The map, week by week

What changed on the map.

Every week we re-check the projects on the map against their sources. This page lists what changed: a new stage reached, a milestone reset, a value revised, a project added. The new position, what it was before, and the source we checked it against, for the last four weeks.

Week of 9 November 2026: 4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised.

Week of 2 November 2026

39 projects changed: 38 reached a new stage, 23 milestones updated, 24 values revised, 2 statuses changed.

Health & Education Estates · Steeton with Eastburn, near Keighley, West Yorkshire

Airedale General Hospital rebuild (NHP Wave 1)

  • Status: Pipelinewas: At tender
  • Stage: Pre-construction; construction contract signed with GRAHAM on 30 July 2026 (Hospital 2.0 Alliance)was: Pre-construction (construction partner contract signed 30 July 2026)
  • Value: Not disclosedwas: £1bn+ (NHP Wave 1; H2A allocation May 2026)
  • Next milestone: Construction start (dates not yet published)was: Detailed design and approvals to follow the July 2026 contract; construction dates not yet published

Source: Airedale NHS Foundation Trust · GRAHAM · Building Better Healthcare →On the map →

Health & Education Estates · Becket Primary School, Derby

Becket Primary School rebuild (SRP)

  • Stage: Operational; new school building completed for the September 2026 school yearwas: Operational (new school building open September 2026)

Source: Derby City Council →On the map →

Health & Education Estates · Fulham Palace Road, Hammersmith, London

Charing Cross & Hammersmith Hospitals rebuild

  • Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035 to 2038)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5 billion to £2 billion
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · St Stephen's Hospital campus, Sarsfield Court, Glanmire, Co. Cork

Cork Elective Hospital

  • Stage: Pre-planning at Sarsfield Court, Glanmire; HSE planning application held up by access road issue (Jan 2026)was: Detailed design underway; surveys and site investigations complete; planning application expected to be lodged in 2026 (timeline slipped - shovel-ready now targeted for 2030 per Minister for Health, May 2026)
  • Next milestone: HSE planning application once access road resolved; shovel-ready not expected until 2030was: Planning and business case

Source: Irish Examiner - Jennifer Carroll MacNeill faces defining year on hospitals, overcrowding and agency spend →On the map →

Health & Education Estates · Derriford, Plymouth

Derriford Emergency Care Hospital

  • Stage: In construction; Emergency Care Building topped out (reported September 2026)was: NHP Wave 1 - in construction; Emergency Care Building topped out (reported September 2026)
  • Value: £247m (Emergency Care Building)was: Not disclosed

Source: University Hospitals Plymouth NHS Trust →On the map →

Health & Education Estates · Williams Avenue, Dorchester

Dorset County Hospital redevelopment

  • Stage: NHP Wave 0, already under construction (January 2025 plan)was: NHP Wave 0 - under construction
  • Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Completion of the redevelopmentwas: New Emergency Department and Critical Care Unit, topped out in July 2026, expected to open in 2027

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Kings Drive, Eastbourne, East Sussex

Eastbourne DGH & Conquest Hospital redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2037 to 2039)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Junction 7 M3, near Basingstoke, Hampshire

Hampshire Hospitals new acute hospital

  • Stage: NHP Wave 3; NHP funding committed to buy land at M3 J7; final site not decidedwas: NHP Wave 3 - committed (trust expects construction 2037-2039); site at M3 Junction 7 near Basingstoke purchased March 2026 with ringfenced NHP funds (land to remain farmed until needed)
  • Next milestone: Construction start 2037-39was: Programme business case / land assembly

Source: Hampshire Together - A funding commitment from New Hospital Programme to purchase land →On the map →

Health & Education Estates · Lowestoft Road, Gorleston-on-Sea, Great Yarmouth, Norfolk

