Every week we re-check the projects on the map against their sources. This page lists what changed: a new stage reached, a milestone reset, a value revised, a project added. The new position, what it was before, and the source we checked it against, for the last four weeks.

Week of 9 November 2026: 4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised.

Week of 9 November 2026

2 projects changed: 2 reached a new stage, 2 milestones updated, 1 value revised.

Power & Grid · Peterhead, Aberdeenshire → Drax, Yorkshire

Eastern Green Link 2

  • Stage: The link has been under construction since late 2024.was: In construction — major construction phase from Jul 2026
  • Value: £4.3 billionwas: £4.3bn (corpus: gap-11)
  • Next milestone: Construction continues through 2027, and the link is due to start operating in 2029.was: Rattray Estate HDD for the 400kV Peterhead connection — start window (from Aug 2026) has passed; confirm commencement at next cycle

Source: SSEN Transmission and National Grid, EGL2 (6 Nov 2026) →On the map →

Power & Grid · Arnish Moor / Stornoway, Isle of Lewis to Fanellan (near Beauly)

Western Isles HVDC Link (Lewis Hub)

  • Stage: Under construction. SSEN Transmission marked the start of main construction at Arnish Moor, near Stornoway, on 5 November 2026.was: Consented (Nov 2025) - early construction works underway; dedicated delivery vessel secured (Feb 2026)
  • Next milestone: RJ McLeod is carrying out the first major set of construction works, preparing the site for the converter station and substation. SSEN Transmission expects to switch the link on by 2030, subject to approvals.was: Start of Lewis Hub construction / cable installation campaign

Source: SSEN Transmission, Lewis Hub news (6 Nov 2026) →On the map →

Week of 2 November 2026

47 projects changed: 41 reached a new stage, 33 milestones updated, 8 values revised, 5 statuses changed, 6 projects added.

Power & Grid · Beauly (near Inverness) - Blackhillock (Moray) - New Deer - Peterhead (Aberdeenshire)

Beauly to Blackhillock to New Deer to Peterhead 400kV

  • Stage: Consenting; Section 37 application referred to a public local inquiry after Highland and Moray council objections; inquiry sessions scheduled 18 to 27 August 2026was: Consenting; Section 37 application (October 2025) at public inquiry after council objections

Source: Highland Council / SSEN Transmission →On the map →

Power & Grid · Bramford (Suffolk) to Twinstead (Essex), via the Stour Valley

Bramford to Twinstead Reinforcement

  • Stage: Consent granted September 2024; main construction compound set-up begun near Leavenheathwas: In construction
  • Next milestone: Overhead line construction by Balfour Beatty, then underground cable workswas: Main construction along the route, programmed by National Grid for 2026 to 2029

Source: National Grid - Bramford to Twinstead →On the map →

Power & Grid · Brinsworth (South Yorkshire) - Chesterfield - High Marnham (Nottinghamshire)

Brinsworth to High Marnham Uprating

  • Stage: Consented; planning permission granted for all three substations (High Marnham June 2026, Long Lane and near Chesterfield July 2026)was: Consented - planning permission granted for all three substations
  • Next milestone: Start of construction; no dates publishedwas: Start of substation construction; no dates published

Source: National Grid news release, 24 August 2026 →On the map →

Power & Grid · Ballyadam converter station, Carrigtwohill, Co. Cork (subsea to Brittany, France)

Celtic Interconnector

  • Stage: In construction (Step 6); HVDC subsea cable burial and protection in Irish waters completed (Sep 2026)was: In construction (Step 6); AC route complete, DC route Phase 2 ~70%; commissioning now expected spring 2028
  • Value: Not disclosed (€530.7m EU Connecting Europe Facility grant awarded)was: ≈€1bn+ project, incl. €530.7m EU Connecting Europe Facility grant (EirGrid)
  • Next milestone: Commissioning expected Q4 2028was: Energisation revised to spring 2028; remaining subsea cable installation through 2026-27

Source: EirGrid - Celtic Interconnector →On the map →

Power & Grid · New Creag Dhubh substation to Glen Lochy near Dalmally, Argyll

Creag Dhubh to Dalmally 275kV Overhead Line

  • Stage: In construction; first of 47 towers assembled, Creag Dhubh substation construction reaching the halfway markwas: In construction
  • Next milestone: Electrical installation work at the substation by Siemens Energy; continued tower assembly along the 13.3 km routewas: Transformer installation and commissioning at Creag Dhubh substation; erection of the remaining towers on the 47-tower, 13.3km route

