Dunstown substation, Co. Kildare to Woodland substation, Co. Meath·Under wayPower & Grid
Kildare-Meath Grid Upgrade (Woodland-Dunstown)
- StageStep 6: construction, energisation and benefit sharing; planning permission granted by An Bord Pleanála in March 2025
- Next milestoneOngoing construction; community benefit fund consultation with local groups
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Ongoing construction; community benefit fund consultation with local groups2 November 2026 · previously: Ongoing construction; community benefit fund consultations
- Stage: Step 6: construction, energisation and benefit sharing; planning permission granted by An Bord Pleanála in March 20252 November 2026 · previously: Construction, energisation and benefit sharing
More Power & Grid projects
- Western Isles HVDC Link (Lewis Hub)Arnish Moor / Stornoway, Isle of Lewis to Fanellan (near Beauly)
- Theddlethorpe Flexible Generation ProjectTheddlethorpe, near Mablethorpe, Lincolnshire
- SP Mid Wales (Electricity) Connections Project (SP Manweb)Mid Wales, Powys
- AQUIND InterconnectorPortsmouth to Lovedean, Hampshire, and the English Channel
- Morgan and Morecambe Offshore Wind Farms Transmission AssetsEast Irish Sea and North West England
- Green Gen Vyrnwy FranktonPowys to Lower Frankton, Shropshire
- Cross Border Connection (England)Carlisle to the England-Scotland border, Cumbria
- Powering Up Dublin, Finglas–North WallDublin, Ireland
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.