The map, week by week

What changed on the map.

Every week we re-check the projects on the map against their sources. This page lists what changed: a new stage reached, a milestone reset, a value revised, a project added. The new position, what it was before, and the source we checked it against, for the last four weeks.

Week of 9 November 2026: 4 projects changed: 2 reached a new stage, 4 milestones updated, 1 value revised.

Week of 2 November 2026

110 projects changed: 93 reached a new stage, 90 milestones updated, 14 values revised, 2 statuses changed.

Battery Storage · Auchteraw, near Fort Augustus, Highland, Scotland, UK

Auchteraw

  • Stage: Operational; fully energised and in operation (reported 3 September 2025)was: Operational (50MW/100MWh; energised September 2025)
  • Next milestone: Ongoing operationwas: No further milestone published; operational since September 2025

Source: Field - largest battery site to date →On the map →

Battery Storage · Near Buncrana (Trillick substation), County Donegal, Ireland

Ballynahone Energy Storage

  • Stage: Third-party planning appeal lodged with An Coimisiún Pleanála 4 Dec 2024; no decision listedwas: Consented by Donegal County Council (November 2024); under appeal to An Coimisiún Pleanála, re-advertised July 2026
  • Next milestone: An Coimisiún Pleanála appeal decisionwas: An Coimisiun Pleanala determination of the appeal

Source: An Coimisiún Pleanála - Case PL05E.321384 →On the map →

Battery Storage · South Kilvington, near Thirsk, North Yorkshire, England, UK

Bellmoor BESS

  • Stage: In planning (application ZB24/02454/HYB submitted to North Yorkshire Council, January 2025)was: In planning

Source: NatPower UK - Bellmoor →On the map →

Battery Storage · Near Berkswell, Solihull/Warwickshire border, West Midlands, England, UK

Berkswell BESS

  • Stage: Under construction since September 2026was: Under construction (200MW/857MWh; BW ESS/Penso Power with AIP Management investment)
  • Next milestone: Commercial operation, expected Q4 2027was: Planning determination and build-out toward ~2026 commissioning

Source: Energy Global - BW ESS and Danske Commodities sign optimisation agreement for 200 MW battery in UK →On the map →

Battery Storage · Bicker Fen, near Bicker/Boston, Lincolnshire, England, UK

Bicker Fen 1 BESS

  • Next milestone: In October 2026, Fidra Energy had yet to confirm the investment decision or a date for the site to start operating. Fidra lists Bicker Fen 1 and 2 as one combined site.was: Final investment decision expected 2026; operations targeted 2028

Source: Fidra Energy - Our Projects →On the map →

Battery Storage · Bicker Fen, near Bicker/Boston, Lincolnshire, England, UK

Bicker Fen 2 BESS

  • Next milestone: In October 2026, Fidra Energy had yet to confirm the investment decision or a date for the site to start operating. Fidra lists Bicker Fen 1 and 2 as one combined site.was: Final investment decision expected 2027; operations targeted 2029

Source: Fidra Energy - Our Projects →On the map →

Battery Storage · Keith, Moray

Blackhillock Phase 2 (Zenobe)

  • Stage: In construction; Phase 2 under way (Phase 1 in commercial operation since early 2025)was: In construction — Phase 2 under way
  • Value: Part of Zenobē's £750m Scottish investment programmewas: Part of Zenobe's £750m+ Scottish programme
  • Next milestone: Final commissioning and energisation Q1 to Q2 2027was: Phase 2 energisation — confirm date against Zenobe

Source: Zenobe Blackhillock project page / NS Energy →On the map →

Battery Storage · Bramford, near Ipswich, Suffolk, England, UK

Bramford BESS

  • Stage: Consented by Mid Suffolk District Council (April 2025)was: Consented
  • Next milestone: Construction; operation targeted for 2029was: Move to construction; operational target 2029

Source: Clearstone Energy →On the map →

Battery Storage · Brinsworth, Rotherham, South Yorkshire, England, UK

Brinsworth BESS

  • Stage: Consented; planning approved unanimously by committee in 2025was: Consented
  • Next milestone: Start of construction; energisation scheduled for mid-2028was: Start of construction; Root-Power gives mid-2028 for energisation

Source: Root-Power project page →On the map →

Battery Storage · Govan (near Ibrox), Glasgow, Scotland, UK

Broomloan Road BESS

  • Stage: In construction; development began in late 2023was: In construction
  • Next milestone: Energisation, scheduled by the developer for mid-2026was: Energisation; the developer's stated mid-2026 date has passed with no energisation announced