Source: SSEN Transmission - First tower completed on Creag Dhubh-Dalmally →On the map →

Power & Grid · Creag Dhubh (near Dalmally) to Inveraray, Argyll & Bute

Creag Dhubh to Inveraray 275kV Overhead Line

  • Stage: In construction; first steel lattice tower assembled, over 4km of access tracks built (Mar 2026)was: In construction (first tower erected Mar 2026)
  • Next milestone: Complete tower assembly along the route, then commissioning (date not published)was: Tower erection and stringing ongoing across the Argyll & Kintyre reinforcement

Source: SSEN Transmission - First tower erected on new Creag Dhubh - Inveraray line →On the map →

Power & Grid · Bonnybridge - Cumbernauld - Wishaw corridor, Falkirk & North Lanarkshire

Denny to Wishaw Network Upgrade

  • Stage: Consenting; three Section 37 applications submitted to Scottish Ministers, plus Cumbernauld substation extension planning application to North Lanarkshire Council (page dated 26 Jun 2026)was: Consultation complete (final information events Feb 2026); preparing to submit consent applications
  • Next milestone: Determination of Section 37 and planning applicationswas: EIA / Section 37 consent application

Source: SP Energy Networks - Denny to Wishaw Latest News →On the map →

Power & Grid · Torness/Branxton, East Lothian to Hawthorn Pit, County Durham

Eastern Green Link 1

  • Stage: Under construction; main foundation piling complete at Murton converter station and Hawthorn Pit substation (Sep 2026)was: In construction
  • Value: Not disclosedwas: £2.5bn (Ofgem-approved funding, Nov 2024)
  • Next milestone: Next phase of construction at both siteswas: Full operation targeted 2029

Source: Eastern Green Link 1 - Main foundation piling works completed →On the map →

Power & Grid · Westfield converter station, near Ballingry, Fife (Scotland) to Norfolk (England)

Eastern Green Link 4 (EGL4)

  • Status: Pipelinewas: At tender
  • Stage: Consenting; Fife Council planning applications submitted Dec 2025; EGL4 CPO 2026 made, awaiting confirmationwas: Pre-application / consenting; DCO submission targeted Aug 2026 (Ofgem investment approval Dec 2025, supply-chain contracts signed, but construction not started)
  • Value: Not disclosedwas: ~£3bn total EGL4 contracts awarded (2026)

Source: SP Energy Networks - Eastern Green Link 4 →On the map →

Power & Grid · Grimsby West substation (NE Lincolnshire) to Walpole (Norfolk)

Grimsby to Walpole

  • Stage: Pre-application; Stage 2 consultation held 11 June to 6 August 2025was: Pre-application (post Stage 2 and targeted consultation)
  • Next milestone: DCO application expected summer 2027; decision expected 2028; construction 2029, fully operational 2033was: DCO application planned for summer 2027; decision expected 2028; construction 2029 to 2033

Source: National Grid - Grimsby to Walpole →On the map →

Power & Grid · Shurton/Bridgwater (Somerset) to Seabank, Avonmouth (South Gloucestershire)

Hinkley Connection Project

  • Stage: Northern section energised; land restoration under way; 13 T-pylons still to be energisedwas: In construction - final energisation and restoration
  • Next milestone: Energising remaining T-pylons via planned outages at Huntspillwas: Energising remaining 13 T-pylons via planned Huntspill outages

Source: National Grid - Hinkley Connection Project →On the map →

Power & Grid · Between Kendoon and Tongland, Dumfries & Galloway

Kendoon to Tongland Reinforcement (KTR)

  • Stage: Consent granted by Scottish Ministers (Feb 2025)was: Section 37 consent GRANTED by Scottish Ministers Feb 2025 - pre-construction / delivery preparation
  • Next milestone: Start of construction (date not published)was: Scottish Ministers' consent decision

Source: SP Energy Networks - KTR Latest News →On the map →

Power & Grid · Dunstown substation, Co. Kildare to Woodland substation, Co. Meath

Kildare-Meath Grid Upgrade (Woodland-Dunstown)

