39 projects changed: 38 reached a new stage, 23 milestones updated, 24 values revised, 2 statuses changed.
Health & Education Estates · Steeton with Eastburn, near Keighley, West Yorkshire
Airedale General Hospital rebuild (NHP Wave 1)
- Status: Pipelinewas: At tender
- Stage: Pre-construction; construction contract signed with GRAHAM on 30 July 2026 (Hospital 2.0 Alliance)was: Pre-construction (construction partner contract signed 30 July 2026)
- Value: Not disclosedwas: £1bn+ (NHP Wave 1; H2A allocation May 2026)
- Next milestone: Construction start (dates not yet published)was: Detailed design and approvals to follow the July 2026 contract; construction dates not yet published
Health & Education Estates · Becket Primary School, Derby
Becket Primary School rebuild (SRP)
- Stage: Operational; new school building completed for the September 2026 school yearwas: Operational (new school building open September 2026)
Health & Education Estates · Fulham Palace Road, Hammersmith, London
Charing Cross & Hammersmith Hospitals rebuild
- Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035 to 2038)
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5 billion to £2 billion
- Next milestone: Construction startwas: Programme business case / land assembly
Health & Education Estates · St Stephen's Hospital campus, Sarsfield Court, Glanmire, Co. Cork
Cork Elective Hospital
- Stage: Pre-planning at Sarsfield Court, Glanmire; HSE planning application held up by access road issue (Jan 2026)was: Detailed design underway; surveys and site investigations complete; planning application expected to be lodged in 2026 (timeline slipped - shovel-ready now targeted for 2030 per Minister for Health, May 2026)
- Next milestone: HSE planning application once access road resolved; shovel-ready not expected until 2030was: Planning and business case
Health & Education Estates · Derriford, Plymouth
Derriford Emergency Care Hospital
- Stage: In construction; Emergency Care Building topped out (reported September 2026)was: NHP Wave 1 - in construction; Emergency Care Building topped out (reported September 2026)
- Value: £247m (Emergency Care Building)was: Not disclosed
Health & Education Estates · Williams Avenue, Dorchester
Dorset County Hospital redevelopment
- Stage: NHP Wave 0, already under construction (January 2025 plan)was: NHP Wave 0 - under construction
- Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
- Next milestone: Completion of the redevelopmentwas: New Emergency Department and Critical Care Unit, topped out in July 2026, expected to open in 2027
Health & Education Estates · Kings Drive, Eastbourne, East Sussex
Eastbourne DGH & Conquest Hospital redevelopment
- Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2037 to 2039)
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn
- Next milestone: Construction startwas: Programme business case / land assembly
Health & Education Estates · Junction 7 M3, near Basingstoke, Hampshire
Hampshire Hospitals new acute hospital
- Stage: NHP Wave 3; NHP funding committed to buy land at M3 J7; final site not decidedwas: NHP Wave 3 - committed (trust expects construction 2037-2039); site at M3 Junction 7 near Basingstoke purchased March 2026 with ringfenced NHP funds (land to remain farmed until needed)
- Next milestone: Construction start 2037-39was: Programme business case / land assembly
Health & Education Estates · Pield Heath Road, Uxbridge, London Borough of Hillingdon
Hillingdon Hospital rebuild
- Stage: NHP Wave 1; construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 - pre-construction
- Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: Not disclosed
Health & Education Estates · Hinchingbrooke Park, Huntingdon, Cambridgeshire
Hinchingbrooke Hospital replacement
- Stage: Kier appointed construction partner (announced Jul 2026); temporary lease of land at Views Common for construction compounds planned (Oct 2026)was: NHP Wave 1 (RAAC) - pre-construction; Strategic Outline Case approved, OBC in development
Health & Education Estates · Lowestoft Road, Gorleston-on-Sea, Great Yarmouth, Norfolk
James Paget University Hospital replacement
- Stage: Hybrid planning application 06/25/1043/O validated Dec 2025, undecidedwas: NHP Wave 1 (RAAC) - pre-construction; Strategic Outline Case approved, OBC in development
- Next milestone: Planning decision (due by 31 Dec 2026), then reserved matterswas: Construction start c.2027-28
Health & Education Estates · Rothwell Road, Kettering, Northamptonshire
Kettering General Hospital redevelopment
- Stage: Rockingham Wing maternity extension paused on cost (Oct 2026); energy centre under constructionwas: NHP Wave 2 - committed (construction start 2030-2035); enabling works underway - new energy centre under construction (completion targeted 2027), main scheme development resumes 2029/30
- Next milestone: Business case assessment of maternity options (new build or Rockingham Wing extension); energy centre completion expected end 2027was: Business case / construction start early 2030s