Source: Root-Power →On the map →

Battery Storage · Trafford, Greater Manchester

Carrington Storage, Trafford Low Carbon Energy Park

  • Stage: In construction (from autumn 2025); financial close reachedwas: In construction (from autumn 2025)
  • Next milestone: Energisation targeted for late 2027was: Energisation expected late 2027

Source: Statera Energy (Nov 2025) →On the map →

Battery Storage · Great Barr, Walsall, West Midlands, England, UK

Chapel Lane BESS

  • Stage: Allowed by planning inspector; Walsall Council's court challenge dismissed (Sep 2025)was: Consented on appeal; Walsall Council's High Court challenge dismissed September 2025, permission stands
  • Next milestone: Construction startwas: Planning determination and construction

Source: Walsall Council - Court dismisses case against Chapel Lane battery storage facility planning permission →On the map →

Battery Storage · Upminster, Essex (near M25), England, UK

Clay Tye BESS

  • Stage: Operational; energised and launched March 2024was: Operational
  • Next milestone: Continued operationwas: Continued merchant operation

Source: Harmony Energy / FRV →On the map →

Battery Storage · Graveney, near Faversham, Kent, England, UK

Cleve Hill Solar & Storage

  • Stage: Solar (373MWdc) operating since Jul 2025; 150MW/300MWh battery under constructionwas: Solar park operational since July 2025; 150MW battery storage under construction
  • Value: Not disclosedwas: ~£450 million (construction)
  • Next milestone: Battery commercial operation, estimated 2026was: Completion of the 150MW battery storage system; the developer's stated early 2026 completion has passed with no completion announced

Source: Quinbrook - Cleve Hill →On the map →

Battery Storage · Near Lesmahagow / Coalburn, South Lanarkshire, Scotland, UK

Coalburn BESS

  • Stage: Under construction (started 2026, about 18 months)was: Active confirmed: financial close 18 Jun 2026 AND preparatory site works begun per Zenobe; main construction from Jul 2026. Naming fix: Zenobe calls it 'Coalburn' (Alcemi/CIP's is the separate project)
  • Next milestone: Operational in 2027was: Complete construction; expected commercial operation mid-2027

Source: Zenobe - Coalburn project page →On the map →

Battery Storage · Coolkeeragh, Foyle Port, near Londonderry, County Londonderry, Northern Ireland, UK

Coolkeeragh BESS

  • Stage: Consented (2-hour scheme); revised four-hour application submitted to Derry City and Strabane District Council in November 2025was: Consented; revised planning application for a four-hour design submitted November 2025
  • Value: Not disclosedwas: Over £100 million (with Magherafelt)
  • Next milestone: Council decision on the revised application; construction and operation would take about 9 to 12 months if approvedwas: Decision by Derry City and Strabane District Council on the revised four-hour application

Source: ABO Energy project page →On the map →

Battery Storage · Dunsinane, Dundee, Scotland, UK

Dunsinane Battery Storage

  • Stage: Operational; began commercial operations in April 2023was: Operational
  • Next milestone: Continued operation with EDF as trading and optimisation partnerwas: Continued operation with EDF route-to-market

Source: EDF Energy →On the map →

Battery Storage · Eccles, Scottish Borders

Eccles BESS (Zenobe)

  • Stage: Construction largely complete; testing and commissioning to followwas: Construction largely complete — commercial operation was due June 2026
  • Value: Not disclosedwas: £220m
  • Next milestone: Operation expected in 2027was: Confirm whether the site has entered commercial operation. Zenobe's stated June 2026 commercial-operation date has passed and no confirmation of energisation was found on 8 Sep 2026 — if it is live, this entry moves off the active-build list.

Source: Zenobe Eccles project page →On the map →

Battery Storage · Aghada, Cork Harbour, County Cork, Ireland

ESB Aghada BESS (Phase 1)

  • Stage: Operational; launched in 2022 as ESB's first battery storage sitewas: Operational
  • Next milestone: Continued operationwas: Ongoing operation and grid services

Source: ESB press release →On the map →

Battery Storage · Aghada, Cork Harbour, County Cork, Ireland

ESB Aghada BESS (Phase 2)

  • Stage: Operational; officially opened on 15 November 2024was: Operational
  • Value: Part of ESB's investment of up to €300m in battery storage across Dublin and Corkwas: Part of ESB's ~€300m battery investment
  • Next milestone: Continued operation providing fast-acting storage for grid stabilitywas: Ongoing operation and grid/DS3 services

