Colne Valley Viaduct, Hertfordshire (representative point on line)·Under wayRail

HS2 Phase One (London–West Midlands)

  • StageCivils works at maximum effort; programme reset under way, new cost and schedule not yet published (Mar 2026)
  • Next milestoneFinish civil works, then start rail systems installation; publish new cost and schedule
  • Last checked1 November 2026
Source: GOV.UK, HS2 6-monthly report to Parliament: March 2026 →

What has changed on this project, and when

  • Next milestone: Finish civil works, then start rail systems installation; publish new cost and schedule2 November 2026 · previously: Complete civils/tunnelling and start track and systems installation across Phase One.
  • Stage: Civils works at maximum effort; programme reset under way, new cost and schedule not yet published (Mar 2026)2 November 2026 · previously: active
  • Value: £43.6bn spent by end Feb 2026; total cost not published2 November 2026 · previously: £45bn+ (Phase 1)