  • Stage: Step 6: construction, energisation and benefit sharing; planning permission granted by An Bord Pleanála in March 2025was: Construction, energisation and benefit sharing
  • Next milestone: Ongoing construction; community benefit fund consultation with local groupswas: Ongoing construction; community benefit fund consultations

Source: EirGrid - Kildare-Meath Grid Upgrade →On the map →

Power & Grid · New Coolnabacky 400/110kV substation, near Portlaoise, Co. Laois

Laois-Kilkenny Reinforcement

  • Stage: Step 6: construction, energisation and benefit sharing; 110kV GIS commissioning ongoing and 400kV GIS electrical installation under way at Coolnabacky (March 2026 update)was: Construction and energisation

Source: EirGrid - Laois Kilkenny Reinforcement →On the map →

Power & Grid · Walberswick, Suffolk landfall (multi-purpose interconnector to the Netherlands)

LionLink

  • Stage: Consultation closed (March 2026 update)was: Pre-application - statutory consultation held Jan 2026; DCO not yet submitted
  • Next milestone: Application for development consent (no date published)was: DCO application expected 2026; operational target 2032

Source: National Grid Ventures - LionLink: About →On the map →

Power & Grid · Kilroot, Co. Antrim (near Carrickfergus) to Hunterston, Ayrshire

LirIC (Northern Ireland to Scotland)

  • Stage: Development; Ofgem cap and floor award in principle, Northern Ireland transmission licence granted in 2024was: Development (licensing / consenting pre-construction)
  • Next milestone: Consents and construction; commissioning targeted for 2032was: Progress toward final consents; targeting commissioning 2032

Source: Transmission Investment - LirIC →On the map →

Power & Grid · Greater Dublin Area (Ireland) to Bodelwyddan, Denbighshire (North Wales)

MaresConnect

  • Stage: Development; proposed interconnector, Irish converter station location under technical reviewwas: Consenting / development (Ofgem licence granted)
  • Value: €860m (stated private capital investment)was: €860m (stated investment)
  • Next milestone: Finalisation of Irish converter station siting; consent submissionswas: Finalisation of Irish converter siting; consent submissions

Source: MaresConnect Interconnector →On the map →

Power & Grid · Isle of Grain, Kent (UK) to Wilhelmshaven, Lower Saxony (Germany)

NeuConnect (Great Britain to Germany)

  • Stage: In construction; offshore cabling works continuing between the UK and Germany (2025 to 2026 milestone)was: Construction (cabling and converter installation)
  • Value: Not disclosedwas: £2.4bn / €2.8bn (stated investment)
  • Next milestone: System-wide testing, commissioning and trial operations begin 2027; commercial operations 2028was: Testing and commissioning begins 2027; commercial operation 2028

Source: NeuConnect Interconnector →On the map →

Power & Grid · Ballina, Co. Mayo to Ballaghaderreen, Co. Roscommon

North Connacht 110kV Project

  • Stage: Step 6: construction, energisation and benefit sharing; main underground cabling contract awarded and construction begunwas: Construction (main works underway)
  • Next milestone: Substation and overhead line works due to conclude in 2026; main underground cabling to conclude in 2028was: Main construction to conclude in 2028, substation and overhead line works in 2026

Source: EirGrid - North Connacht 110kV Project →On the map →

Power & Grid · Birkhill Wood (near Hull, East Yorkshire) to High Marnham (Nottinghamshire)

North Humber to High Marnham

  • Stage: DCO application received 16 October 2026; acceptance decision due by 13 November 2026was: Pre-application (pre-DCO)
  • Next milestone: Planning Inspectorate decision on accepting the application for examinationwas: DCO application submission expected later in 2026, construction from 2028 if consented, fully operational 2031

Source: Planning Inspectorate (EN020034), National Grid →On the map →

Power & Grid · Pelham-Rye House-Waltham Cross-Brimsdown-Tottenham-Hackney (Hertfordshire and North London)

North London Reinforcement

  • Stage: In construction; reconductoring ongoing on all five sections, enabling works complete from Waltham Cross to Hackneywas: In construction
  • Next milestone: Completion of reconductoring and demobilisation (dates TBC)was: Main construction 2026 to 2029, testing and commissioning 2029 to 2030, fully operational from 2030

