Projects · Battery Storage

Near Thurso (Dounreay), Caithness, Highland, Scotland, UK·Under wayBattery Storage

Dounreay BESS

  • StageConstruction began in May 2025 after planning permission in January 2025
  • Next milestoneGo-live, expected by the developer in mid-2026
  • Last checked1 November 2026
Source: Root-Power, developer/operator record · reported Solar Power Portal →

What has changed on this project, and when

  • Next milestone: Go-live, expected by the developer in mid-20262 November 2026 · previously: Commissioning; the developer's stated mid-2026 go-live has passed with no energisation announced
  • Stage: Construction began in May 2025 after planning permission in January 20252 November 2026 · previously: In construction
  • Next milestone: Commissioning; the developer's stated mid-2026 go-live has passed with no energisation announced6 October 2026 · previously: Commissioning / go-live mid-2026

More Battery Storage projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.