Projects · Power & Grid

Westfield converter station, near Ballingry, Fife (Scotland) to Norfolk (England)·In developmentPower & Grid

Eastern Green Link 4 (EGL4)

  • StageConsenting; Fife Council planning applications submitted Dec 2025; EGL4 CPO 2026 made, awaiting confirmation
  • Next milestoneScottish Ministers' CPO confirmation and Fife Council planning determination
  • Last checked1 November 2026
Source: SP Energy Networks, Eastern Green Link 4 →

What has changed on this project, and when

  • Stage: Consenting; Fife Council planning applications submitted Dec 2025; EGL4 CPO 2026 made, awaiting confirmation2 November 2026 · previously: Pre-application / consenting; DCO submission targeted Aug 2026 (Ofgem investment approval Dec 2025, supply-chain contracts signed, but construction not started)
  • Status: In development2 November 2026 · previously: At tender
  • Value: Not disclosed2 November 2026 · previously: ~£3bn total EGL4 contracts awarded (2026)