Source: National Grid - North London Reinforcement →On the map →

Power & Grid · Woodland substation, Co. Meath to Turleenan, Co. Tyrone

North-South Interconnector

  • Stage: Step 6: construction, energisation and benefit sharing; full planning consent in Ireland and Northern Irelandwas: Construction, energisation and benefit sharing
  • Next milestone: Landowner agreements under the revised compensation proposal issued in March 2026, and access arrangements for constructionwas: Landowner access/compensation agreements ahead of main civil works

Source: EirGrid - North South 400kV Interconnector →On the map →

Power & Grid · Norfolk–Suffolk–Essex

Norwich to Tilbury

  • Status: Pipelinewas: At tender
  • Stage: Examination closed; recommendation stage in progresswas: In examination — examination closed 10 Aug 2026
  • Value: Not disclosedwas: Multi-billion (corpus: gap-11)
  • Next milestone: Examining Authority recommendation due by 10 November 2026; Secretary of State decision within three months of receiving itwas: Examining Authority recommendation due within three months of the 10 Aug 2026 close; Secretary of State (DESNZ) decision a further three months after that. No decision date has been published.

Source: Planning Inspectorate EN020027; Diss Mercury (Aug 2026) →On the map →

Power & Grid · Finstown, Orkney to Dounreay West, Caithness (via the Pentland Firth)

Orkney Link (Orkney to Caithness 220kV Subsea Connection)

  • Stage: In construction; full delivery across multiple sites, Warebeth landfall drilling complete and Finstown foundation pours completewas: In construction (year 2 of delivery)
  • Next milestone: Erection of remaining building frames at Finstown and installation of the underground land cablewas: Onshore cable pulling and jointing from autumn 2026, Finstown to Warebeth installation due 2027, energisation targeted for 2028

Source: SSEN Transmission - One year of delivery on Orkney Link →On the map →

Power & Grid · Pentir to Trawsfynydd, Gwynedd/Eryri (Snowdonia), North Wales; Glaslyn Estuary crossing at Porthmadog

Pentir to Trawsfynydd Reinforcement

  • Stage: Trawsfynydd substation works approved subject to conditions by Eryri National Park Authority (15 Jul 2026)was: Planning applications submitted; Pentir Substation cables approved by Cyngor Gwynedd, remaining applications awaiting LPA decisions; DESNZ consent application still to come 2026
  • Next milestone: Remaining planning decisions; construction startwas: Planning decisions; construction due to begin summer 2026; operational by 2030

Source: Public Notice Portal - Eryri National Park Authority decision NP5/73/287V →On the map →

Power & Grid · Dublin (incl. Dublin Bay marine section)

Powering Up Dublin — Carrickmines–Poolbeg

  • Status: Pipelinewas: At tender
  • Stage: Consenting; onshore planning application submitted to Dún Laoghaire-Rathdown County Council; marine surveys in Dublin Bay from spring 2026 to summer 2027was: In procurement and consenting (planning application due by autumn 2026)
  • Next milestone: Planning decision on the onshore section; offshore licences and planning permission for the Dublin Bay sectionwas: Onshore construction contract award and planning application to Dún Laoghaire-Rathdown County Council, 2026

Source: EirGrid — Powering Up Dublin →On the map →

Power & Grid · Dublin, Ireland

Powering Up Dublin — Finglas–North Wall

  • Status: Pipelinewas: Live
  • Stage: Best Performing Option for the route published (January 2025); community benefit fund being establishedwas: Construction commencing 2026
  • Next milestone: Planning consent and constructionwas: Inchicore–Poolbeg micro-tunnel route consultation 2026

Source: EirGrid — Powering Up Dublin →On the map →

Power & Grid · Tonn Nua / Maritime Area A off Cork, Waterford & Wexford; landfall options at Garryvoe (Cork)

Powering Up Offshore - South Coast

  • Stage: Step 4: location determination; Step 4a 12-week consultation on landfall and route options running 15 September to 8 Decemberwas: Location determination; Step 4a consultation on emerging best performing options open 15 September to 8 December 2026
  • Next milestone: Step 4a consultation closes 8 December; project update with survey outcomes planned for autumn 2026was: The Step 4a consultation closes on 8 December 2026.