Source: ESB press release →On the map →

Battery Storage · Poolbeg peninsula, Ringsend, Dublin, Ireland

ESB Poolbeg BESS

  • Stage: Operational since late November 2023; officially launched February 2024was: Operational
  • Value: Part of ESB's investment of up to €300m in battery projectswas: Part of ESB's ~€300m battery investment
  • Next milestone: Continued operation providing fast-acting storage for grid stabilitywas: Ongoing EirGrid grid/DS3 system services

Source: ESB press release →On the map →

Battery Storage · Ferrybridge, near Knottingley, West Yorkshire, England, UK

Ferrybridge BESS

  • Stage: Fully operational (March 2026); construction began August 2023was: Operational
  • Next milestone: Ongoing operation supporting grid flexibility and system resiliencewas: Ongoing commercial dispatch and grid balancing

Source: SSE plc →On the map →

Battery Storage · Cuerdley, near Widnes/Warrington, Cheshire, England, UK

Fiddler's Ferry BESS

  • Stage: In construction since early 2024was: In construction
  • Next milestone: Completion and commissioningwas: Commissioning and grid energisation

Source: SSE Renewables →On the map →

Battery Storage · Gorman, near Wilkinstown/Navan, County Meath, Ireland

Gorman BESS

  • Stage: Operational; started up June 2022was: Operational
  • Value: EUR 28 millionwas: ~€28 million
  • Next milestone: Continued DS3 service to EirGrid under a six-year arrangementwas: Continued DS3 frequency-regulation service

Source: Iberdrola →On the map →

Battery Storage · Near Carlisle, Cumbria (location indicative), England, UK

Harker BESS

  • Stage: Consented (planning permission granted October 2023); initial enabling works from August 2026was: Consented / pre-construction
  • Next milestone: Site mobilisation in Q1 2027; energisation expected in 2028; commercial operation expected late 2028 or early 2029was: Main construction mobilisation in Q1 2027; energisation expected in 2028; commercial operation in late 2028 or early 2029

Source: Zenobe - Harker 400MW BESS project page →On the map →

Battery Storage · Harker, near Carlisle, Cumbria, England, UK

Harker BESS (Recurrent Energy)

  • Stage: Consented (Cumberland Council, June 2024)was: Consented
  • Next milestone: Construction anticipated from Q4 2029, subject to grid connection datewas: Construction anticipated from Q4 2029 unless an earlier grid connection date is agreed

Source: Recurrent Energy →On the map →

Battery Storage · Near South Hetton, County Durham, England, UK

Hawthorn Pit BESS (Zenobe)

  • Stage: In planning (application DM/26/01837/FPA being considered by Durham County Council)was: In planning (application submitted)
  • Next milestone: Determination by Durham County Council; earliest construction 2029was: Decision by Durham County Council on application DM/26/01837/FPA. No decision date has been published. Earliest construction start is 2029.

Source: Zenobe - Hawthorn Pit 300MW BESS project page →On the map →

Battery Storage · Kilmarnock (south of the town), East Ayrshire, Scotland, UK

Kilmarnock South BESS

  • Stage: Operational (commercial operations began January 2026)was: Operational (commercial operations began 21 Jan 2026)
  • Next milestone: Ongoing operation, including stability serviceswas: Entry into commercial operation (targeted late 2025/early 2026)

Source: Zenobe - Zenobe powers up Kilmarnock South battery storage project →On the map →

Battery Storage · Lister Drive, Tuebrook, Liverpool, Merseyside, England, UK

Lister Drive

  • Stage: Conditionally acquired by GRID in May 2026 (part of 777MW of new projects)was: Contracted - SPA signed 28 May 2026 (conditional acquisition by GRID); consented with Capacity Market contracts, Gate 2 connection Sep 2029, construction expected from early 2027; STP holds exclusivity on 25% stake
  • Next milestone: Completion of acquisition and financingwas: GRID acquisition and financing then construction

Source: Gresham House Energy Storage Fund - Interim Results for period ended 30 June 2026 (RNS) →On the map →

Battery Storage · Magherafelt, Mid Ulster, County Londonderry, Northern Ireland, UK

Magherafelt BESS

  • Stage: Consented (2-hour scheme); revised 4-hour application submitted to Mid Ulster Council in October 2025was: Consented (2-hour scheme), revised 4-hour application under determination
  • Value: Not disclosedwas: Over £100 million (with Coolkeeragh)
  • Next milestone: Council decision on the revised application; construction and operation would take about 9 to 12 months if approvedwas: Mid Ulster Council decision on the revised 4-hour application, then about 9 to 12 months of construction

