29 projects changed: 27 reached a new stage, 21 milestones updated, 9 values revised, 3 statuses changed.
Data Centres · Hilfield Park, Elstree, Hertsmere, Hertfordshire
Ark Hilfield Park campus (Watford/Elstree)
- Stage: Pre-application consultation; planning application in preparationwas: Pre-application consultation; approval targeted 2026
- Next milestone: Planning application to Hertsmere Borough Councilwas: Planning submission / determination
Data Centres · Longcross Park, Chertsey, Surrey
Ark Longcross Park (LP02), Chertsey
- Stage: Planning permission granted for next phase, including new 36MW LP02 buildingwas: Planning approved; pre-construction / build-out
- Value: £807m (~$1bn) campus investmentwas: £807m (~$1bn)
Data Centres · Spring Park, Corsham, Wiltshire
Ark Spring Park Extension, Corsham
- Stage: Planning approved with conditions by Wiltshire Council (10 February)was: Planning approved with conditions (Feb 2026)
Data Centres · Cruiserath Road, Mulhuddart, Dublin 15
AWS Mulhuddart campus (three data centres)
- Stage: Permission granted with revised conditions on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-constructionwas: Permission granted on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction
- Next milestone: Construction startwas: Execute PPA; construction start
Data Centres · Former Premier Periclase site, Drogheda, Co. Louth
CORE Sustainability Campus, Drogheda
- Stage: Louth County Council application (ref 2460674) under third-party appeal by An Taisce, lodged 24 Jul 2025 (PL15.323134); no decision shown, due date of 26 Nov 2025 passedwas: Planning granted by Louth County Council (Jun 2025, ref 2460674); under third-party appeal to An Coimisiún Pleanála (An Taisce, lodged 24 Jul 2025), appeal undecided; 32MW phase 1
- Value: Not disclosedwas: €600m-€1bn (10 years)
- Next milestone: An Coimisiún Pleanála appeal decisionwas: Planning determination
Data Centres · Culham Science Centre, near Abingdon, Oxfordshire
Culham AI Growth Zone
- Stage: Announced as first AI Growth Zone (Jan 2025); private-sector partner still being sought (Mar 2026)was: Designated (Apr 2025); Strategic Investment Partner procurement underway
- Next milestone: Agreement of public-private partnership with a private-sector partnerwas: Selection of Strategic Investment Partner
Data Centres · Avoca River Business Park (former IFI site), Arklow, Co. Wicklow
Echelon DUB20 Green Energy Park, Arklow
- Stage: Under construction (reported 26 March 2026)was: Under construction
- Next milestone: Completion (due by 2028)was: Completion (~2028)
Data Centres · Kilmeaden, near Waterford city, Co. Waterford
Echelon Kilmeaden campus, Waterford
- Stage: Planning permission sought (September 2025); more than 300 objectionswas: Planning submitted (Oct 2025)
Data Centres · Ballymakaily, Lucan, Co. Dublin
EdgeConneX Lucan (Ballymakaily, two buildings)
- Stage: Planning granted on appeal by An Coimisiún Pleanála, overturning South Dublin County Council's refusal; pre-constructionwas: Planning granted on appeal (Aug 2025); pre-construction
- Next milestone: Construction start; corporate renewable PPA required before operationwas: Construction start
Data Centres · Ennis, Co. Clare, Ireland
Ennis campus (Art Data Centres)
- Stage: Works set to commence after the High Court found in the developer's favour in judicial review proceedings (March 2026)was: Build starting (judicial review dismissed March 2026; leave to appeal refused June 2026)
Data Centres · Blanchardstown, Dublin 15
Equinix DB7x, Blanchardstown
- Stage: Construction began (announced 20 March 2026)was: Under construction (from Mar 2026)
- Next milestone: Retail capacity available from early 2028was: Availability (early 2028)
Data Centres · South Mimms, Hertsmere, Hertfordshire
Equinix DC01UK / Hertfordshire Campus, South Mimms
- Stage: 85-acre site acquired, permitted for data centre development (Oct 2025)was: Outline planning permission granted (January 2025); pre-construction
- Next milestone: Construction startwas: Detailed planning approvals and groundbreaking. No construction start date has been published.