James Paget University Hospital replacement

  • Stage: Hybrid planning application 06/25/1043/O validated Dec 2025, undecidedwas: NHP Wave 1 (RAAC) - pre-construction; Strategic Outline Case approved, OBC in development
  • Next milestone: Planning decision (due by 31 Dec 2026), then reserved matterswas: Construction start c.2027-28

Source: Great Yarmouth Borough Council - planning application 06/25/1043/O →On the map →

Health & Education Estates · Rothwell Road, Kettering, Northamptonshire

Kettering General Hospital redevelopment

  • Stage: Rockingham Wing maternity extension paused on cost (Oct 2026); energy centre under constructionwas: NHP Wave 2 - committed (construction start 2030-2035); enabling works underway - new energy centre under construction (completion targeted 2027), main scheme development resumes 2029/30
  • Next milestone: Business case assessment of maternity options (new build or Rockingham Wing extension); energy centre completion expected end 2027was: Business case / construction start early 2030s

Source: Kettering General Hospital - Update on future maternity, neonatal and gynaecology facilities →On the map →

Health & Education Estates · Standing Way, Eaglestone, Milton Keynes

Milton Keynes University Hospital redevelopment

  • Stage: NHP Wave 1; construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 - pre-construction
  • Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Construction startwas: Formal contract signing with Morgan Sindall, then construction start in 2027 to 2028

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · St James's Hospital campus, Dublin 8

National Children's Hospital, Dublin

  • Stage: In construction; completion and validation phase (over 2,850 of 5,728 rooms validated, March 2026); substantial completion will miss end-April deadlinewas: In construction — completion/validation phase
  • Value: €1.6bn incurred by NPHDB to end of February 2026 (including VAT)was: €1.6bn incurred to Feb 2026; final cost above €2.24bn approved budget (RTE/Oireachtas)
  • Next milestone: New substantial completion date awaited, followed by c.7-month commissioning before openingwas: Substantial completion and handover of keys; opening c.7 months later

Source: NPHDB — Oireachtas committee evidence (official record) →On the map →

Health & Education Estates · St Vincent's University Hospital campus, Elm Park, Dublin 4

National Maternity Hospital relocation to Elm Park

  • Stage: Preparatory works under way at St Vincent's; working with preferred bidders, main contract not awarded; final business case under review (Oct 2026)was: Enabling works underway at St Vincent's campus; main contract not awarded; new financial safeguards applied
  • Next milestone: Government approval of final business case and main contract awardwas: Main construction contract

Source: HSE - New National Maternity Hospital at the St Vincent's University Hospital campus →On the map →

Health & Education Estates · Leighton, Crewe, Cheshire

New Leighton Hospital, Crewe (NHP Wave 1)

  • Stage: Planning permission received June 2026; contractor appointment scheduled for summer 2026was: Planning approved (June 2026); pre-construction
  • Next milestone: Enabling works to begin on site summer 2027; main construction from 2028; opening 2032/33was: Enabling works to begin on site in summer 2027; main construction 2028; opening 2032/33

Source: Mid Cheshire Hospitals NHS Foundation Trust →On the map →

Health & Education Estates · Northern Meadows, Whitchurch, Cardiff

New Velindre Cancer Centre, Cardiff

  • Stage: Structure topped out (November 2025); internal fit-out startingwas: In construction — fit-out
  • Value: Not disclosedwas: PPP via Acorn consortium — construction value not published (widely reported c.£400m programme)

Source: Sacyr (Acorn consortium) →On the map →

Health & Education Estates · Delaunays Road, Crumpsall, Manchester

North Manchester General Hospital rebuild

  • Stage: NHP Wave 1; construction partner Bovis appointed (August 2026)was: NHP Wave 1, contractor appointed, pre-construction
  • Value: Up to £1.5bn reconstruction investment over nine yearswas: Not disclosed
  • Next milestone: Outpatient Centre construction start in 2027 subject to approvals, opening 2029; full hospital projected to open in 2035was: Outpatient Centre construction start 2027 subject to approvals, opening 2029, full hospital opening 2035