Source: EirGrid - Powering Up Offshore South Coast →On the map →

Power & Grid · Sizewell area (Suffolk) to Richborough / Minster Marshes (Kent)

Sea Link

  • Stage: Development consent granted by the Secretary of State on 30 October 2026was: Recommendation with Secretary of State; decision due 30 October 2026
  • Next milestone: Construction startwas: Secretary of State decision due by 30 October 2026

Source: Planning Inspectorate - Sea Link (EN020026) →On the map →

Power & Grid · Fort Augustus to Skye (Edinbane, Broadford, Ardmore)

Skye Reinforcement

  • Status: Pipelinewas: Live
  • Stage: Consented; Section 37 consent granted by the Scottish Government, project moving to the delivery phasewas: Consented (Jun 2025) - mobilising into construction
  • Value: Not disclosedwas: ~£690m (reported by New Civil Engineer)
  • Next milestone: Delivery, including replacement of Broadford and Edinbane substationswas: Main construction ramp-up; Broadford/Edinbane substation works

Source: SSEN Transmission - Skye upgrade granted consent →On the map →

Power & Grid · Spittal (Caithness) - Loch Buidhe (Sutherland) - Beauly (Highland)

Spittal to Loch Buidhe to Beauly 400kV

  • Stage: Consenting; Section 37 application (ECU00006008, received 14 Aug 2025) referred to DPEAwas: Consenting - Section 37 application under consideration (ECU00006008, received 14 Aug 2025); public local inquiry reported
  • Next milestone: DPEA process and report, then Scottish Ministers' decisionwas: Ministerial determination (within 52 weeks of submission)

Source: Scottish Government Energy Consents Unit - Spittal to Loch Buidhe to Beauly 400 kV OHL Connection →On the map →

Power & Grid · Landfall south of Harwich with converter east of Ardleigh, Essex (UK) to Niederlangen, Germany

Tarchon (Great Britain to Germany)

  • Stage: Pre-application with the Planning Inspectorate (applicant Tarchon Energy Limited)was: Pre-application / consenting; non-statutory consultation 3 Jul-13 Aug 2026 ahead of DCO
  • Next milestone: DCO application expected July 2028was: Summer 2026 non-statutory consultation; DCO application ~Jan 2028

Source: Planning Inspectorate - Tarchon Interconnector (EN0210009) →On the map →

Power & Grid · Tealing (near Dundee) to Kincardine, via a new Conland substation near Glenrothes, Fife

Tealing to Kincardine Upgrade Project (TKUP)

  • Stage: Consenting in parts; Westfield applications with Fife Council (Dec 2025); Conland application in preparation; Mossmorran consultation closed 17 Jul 2026was: Post-consultation - EIA and planning applications in preparation
  • Next milestone: Conland and Mossmorran planning applications; Section 37 applications for overhead line changeswas: EIA and planning / Section 37 applications

Source: SP Energy Networks - Tealing to Kincardine Upgrade Project →On the map →

Power & Grid · Kilmarnock South substation to Monkton/Grangestone, Ayrshire (subsea HVDC to Wales)

Western Link 2 (WL2)

  • Stage: Development; consultation on initial preferred routes closed 28 November 2025, detailed plans being prepared ahead of planning submissionwas: Detailed design / pre-planning
  • Next milestone: Planning permission in principle applications to East Ayrshire and South Ayrshire councils; construction anticipated to start in 2030was: Planning-permission-in-principle applications to Ayrshire councils (construction targeted ~2030)

Source: SP Energy Networks - Western Link 2 →On the map →

Power & Grid · Shipton (near York) to Monk Fryston, plus Osbaldwick substation, North/West Yorkshire

Yorkshire GREEN (Green Energy Enablement)

  • Stage: Preparatory works began in autumn 2024was: In construction
  • Value: Not disclosedwas: ~£524m (reported by T&D World)
  • Next milestone: Construction completion expected by 2028was: Completion targeted by 2028

Source: National Grid - Yorkshire GREEN →On the map →

How this works: each week's published map is compared with the one before, record by record, using a permanent ID for every project. A project re-checked with nothing new to report is not listed. Every change links to the source we checked. How we verify →

Follow

Follow a sector or a project.

Choose what you care about. We email you on a Monday, only when something you follow has changed. One click in any email stops it.

Sectors

Projects

Press “Follow this project” on any change above to add it here.

Ask us

Email a specialist.

Tell us what you're bidding for, or which sector you're watching. We'll reply with the report that covers it, or scope a piece of work.

Email us →