Data Centres · Nutmeg Lane, Poplar, Tower Hamlets, East London
Global Switch London South, Docklands
- Status: Pipelinewas: At tender
- Stage: Planning approved; Global Switch says London South 'is being developed'; no construction or completion date publishedwas: Planning approved (Feb 2024); pre-construction — no evidence of site works; completion targeted ~2027
- Next milestone: Construction start (date not published)was: Completion (~2027)
Data Centres · South Dublin, Ireland
Grange Castle Phase 3 (Google)
- Next milestone: Construction start (no date published)was: Grid connection and start of construction; no dates published
Data Centres · Former RAF Elsham Wolds, near Brigg, North Lincolnshire
Greystoke Elsham Tech Park, North Lincolnshire
- Stage: Planning approved by North Lincolnshire councillors (reported Mar 2026); construction expected from 2027, first phase to open 2029was: Planning approved Mar 2026; construction planned to begin 2027, open 2029; no judicial review surfaced
- Value: Up to £10bnwas: £7.5-10bn
Data Centres · Peel Waters / TraffordCity, Salford, Greater Manchester
Halo West data centre, Peel Waters, Salford
- Stage: Unanimous approval by Salford City Council planning committee (reported 7 March 2025); pre-constructionwas: Planning approved (Feb 2025); pre-construction
Data Centres · Naas Enterprise Park, Naas, Co. Kildare
Herbata 'grid-free' data campus, Naas
- Stage: Under appeal to An Coimisiún Pleanála (first and third party appeals lodged 16 September 2025); decision not yet madewas: Planning granted (Aug 2025); under appeal
- Value: Not disclosedwas: €3bn
- Next milestone: An Coimisiún Pleanála decision, originally due by 28 January 2026was: An Coimisiún Pleanála decision on appeals lodged September 2025, originally due by 28 January 2026
Data Centres · Kao Data campus, Harlow, Essex
Kao Data Harlow campus expansion (KLON-03/04)
- Status: Pipelinewas: Live
- Stage: KLON-03 (17.6MW) announced Mar 2025; two further buildings planned (Sep 2025); Nebius 22MW ten-year lease signedwas: KLON-03 under construction; further phases in planning
- Value: Not disclosedwas: £1.7bn (Nebius UK deployment)
- Next milestone: Construction of KLON-03 and planning for further buildingswas: KLON-03 energisation; KLON-04 consent
Data Centres · Bidder Street, Canning Town, Newham, East London
L&G / Goldacre hyperscale data centre, Canning Town
- Stage: Planning permission granted by LB Newham councillors; pre-constructionwas: Planning granted (Oct 2024); pre-construction
- Next milestone: Construction; could be operational by 2027was: Construction; operational ~2027
Data Centres · Rover Way, Cardiff, South Wales
Latos Cardiff (Rover Way)
- Next milestone: Start of development work, expected immediately; no delivery timeline publishedwas: Start of development, no delivery timeline published
Data Centres · Little Island, Cork Harbour, Co. Cork
Little Island data centre (former Mitsui Denman site), Cork
- Stage: Building 1 fully constructed, fit-out outstanding (Mar 2025); grid connection agreement issued 18 Jul 2024; permission extended to 2027was: Building 1 shell complete — awaiting grid connection/fit-out; permission extended to 2027
- Next milestone: Fit-out of building 1; second buildingwas: Fit-out; second building
Data Centres · Skelton Grange, Stourton, Leeds, West Yorkshire
Microsoft data campus, Skelton Grange, Leeds
- Stage: Hybrid planning unanimously approved by Leeds City Council (Apr 2026); pre-constructionwas: Planning approved Apr 2026; construction now expected to begin early 2027
- Value: £4bn (reported)was: £4bn
- Next milestone: Construction start, likely within 12 to 18 months of approvalwas: Construction start
Data Centres · Trawsfynydd, Gwynedd (former nuclear power station) with a second base at Prosperity Parc, Anglesey, North Wales
North Wales AI Growth Zone (Trawsfynydd / Anglesey)
- Stage: Announced (13 Nov 2025); securing investment partnerwas: Designated (Nov 2025); securing investment partner
- Value: Not disclosedwas: Up to £100bn (programme-wide AIGZ figure)
- Next milestone: Confirmation of investment partner, then construction startwas: Confirmation of investment partner / construction start
Data Centres · Brent Cross Town, Barnet, North London
Pure DC Brent Cross campus (LON1)
- Stage: Live operational campus; 70MW LON01B2 final build phase under way, Glencar piling West Shell (Sep 2026)was: Building 1 operating; Building 2 under construction
- Next milestone: LON01B2 completion (Q2 2029)was: Phase completion (~2029)
Data Centres · Cambois, near Blyth, Northumberland
QTS Cambois campus (Blackstone)
- Status: Livewas: At tender
- Stage: First phase (first two of up to ten buildings) approved by Strategic Planning Committee; enabling works well under way (December 2025)was: Consented; Phase 1 reserved matters approved, enabling works
- Value: £10bnwas: Up to £10bn (Northumberland County Council)
- Next milestone: Construction of the first data centre buildingswas: Construction of the first data centre building during 2026
Data Centres · Rochfortbridge, Co. Westmeath
Red Admiral data campus, Rochfortbridge
- Stage: Westmeath County Council application (ref 2560344) under third-party appeal to An Coimisiún Pleanála (PL25M.501550), lodged 17 Jun 2026; no decision shownwas: Granted 3 Jun 2026; stalled — 10 third-party appeals lodged with An Coimisiun Pleanala (one ruled invalid); decision awaited
- Value: Not disclosedwas: €1bn
Data Centres · Slough Trading Estate, Slough, Berkshire
SEGRO Slough Trading Estate data centre
- Stage: Pre-let signed in H1 2026 for a multistorey powered shell data centre; Slough Simplified Planning Zone pre-approves data centre developmentwas: Pre-let signed March 2026; consented under the estate's Simplified Planning Zone
- Next milestone: Delivery in two phases as power becomes available; no completion date publishedwas: No completion date published as of October 2026
Data Centres · Slough Trading Estate, Slough, Berkshire
VIRTUS LONDON19, Slough
- Stage: Announced June 2026; planning secured via the Slough Trading Estate Simplified Planning Zonewas: Planning approved (2026); pre-construction
- Next milestone: Construction start, expected shortly after design approvalwas: Construction start
Data Centres · West Sleekburn, near Bedlington, Northumberland
West Sleekburn data centre campus, Northumberland
- Stage: Planning application filed with Northumberland County Council by Wansbeck Regeneration; no decision reportedwas: Planning submitted (Jun 2026)