCO consenting to follow
- Value: £57m FEED funding (Ofgem, 2025/26 prices)was: £164m development funding
Hydrogen · St Austell, Cornwall, England
St Austell Green Hydrogen (Four Zeros)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Strathallan, near Auchterarder, Perth & Kinross, Scotland
Strathallan Hydrogen Facility
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
Hydrogen · Redcar / Teesside, England
Tees Green Hydrogen Phase 2 (EDF)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Teesside, England
Teesside Green Hydrogen (MorGen Energy)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Tyseley, Birmingham, West Midlands, England
Tyseley 10MW Green Hydrogen (Motive Fuels)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Walsall, West Midlands, England
Walsall Green Hydrogen (Carlton Power)
- Stage: Shortlisted for HAR2 (April 2025); subject to due diligence stagewas: HAR2 shortlisted (pre-construction / due diligence)
- Value: Not disclosedwas: HAR2 shortlist (contracts not yet signed)
- Next milestone: HAR2 due diligence and funding decisionwas: Progress HAR2 due diligence toward Low Carbon Hydrogen Agreement
Hydrogen · Milford Haven, Pembrokeshire, Wales
West Wales Hydrogen (Milford Haven)
- Status: Pipelinewas: Live
- Stage: Final investment decision reached (11 March 2026); construction expected to begin in 2026was: Final investment decision March 2026; construction expected in 2026
- Value: Not disclosedwas: HAR1 revenue support; per-project value undisclosed
- Next milestone: Commissioning by early 2028was: Commissioning expected by early 2028