Near Lesmahagow / Coalburn, South Lanarkshire, Scotland, UK·Under wayBattery Storage

Coalburn BESS

  • StageUnder construction (started 2026, about 18 months)
  • Next milestoneOperational in 2027
  • Last checked1 November 2026
Source: Zenobe, Coalburn project page →

What has changed on this project, and when

  • Next milestone: Operational in 20272 November 2026 · previously: Complete construction; expected commercial operation mid-2027
  • Stage: Under construction (started 2026, about 18 months)2 November 2026 · previously: Active confirmed: financial close 18 Jun 2026 AND preparatory site works begun per Zenobe; main construction from Jul 2026. Naming fix: Zenobe calls it 'Coalburn' (Alcemi/CIP's is the separate project)