Dublin, Ireland·In developmentPower & Grid

Powering Up Dublin, Finglas–North Wall

  • StageBest Performing Option for the route published (January 2025); community benefit fund being established
  • Next milestonePlanning consent and construction
  • Last checked1 November 2026
Source: EirGrid, Powering Up Dublin →

What has changed on this project, and when

  • Next milestone: Planning consent and construction2 November 2026 · previously: Inchicore–Poolbeg micro-tunnel route consultation 2026
  • Stage: Best Performing Option for the route published (January 2025); community benefit fund being established2 November 2026 · previously: Construction commencing 2026
  • Status: In development2 November 2026 · previously: Under way
  • Value: Not disclosed24 September 2026 · previously: Programme value per EirGrid