Projects · Battery Storage
Auchteraw, near Fort Augustus, Highland, Scotland, UK·Under wayBattery Storage
Auchteraw
- StageOperational; fully energised and in operation (reported 3 September 2025)
- Next milestoneOngoing operation
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Ongoing operation2 November 2026 · previously: No further milestone published; operational since September 2025
- Stage: Operational; fully energised and in operation (reported 3 September 2025)2 November 2026 · previously: Operational (50MW/100MWh; energised September 2025)
- Next milestone: No further milestone published; operational since September 202529 September 2026 · previously: Full commercial operation reducing Scottish grid constraint costs
- Stage: Operational (50MW/100MWh; energised September 2025)29 September 2026 · previously: Operational
More Battery Storage projects
- Swinford BESSNottinghamshire, England, UK
- Withy Place BESSReading, Berkshire, England, UK
- EDF West Burton BESSWest Burton, near Retford, Nottinghamshire, England, UK
- Carrington Storage, Trafford Low Carbon Energy ParkTrafford, Greater Manchester
- Blackhillock Phase 2 (Zenobe)Keith, Moray
- Eccles BESS (Zenobe)Eccles, Scottish Borders
- Thorpe Marsh BESS (Fidra Energy)Thorpe Marsh (former power station site), near Barnby Dun, Doncaster
- Pillswood BESSCottingham, near Hull, East Riding of Yorkshire, England, UK
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.