Projects · Battery Storage

Govan (near Ibrox), Glasgow, Scotland, UK·Under wayBattery Storage

Broomloan Road BESS

  • StageIn construction; development began in late 2023
  • Next milestoneEnergisation, scheduled by the developer for mid-2026
  • Last checked1 November 2026
Source: Root-Power →

What has changed on this project, and when

  • Next milestone: Energisation, scheduled by the developer for mid-20262 November 2026 · previously: Energisation; the developer's stated mid-2026 date has passed with no energisation announced
  • Stage: In construction; development began in late 20232 November 2026 · previously: In construction
  • Next milestone: Energisation; the developer's stated mid-2026 date has passed with no energisation announced6 October 2026 · previously: Commissioning / go-live mid-2026

More Battery Storage projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.