West Burton, near Retford, Nottinghamshire, England, UK·In developmentBattery Storage
West Burton C BESS
- StageFinancial close reached (17 Jul 2026); construction due to start later in 2026
- Value£231m loan facilities
- Next milestoneConstruction start; fully operational in 2028
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Construction start; fully operational in 20282 November 2026 · previously: Final investment decision expected H1 2026; operations targeted Q4 2027
- Stage: Financial close reached (17 Jul 2026); construction due to start later in 20262 November 2026 · previously: Consented; 10-year tolling agreement with Drax signed for 250MW/500MWh (Jan 2026); FID expected by Q3 2026, commercial operation target moved to 2028
- Value: £231m loan facilities2 November 2026 · previously: Not disclosed
More Battery Storage projects
- Swinford BESSNottinghamshire, England, UK
- Withy Place BESSReading, Berkshire, England, UK
- EDF West Burton BESSWest Burton, near Retford, Nottinghamshire, England, UK
- Carrington Storage, Trafford Low Carbon Energy ParkTrafford, Greater Manchester
- Blackhillock Phase 2 (Zenobe)Keith, Moray
- Eccles BESS (Zenobe)Eccles, Scottish Borders
- Thorpe Marsh BESS (Fidra Energy)Thorpe Marsh (former power station site), near Barnby Dun, Doncaster
- Pillswood BESSCottingham, near Hull, East Riding of Yorkshire, England, UK
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.