Source: Manchester University NHS FT, GOV.UK (DHSC) New Hospital Programme plan for implementation →On the map →

Health & Education Estates · Queen's Medical Centre, Derby Road, Nottingham

Nottingham Hospitals (QMC & City) redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035-2039)
  • Value: £2bn or more (DHSC estimate, January 2025)was: Not disclosed
  • Next milestone: Construction startwas: Programme business case / land assembly

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Pear Tree Infant and Nursery School, Derby

Pear Tree Infant & Nursery School rebuild (SRP)

  • Stage: Under construction; topping out reached (March 2026), school expected to open to pupils September 2026was: Under construction
  • Next milestone: Pupils move into the new school, then the former infant school is demolished and replaced with a playing fieldwas: Demolition of the old infant school after pupils move in, full scheme completion January 2027

Source: Derby City Council →On the map →

Health & Education Estates · Hamstel Road, Harlow, Essex

Princess Alexandra Hospital replacement

  • Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn (NHP cost band)
  • Next milestone: Construction startwas: Outline and full business cases, with construction start expected 2032 to 2034

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · London Road, Reading, Berkshire

Royal Berkshire Hospital redevelopment

  • Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2037 to 2039
  • Value: £2bn or more (DHSC estimate, January 2025)was: £2 billion or more (government cost band)
  • Next milestone: Construction startwas: Construction due to start between 2037 and 2039

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Ashton Road, Lancaster, Lancashire

Royal Lancaster Infirmary redevelopment

  • Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2035 to 2038
  • Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: £1 billion to £1.5 billion (government cost band)
  • Next milestone: Construction startwas: Construction due to start between 2035 and 2038

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Royal Sussex County Hospital, Brighton

Sussex Cancer Centre, Brighton (NHP)

  • Stage: £250m funding confirmed (January 2026); above-ground works planned to start on site summer 2026was: In construction
  • Value: £250m (New Hospital Programme)was: c.£250m (DHSC New Hospital Programme)
  • Next milestone: Opening 2029was: Above-ground works from summer 2026; opening 2029

Source: University Hospitals Sussex NHS Foundation Trust →On the map →

Health & Education Estates · Lawes Bridge, Torquay, Devon

Torbay Hospital redevelopment

  • Stage: New Hospital Programme Wave 2 scheme; construction start window 2032 to 2034 (NHP plan, Jan 2025)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £501m to £1bn (NHP cost band)was: Not disclosed
  • Next milestone: Construction start 2032 to 2034was: Business case / construction start early 2030s

Source: GOV.UK (DHSC) - New Hospital Programme: plan for implementation →On the map →

Health & Education Estates · Vicarage Road, Watford, Hertfordshire

Watford General Hospital redevelopment

  • Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
  • Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn estimated cost (DHSC, January 2025)

Source: DHSC / GOV.UK - New Hospital Programme (plan for implementation); Building Better Healthcare wave breakdown →On the map →

Health & Education Estates · Whipps Cross Road, Leytonstone, London

Whipps Cross University Hospital rebuild

  • Stage: Planning approved (refs 211245, 211244); construction now estimated to begin 2032-34 after NHP reviewwas: Enabling milestone - multi-storey car park opened Nov 2025; main scheme uncontracted
  • Next milestone: Construction start 2032-34; completion 2036-38was: Business case / construction start early 2030s

Source: Barts Health NHS Trust - Whipps Cross redevelopment →On the map →

How this works: each week's published map is compared with the one before, record by record, using a permanent ID for every project. A project re-checked with nothing new to report is not listed. Every change links to the source we checked. How we verify →

Follow

Follow a sector or a project.

Choose what you care about. We email you on a Monday, only when something you follow has changed. One click in any email stops it.

Sectors

Projects

Press “Follow this project” on any change above to add it here.

Ask us

Email a specialist.

Tell us what you're bidding for, or which sector you're watching. We'll reply with the report that covers it, or scope a piece of work.

Email us →