Source: ABO Energy →On the map →

Battery Storage · North Yorkshire, England, UK

Monet's Garden

  • Status: Livewas: Pipeline
  • Stage: Under construction; financial close May 2026was: Consented/construction-ready - GRID acquisition completed Dec 2025, £141m senior debt concluded 26 May 2026, 25% STP JV equity completed 8 Jun 2026, construction due to start immediately; Gate 2 connection Jul 2027
  • Next milestone: Target energisation H2 2027was: Deal completion then construction start

Source: Gresham House Energy Storage Fund - Interim Results for period ended 30 June 2026 (RNS) →On the map →

Battery Storage · East Rounton, North Yorkshire, England, UK

Mowbray BESS

  • Stage: In planning (application ZB24/02455/HYB submitted to North Yorkshire Council, January 2025)was: In planning
  • Next milestone: Council determination; construction expected to start in 2026 if approvedwas: Council determination (ZB24/02455/HYB); construction anticipated from 2026

Source: NatPower UK - Mowbray →On the map →

Battery Storage · Mullavilly, near Tandragee, County Armagh, Northern Ireland, UK

Mullavilly BESS

  • Stage: Operational (as at November 2021)was: Operational
  • Next milestone: Ongoing operationwas: Ongoing grid-services optimisation

Source: Gore Street Energy Storage Fund RNS →On the map →

Battery Storage · Pembroke (Pembroke Net Zero Centre), Pembrokeshire, Wales, UK

Pembroke BESS

  • Status: Pipelinewas: At tender
  • Stage: Final investment decision taken December 2025; construction planned from H1 2026was: FID taken (Dec 2025); pre-construction - RWE: construction to start H1 2026, no site mobilisation evidenced
  • Next milestone: Construction; commissioning H2 2028, subject to grid connectionwas: Construction from H1 2026; commissioning H2 2028

Source: RWE - RWE to build its largest battery energy storage facility in the UK →On the map →

Battery Storage · Red Scar Business Park, Preston, Lancashire, England, UK

Red Scar

  • Stage: Operational (49MW); scheduled to be taken offline during Q2 2026 for augmentationwas: Operational but scheduled offline Q2 2026 for augmentation (GRID Q1 2026 RNS); recheck next cycle
  • Next milestone: Augmentation, then return to operationwas: Ongoing operation

Source: Gresham House Energy Storage Fund - Factsheet 31 March 2026 →On the map →

Battery Storage · Rufford, near Ollerton, Nottinghamshire, England, UK

Rufford

  • Stage: Operational (7MW); scheduled to be taken offline during Q2 2026 for augmentationwas: Operational but temporarily offline for augmentation (GRID Q1 2026 RNS); recheck next cycle
  • Next milestone: Augmentation, then return to operationwas: Ongoing operation

Source: Gresham House Energy Storage Fund - Factsheet 31 March 2026 →On the map →

Battery Storage · Salisbury, Wiltshire (adjacent to Salisbury substation), England, UK

Salisbury BESS

  • Stage: Operational since April 2024 (SSE Renewables, 50MW/100MWh)was: Operational since April 2024 (50MW/100MWh, SSE Renewables; Harmony divested the consented site to SSE in Aug 2021)
  • Next milestone: Ongoing operationwas: Start of construction (shovel-ready)

Source: SSE Renewables - Salisbury BESS project page →On the map →

Battery Storage · Lerwick, Shetland, Scotland, UK

Shetland BESS

  • Stage: Main construction complete; electrical installation under way (Jun 2026)was: Main construction complete; electrical installation and cold commissioning imminent (Zenobe, Jun 2026)

Source: Zenobe - Shetland Standby Project page →On the map →

Battery Storage · Quidhampton, near Salisbury, Wiltshire, England, UK

SSE Salisbury BESS

  • Stage: Fully operational since April 2024was: Operational

Source: SSE Renewables →On the map →

Battery Storage · Cushaling, County Offaly, Ireland

Statkraft Cushaling BESS

  • Stage: Operational; officially opened February 2026was: Operational
  • Next milestone: Ongoing operation; annual EUR 25,000 Sustainability Fund to begin in 2026was: Benchmark for further long-duration BESS in Ireland

Source: Statkraft Ireland →On the map →

Battery Storage · Tarbert, County Kerry, Ireland

Statkraft Kelwin-2 BESS

  • Stage: Operational since 2021was: Operational
  • Next milestone: Ongoing operationwas: Ongoing reserves/grid services to EirGrid

