Projects · Power & Grid

Creag Dhubh (near Dalmally) to Inveraray, Argyll & Bute·Under wayPower & Grid

Creag Dhubh to Inveraray 275kV Overhead Line

  • StageIn construction; first steel lattice tower assembled, over 4km of access tracks built (Mar 2026)
  • Next milestoneComplete tower assembly along the route, then commissioning (date not published)
  • Last checked1 November 2026
Source: SSEN Transmission, First tower erected on new Creag Dhubh, Inveraray line →

What has changed on this project, and when

  • Next milestone: Complete tower assembly along the route, then commissioning (date not published)2 November 2026 · previously: Tower erection and stringing ongoing across the Argyll & Kintyre reinforcement
  • Stage: In construction; first steel lattice tower assembled, over 4km of access tracks built (Mar 2026)2 November 2026 · previously: In construction (first tower erected Mar 2026)