Week of 9 November 2026: 4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised.

Week of 2 November 2026

29 projects changed: 27 reached a new stage, 21 milestones updated, 9 values revised, 3 statuses changed.

Data Centres · Cruiserath Road, Mulhuddart, Dublin 15

AWS Mulhuddart campus (three data centres)

  • Stage: Permission granted with revised conditions on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-constructionwas: Permission granted on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction
  • Next milestone: Construction startwas: Execute PPA; construction start

Source: An Coimisiún Pleanála →On the map →

Data Centres · Former Premier Periclase site, Drogheda, Co. Louth

CORE Sustainability Campus, Drogheda

  • Stage: Louth County Council application (ref 2460674) under third-party appeal by An Taisce, lodged 24 Jul 2025 (PL15.323134); no decision shown, due date of 26 Nov 2025 passedwas: Planning granted by Louth County Council (Jun 2025, ref 2460674); under third-party appeal to An Coimisiún Pleanála (An Taisce, lodged 24 Jul 2025), appeal undecided; 32MW phase 1
  • Value: Not disclosedwas: €600m-€1bn (10 years)
  • Next milestone: An Coimisiún Pleanála appeal decisionwas: Planning determination

Source: An Coimisiún Pleanála - Case PL15.323134 →On the map →

Data Centres · Culham Science Centre, near Abingdon, Oxfordshire

Culham AI Growth Zone

  • Stage: Announced as first AI Growth Zone (Jan 2025); private-sector partner still being sought (Mar 2026)was: Designated (Apr 2025); Strategic Investment Partner procurement underway
  • Next milestone: Agreement of public-private partnership with a private-sector partnerwas: Selection of Strategic Investment Partner

Source: South Oxfordshire and Vale - Statement of Common Ground for Culham Campus (LPA59 AS11) →On the map →

Data Centres · Ballymakaily, Lucan, Co. Dublin

EdgeConneX Lucan (Ballymakaily, two buildings)

  • Stage: Planning granted on appeal by An Coimisiún Pleanála, overturning South Dublin County Council's refusal; pre-constructionwas: Planning granted on appeal (Aug 2025); pre-construction
  • Next milestone: Construction start; corporate renewable PPA required before operationwas: Construction start

Source: Ballymakaily, two buildings — developer/operator record · reported TheJournal.ie →On the map →

Data Centres · Ennis, Co. Clare, Ireland

Ennis campus (Art Data Centres)

  • Stage: Works set to commence after the High Court found in the developer's favour in judicial review proceedings (March 2026)was: Build starting (judicial review dismissed March 2026; leave to appeal refused June 2026)

Source: RTÉ (Mar 2026) / Irish Times (Jun 2026) →On the map →

Data Centres · Blanchardstown, Dublin 15

Equinix DB7x, Blanchardstown

  • Stage: Construction began (announced 20 March 2026)was: Under construction (from Mar 2026)
  • Next milestone: Retail capacity available from early 2028was: Availability (early 2028)

Source: Equinix press release (20 March 2026) →On the map →

Data Centres · South Mimms, Hertsmere, Hertfordshire

Equinix DC01UK / Hertfordshire Campus, South Mimms

  • Stage: 85-acre site acquired, permitted for data centre development (Oct 2025)was: Outline planning permission granted (January 2025); pre-construction
  • Next milestone: Construction startwas: Detailed planning approvals and groundbreaking. No construction start date has been published.

Source: Equinix press release (30 October 2025) · Hertsmere Borough Council →On the map →

Data Centres · Nutmeg Lane, Poplar, Tower Hamlets, East London

Global Switch London South, Docklands

  • Status: Pipelinewas: At tender
  • Stage: Planning approved; Global Switch says London South 'is being developed'; no construction or completion date publishedwas: Planning approved (Feb 2024); pre-construction — no evidence of site works; completion targeted ~2027
  • Next milestone: Construction start (date not published)was: Completion (~2027)

Source: Global Switch - London data centres →On the map →

Data Centres · Former RAF Elsham Wolds, near Brigg, North Lincolnshire

Greystoke Elsham Tech Park, North Lincolnshire

  • Stage: Planning approved by North Lincolnshire councillors (reported Mar 2026); construction expected from 2027, first phase to open 2029was: Planning approved Mar 2026; construction planned to begin 2027, open 2029; no judicial review surfaced
  • Value: Up to £10bnwas: £7.5-10bn

Source: Data Centre Review - North Lincolnshire approves plans for major AI data centre campus →On the map →

Data Centres · Peel Waters / TraffordCity, Salford, Greater Manchester

Halo West data centre, Peel Waters, Salford

  • Stage: Unanimous approval by Salford City Council planning committee (reported 7 March 2025); pre-constructionwas: Planning approved (Feb 2025); pre-construction