Source: Statkraft Ireland →On the map →

Battery Storage · Kilathmoy, Kerry-Limerick border, Ireland

Statkraft Kilathmoy BESS

  • Stage: Operational since April 2020was: Operational
  • Next milestone: Ongoing DS3 System Services to EirGridwas: Ongoing reserves/grid services to EirGrid

Source: Statkraft Ireland →On the map →

Battery Storage · Sundon (beside Sundon National Grid substation), Central Bedfordshire, England, UK

Sundon Storage

  • Stage: Consented Jan 2026; part of Ofgem's LDES scheme, under considerationwas: Consented (Jan 2026) and awarded Ofgem LDES cap-and-floor support in Window 1 (30 Jun 2026); pre-construction, full operation targeted 2030
  • Next milestone: Construction start later this decade; fully operational by 2030was: Construction later this decade; full operation targeted 2030

Source: Statera Energy - Sundon planning approval →On the map →

Battery Storage · Wilton International, Redcar, Tees Valley, England, UK

Teesside GigaPark

  • Stage: Consented (planning consent in place)was: Consented / pre-construction
  • Value: Not disclosedwas: £1 billion
  • Next milestone: Construction start planned 2027; grid connection targeted late 2028 or early 2029was: Construction start planned 2027; grid connection targeted late 2028/early 2029

Source: NatPower UK - Teesside →On the map →

Battery Storage · Thorpe Marsh (former power station site), near Barnby Dun, Doncaster

Thorpe Marsh BESS (Fidra Energy)

  • Stage: Financial close reached (September 2025); construction set to begin immediatelywas: In construction
  • Next milestone: Operational from mid-2027was: Operational mid-2027

Source: National Wealth Fund →On the map →

Battery Storage · Uskmouth, Newport, Wales, UK

Uskmouth BESS

  • Stage: Under construction since November 2023was: In construction
  • Next milestone: Energisation and commercial operation, expected 2026was: Energisation and commercial operation

Source: Quinbrook - Uskmouth →On the map →

Battery Storage · near Wakefield (adjacent to Wakefield B substation), West Yorkshire, England, UK

Wakefield B BESS

  • Stage: Consented on appeal 2 July 2026 (APP/X4725/W/25/3368025); pre-constructionwas: Consented on appeal - Wakefield Council refusal of the 99.9MW Heath scheme overturned by the Planning Inspectorate on 2 July 2026; pre-construction
  • Next milestone: Discharge of conditions and start of construction (permission requires start within three years)was: Planning determination

Source: Planning Inspectorate - Appeal decision, land south of Wakefield B Substation →On the map →

Battery Storage · West Burton, near Retford, Nottinghamshire, England, UK

West Burton C BESS

  • Stage: Financial close reached (17 Jul 2026); construction due to start later in 2026was: Consented; 10-year tolling agreement with Drax signed for 250MW/500MWh (Jan 2026); FID expected by Q3 2026, commercial operation target moved to 2028
  • Value: £231m loan facilitieswas: Not disclosed
  • Next milestone: Construction start; fully operational in 2028was: Final investment decision expected H1 2026; operations targeted Q4 2027

Source: Fidra Energy - Fidra Energy reaches financial close on 500MW West Burton C battery energy storage project →On the map →

Battery Storage · Eaglesham Moor, near Eaglesham, East Renfrewshire, Scotland, UK

Whitelee BESS

  • Stage: Operational since October 2022was: Operational
  • Next milestone: Ongoing operation, providing services to the National Gridwas: Ongoing operation in balancing/frequency markets

Source: ScottishPower Renewables →On the map →

Battery Storage · Wishaw, North Lanarkshire, Scotland, UK

Wishaw BESS

  • Stage: Constructed and connected directly to the transmission system; provides Constraint Management Service to the ESOwas: Operational
  • Next milestone: Continued constraint management serviceswas: Operational, delivering constraint-management services

Source: Zenobe - Wishaw case study →On the map →

How this works: each week's published map is compared with the one before, record by record, using a permanent ID for every project. A project re-checked with nothing new to report is not listed. Every change links to the source we checked. How we verify →

Follow

Follow a sector or a project.

Choose what you care about. We email you on a Monday, only when something you follow has changed. One click in any email stops it.

Sectors

Projects

Press “Follow this project” on any change above to add it here.

Ask us

Email a specialist.

Tell us what you're bidding for, or which sector you're watching. We'll reply with the report that covers it, or scope a piece of work.

Email us →