Health & Education Estates · Leeds General Infirmary, Great George Street, Leeds
Leeds Hospitals of the Future (LGI)
- Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn (Jan 2025 estimate)
Health & Education Estates · Standing Way, Eaglestone, Milton Keynes
Milton Keynes University Hospital redevelopment
- Stage: NHP Wave 1; construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 - pre-construction
- Value: £500m or less (DHSC estimate, January 2025)was: Not disclosed
- Next milestone: Construction startwas: Formal contract signing with Morgan Sindall, then construction start in 2027 to 2028
Health & Education Estates · Parkfield Drive, Taunton, Somerset
Musgrove Park Hospital redevelopment
- Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2, committed (construction start 2032-2034)
- Value: £501m to £1bn (DHSC estimate, January 2025)was: Not disclosed
Health & Education Estates · St James's Hospital campus, Dublin 8
National Children's Hospital, Dublin
- Stage: In construction; completion and validation phase (over 2,850 of 5,728 rooms validated, March 2026); substantial completion will miss end-April deadlinewas: In construction — completion/validation phase
- Value: €1.6bn incurred by NPHDB to end of February 2026 (including VAT)was: €1.6bn incurred to Feb 2026; final cost above €2.24bn approved budget (RTE/Oireachtas)
- Next milestone: New substantial completion date awaited, followed by c.7-month commissioning before openingwas: Substantial completion and handover of keys; opening c.7 months later
Health & Education Estates · St Vincent's University Hospital campus, Elm Park, Dublin 4
National Maternity Hospital relocation to Elm Park
- Stage: Preparatory works under way at St Vincent's; working with preferred bidders, main contract not awarded; final business case under review (Oct 2026)was: Enabling works underway at St Vincent's campus; main contract not awarded; new financial safeguards applied
- Next milestone: Government approval of final business case and main contract awardwas: Main construction contract
Health & Education Estates · Stanford Hall Estate, near Loughborough, Nottinghamshire
National Rehabilitation Centre
- Status: Archivedwas: Live
Health & Education Estates · Leighton, Crewe, Cheshire
New Leighton Hospital, Crewe (NHP Wave 1)
- Stage: Planning permission received June 2026; contractor appointment scheduled for summer 2026was: Planning approved (June 2026); pre-construction
- Next milestone: Enabling works to begin on site summer 2027; main construction from 2028; opening 2032/33was: Enabling works to begin on site in summer 2027; main construction 2028; opening 2032/33
Health & Education Estates · Northern Meadows, Whitchurch, Cardiff
New Velindre Cancer Centre, Cardiff
- Stage: Structure topped out (November 2025); internal fit-out startingwas: In construction — fit-out
- Value: Not disclosedwas: PPP via Acorn consortium — construction value not published (widely reported c.£400m programme)
Health & Education Estates · Raleigh Park, Barnstaple, Devon
North Devon District Hospital rebuild
- Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: NHP Wave 3, committed (construction start 2035-2038)
- Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: Not disclosed
Health & Education Estates · Delaunays Road, Crumpsall, Manchester
North Manchester General Hospital rebuild
- Stage: NHP Wave 1; construction partner Bovis appointed (August 2026)was: NHP Wave 1, contractor appointed, pre-construction
- Value: Up to £1.5bn reconstruction investment over nine yearswas: Not disclosed
- Next milestone: Outpatient Centre construction start in 2027 subject to approvals, opening 2029; full hospital projected to open in 2035was: Outpatient Centre construction start 2027 subject to approvals, opening 2029, full hospital opening 2035
Health & Education Estates · Queen's Medical Centre, Derby Road, Nottingham
Nottingham Hospitals (QMC & City) redevelopment
- Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: NHP Wave 3 - committed (construction start 2035-2039)
- Value: £2bn or more (DHSC estimate, January 2025)was: Not disclosed
- Next milestone: Construction startwas: Programme business case / land assembly
Health & Education Estates · St Pancras Hospital site, Camden, London
Oriel - new Moorfields Eye Hospital & UCL eye centre
- Stage: Construction complete, all 10 levels built; internal fit-out under waywas: All 10 storeys built, internal fit-out underway; opening to patients slipped to summer 2027
- Next milestone: Opening to patients summer 2027was: Fit-out toward opening
Health & Education Estates · Pear Tree Infant and Nursery School, Derby
Pear Tree Infant & Nursery School rebuild (SRP)
- Stage: Under construction; topping out reached (March 2026), school expected to open to pupils September 2026was: Under construction
