Projects · Rail

Swords–Charlemont corridor, Dublin (pin: Swords)·At tenderRail

MetroLink Dublin

  • StageApproved to proceed to detailed tender (Government Approval Gate 2, 16 September 2026)
  • Value€15.75bn central estimate (range €14.44bn to €17.49bn excluding VAT)
  • Next milestoneEnabling works tenders from late 2026 into 2027; main contract tender packs from Q1 2027; tunnelling and station construction planned from 2028
  • Last checked1 November 2026
Source: National Transport Authority / Transport Infrastructure Ireland (16 Sep 2026) →

What has changed on this project, and when

  • Next milestone: Enabling works tenders from late 2026 into 2027; main contract tender packs from Q1 2027; tunnelling and station construction planned from 20282 November 2026 · previously: Enabling works tenders from late 2026; main contract tender packs from Q1 2027; tunnelling and station construction planned from 2028
  • Next milestone: Enabling works tenders from late 2026; main contract tender packs from Q1 2027; tunnelling and station construction planned from 202824 September 2026 · previously: Three bidders per lot shortlisted; M401 tender stage first, M402 to follow months later (TII)
  • Stage: Approved to proceed to detailed tender (Government Approval Gate 2, 16 September 2026)24 September 2026 · previously: Railway Order GRANTED by An Coimisiun Pleanala October 2025; €2bn allocated in NDP review; procurement beginning 2026; no construction/enabling contracts yet
  • Value: €15.75bn central estimate (range €14.44bn to €17.49bn excluding VAT, Detailed Business Case)24 September 2026 · previously: €7.9bn combined maximum civils contracts excl VAT (TII); €2bn ringfenced in NDP