Source: Peel Waters →On the map →

Data Centres · Naas Enterprise Park, Naas, Co. Kildare

Herbata 'grid-free' data campus, Naas

  • Stage: Under appeal to An Coimisiún Pleanála (first and third party appeals lodged 16 September 2025); decision not yet madewas: Planning granted (Aug 2025); under appeal
  • Value: Not disclosedwas: €3bn
  • Next milestone: An Coimisiún Pleanála decision, originally due by 28 January 2026was: An Coimisiún Pleanála decision on appeals lodged September 2025, originally due by 28 January 2026

Source: An Coimisiún Pleanála, RTÉ →On the map →

Data Centres · Kao Data campus, Harlow, Essex

Kao Data Harlow campus expansion (KLON-03/04)

  • Status: Pipelinewas: Live
  • Stage: KLON-03 (17.6MW) announced Mar 2025; two further buildings planned (Sep 2025); Nebius 22MW ten-year lease signedwas: KLON-03 under construction; further phases in planning
  • Value: Not disclosedwas: £1.7bn (Nebius UK deployment)
  • Next milestone: Construction of KLON-03 and planning for further buildingswas: KLON-03 energisation; KLON-04 consent

Source: Kao Data — developer/operator record · reported DatacenterDynamics →On the map →

Data Centres · Little Island, Cork Harbour, Co. Cork

Little Island data centre (former Mitsui Denman site), Cork

  • Stage: Building 1 fully constructed, fit-out outstanding (Mar 2025); grid connection agreement issued 18 Jul 2024; permission extended to 2027was: Building 1 shell complete — awaiting grid connection/fit-out; permission extended to 2027
  • Next milestone: Fit-out of building 1; second buildingwas: Fit-out; second building

Source: Irish Examiner - Little Island data centre permission extension →On the map →

Data Centres · Skelton Grange, Stourton, Leeds, West Yorkshire

Microsoft data campus, Skelton Grange, Leeds

  • Stage: Hybrid planning unanimously approved by Leeds City Council (Apr 2026); pre-constructionwas: Planning approved Apr 2026; construction now expected to begin early 2027
  • Value: £4bn (reported)was: £4bn
  • Next milestone: Construction start, likely within 12 to 18 months of approvalwas: Construction start

Source: Construction Enquirer - Go-ahead for Microsoft's £4bn Leeds data hub push →On the map →

Data Centres · Trawsfynydd, Gwynedd (former nuclear power station) with a second base at Prosperity Parc, Anglesey, North Wales

North Wales AI Growth Zone (Trawsfynydd / Anglesey)

  • Stage: Announced (13 Nov 2025); securing investment partnerwas: Designated (Nov 2025); securing investment partner
  • Value: Not disclosedwas: Up to £100bn (programme-wide AIGZ figure)
  • Next milestone: Confirmation of investment partner, then construction startwas: Confirmation of investment partner / construction start

Source: GOV.UK (DSIT) →On the map →

Data Centres · Cambois, near Blyth, Northumberland

QTS Cambois campus (Blackstone)

  • Status: Livewas: At tender
  • Stage: First phase (first two of up to ten buildings) approved by Strategic Planning Committee; enabling works well under way (December 2025)was: Consented; Phase 1 reserved matters approved, enabling works
  • Value: £10bnwas: Up to £10bn (Northumberland County Council)
  • Next milestone: Construction of the first data centre buildingswas: Construction of the first data centre building during 2026

Source: Northumberland County Council →On the map →

Data Centres · Rochfortbridge, Co. Westmeath

Red Admiral data campus, Rochfortbridge

  • Stage: Westmeath County Council application (ref 2560344) under third-party appeal to An Coimisiún Pleanála (PL25M.501550), lodged 17 Jun 2026; no decision shownwas: Granted 3 Jun 2026; stalled — 10 third-party appeals lodged with An Coimisiun Pleanala (one ruled invalid); decision awaited
  • Value: Not disclosedwas: €1bn

Source: An Coimisiún Pleanála - Case PL25M.501550 →On the map →

Data Centres · Slough Trading Estate, Slough, Berkshire

SEGRO Slough Trading Estate data centre

  • Stage: Pre-let signed in H1 2026 for a multistorey powered shell data centre; Slough Simplified Planning Zone pre-approves data centre developmentwas: Pre-let signed March 2026; consented under the estate's Simplified Planning Zone
  • Next milestone: Delivery in two phases as power becomes available; no completion date publishedwas: No completion date published as of October 2026

Source: SEGRO results for the six months to 30 June 2026 →On the map →

How this works: each week's published map is compared with the one before, record by record, using a permanent ID for every project. A project re-checked with nothing new to report is not listed. Every change links to the source we checked. How we verify →

Follow

Follow a sector or a project.

Choose what you care about. We email you on a Monday, only when something you follow has changed. One click in any email stops it.

Sectors

Projects

Press “Follow this project” on any change above to add it here.

Ask us

Email a specialist.

Tell us what you're bidding for, or which sector you're watching. We'll reply with the report that covers it, or scope a piece of work.

Email us →