- Next milestone: Pupils move into the new school, then the former infant school is demolished and replaced with a playing fieldwas: Demolition of the old infant school after pupils move in, full scheme completion January 2027
Health & Education Estates · Hamstel Road, Harlow, Essex
Princess Alexandra Hospital replacement
- Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn (NHP cost band)
- Next milestone: Construction startwas: Outline and full business cases, with construction start expected 2032 to 2034
Health & Education Estates · Gayton Road, King's Lynn, Norfolk
Queen Elizabeth Hospital King's Lynn replacement
- Stage: SOC approved Nov 2025; outline and full business case in development; enabling works begun, multi-storey car park started Jul 2026was: SOC approved; OBC development underway (NHP annual report 2025-26)
Health & Education Estates · London Road, Reading, Berkshire
Royal Berkshire Hospital redevelopment
- Stage: NHP Wave 3; construction start planned 2037 to 2039 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2037 to 2039
- Value: £2bn or more (DHSC estimate, January 2025)was: £2 billion or more (government cost band)
- Next milestone: Construction startwas: Construction due to start between 2037 and 2039
Health & Education Estates · Ashton Road, Lancaster, Lancashire
Royal Lancaster Infirmary redevelopment
- Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: New Hospital Programme wave 3; construction start 2035 to 2038
- Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: £1 billion to £1.5 billion (government cost band)
- Next milestone: Construction startwas: Construction due to start between 2035 and 2038
Health & Education Estates · Shotley Bridge, Consett, County Durham
Shotley Bridge Community Hospital
- Stage: Land remediation began 7 Sep 2026 (up to 12 months); final approvals outstandingwas: NHP Wave 1 - pre-construction
- Next milestone: Final Business Case to NHS England early 2027; construction from mid-2027was: Construction start c.2026-27
Health & Education Estates · Cotswold Road, Sutton, London
Specialist Emergency Care Hospital, Sutton
- Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: New Hospital Programme Wave 2; construction start 2032 to 2034
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn (estimate)
Health & Education Estates · Praed Street, Paddington, London
St Mary's Hospital rebuild, Paddington
- Stage: NHP Wave 3; construction start planned 2035 to 2038 (January 2025 plan)was: New Hospital Programme Wave 3; construction start 2035 to 2038
- Value: £2bn or more (DHSC estimate, January 2025)was: £2bn or more (estimate)
Health & Education Estates · Royal Sussex County Hospital, Brighton
Sussex Cancer Centre, Brighton (NHP)
- Stage: £250m funding confirmed (January 2026); above-ground works planned to start on site summer 2026was: In construction
- Value: £250m (New Hospital Programme)was: c.£250m (DHSC New Hospital Programme)
- Next milestone: Opening 2029was: Above-ground works from summer 2026; opening 2029
Health & Education Estates · Lawes Bridge, Torquay, Devon
Torbay Hospital redevelopment
- Stage: New Hospital Programme Wave 2 scheme; construction start window 2032 to 2034 (NHP plan, Jan 2025)was: NHP Wave 2 - committed (construction start 2030-2035)
- Value: £501m to £1bn (NHP cost band)was: Not disclosed
- Next milestone: Construction start 2032 to 2034was: Business case / construction start early 2030s
Health & Education Estates · Highfield Campus, Southampton
University of Southampton £180m teaching building
- Stage: Under construction; groundbreaking 5 March 2025was: In construction
Health & Education Estates · Vicarage Road, Watford, Hertfordshire
Watford General Hospital redevelopment
- Stage: NHP Wave 2; construction start planned 2032 to 2034 (January 2025 plan)was: NHP Wave 2 - committed (construction start 2030-2035)
- Value: £1.5bn to £2bn (DHSC estimate, January 2025)was: £1.5bn to £2bn estimated cost (DHSC, January 2025)
Health & Education Estates · Hardwick Lane, Bury St Edmunds, Suffolk
West Suffolk Hospital replacement
- Stage: NHP Wave 1 (RAAC); construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 (RAAC) - pre-construction
- Value: £1bn to £1.5bn (DHSC estimate, January 2025)was: £1bn to £1.5bn estimated cost (DHSC, January 2025)
Health & Education Estates · Whipps Cross Road, Leytonstone, London
Whipps Cross University Hospital rebuild
- Stage: Planning approved (refs 211245, 211244); construction now estimated to begin 2032-34 after NHP reviewwas: Enabling milestone - multi-storey car park opened Nov 2025; main scheme uncontracted
- Next milestone: Construction start 2032-34; completion 2036-38was: Business case / construction start early 2030s
Health & Education Estates · Royal Cornwall Hospital, Treliske, Truro, Cornwall
Women & Children's Hospital, Royal Cornwall
- Stage: NHP Wave 1; construction start planned 2027 to 2028 (January 2025 plan)was: NHP Wave 1 - pre-construction
- Value: £500m or less (DHSC estimate, January 2025)was: Estimated cost of £500m or less (DHSC, January 2025)