Projects · Battery Storage

Brinsworth, Rotherham, South Yorkshire, England, UK·In developmentBattery Storage

Brinsworth BESS

  • StageConsented; planning approved unanimously by committee in 2025
  • Next milestoneStart of construction; energisation scheduled for mid-2028
  • Last checked1 November 2026
Source: Root-Power project page →

What has changed on this project, and when

  • Next milestone: Start of construction; energisation scheduled for mid-20282 November 2026 · previously: Start of construction; Root-Power gives mid-2028 for energisation
  • Stage: Consented; planning approved unanimously by committee in 20252 November 2026 · previously: Consented
  • Next milestone: Start of construction; Root-Power gives mid-2028 for energisation6 October 2026 · previously: Financial close / start of construction

More Battery Storage projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.