North Yorkshire, England, UK·Under wayBattery Storage
Monet's Garden
- StageUnder construction; financial close May 2026
- Next milestoneTarget energisation H2 2027
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Target energisation H2 20272 November 2026 · previously: Deal completion then construction start
- Stage: Under construction; financial close May 20262 November 2026 · previously: Consented/construction-ready, GRID acquisition completed Dec 2025, £141m senior debt concluded 26 May 2026, 25% STP JV equity completed 8 Jun 2026, construction due to start immediately; Gate 2 connection Jul 2027
- Status: Under way2 November 2026 · previously: In development
More Battery Storage projects
- Swinford BESSNottinghamshire, England, UK
- Withy Place BESSReading, Berkshire, England, UK
- EDF West Burton BESSWest Burton, near Retford, Nottinghamshire, England, UK
- Carrington Storage, Trafford Low Carbon Energy ParkTrafford, Greater Manchester
- Blackhillock Phase 2 (Zenobe)Keith, Moray
- Eccles BESS (Zenobe)Eccles, Scottish Borders
- Thorpe Marsh BESS (Fidra Energy)Thorpe Marsh (former power station site), near Barnby Dun, Doncaster
- Pillswood BESSCottingham, near Hull, East Riding of Yorkshire, England, UK
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.