Projects · Power & Grid

Shipton (near York) to Monk Fryston, plus Osbaldwick substation, North/West Yorkshire·Under wayPower & Grid

Yorkshire GREEN (Green Energy Enablement)

  • StagePreparatory works began in autumn 2024
  • Next milestoneConstruction completion expected by 2028
  • Last checked1 November 2026
Source: National Grid, Yorkshire GREEN →

What has changed on this project, and when

  • Next milestone: Construction completion expected by 20282 November 2026 · previously: Completion targeted by 2028
  • Stage: Preparatory works began in autumn 20242 November 2026 · previously: In construction
  • Value: Not disclosed2 November 2026 · previously: ~£524m (reported by T&D World)