Projects · Power & Grid
Bonnybridge, Cumbernauld, Wishaw corridor, Falkirk & North Lanarkshire·In developmentPower & Grid
Denny to Wishaw Network Upgrade
- StageConsenting; three Section 37 applications submitted to Scottish Ministers, plus Cumbernauld substation extension planning application to North Lanarkshire Council (page dated 26 Jun 2026)
- Next milestoneDetermination of Section 37 and planning applications
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Determination of Section 37 and planning applications2 November 2026 · previously: EIA / Section 37 consent application
- Stage: Consenting; three Section 37 applications submitted to Scottish Ministers, plus Cumbernauld substation extension planning application to North Lanarkshire Council (page dated 26 Jun 2026)2 November 2026 · previously: Consultation complete (final information events Feb 2026); preparing to submit consent applications
More Power & Grid projects
- Western Isles HVDC Link (Lewis Hub)Arnish Moor / Stornoway, Isle of Lewis to Fanellan (near Beauly)
- Theddlethorpe Flexible Generation ProjectTheddlethorpe, near Mablethorpe, Lincolnshire
- SP Mid Wales (Electricity) Connections Project (SP Manweb)Mid Wales, Powys
- AQUIND InterconnectorPortsmouth to Lovedean, Hampshire, and the English Channel
- Morgan and Morecambe Offshore Wind Farms Transmission AssetsEast Irish Sea and North West England
- Green Gen Vyrnwy FranktonPowys to Lower Frankton, Shropshire
- Cross Border Connection (England)Carlisle to the England-Scotland border, Cumbria
- Powering Up Dublin, Finglas–North WallDublin, Ireland
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.