Immingham to Theddlethorpe, Lincolnshire (storage in offshore Viking depleted gas fields)·In developmentCarbon Capture

Viking CCS CO2 Transport & Storage (Harbour Energy / bp)

  • StageOnshore pipeline DCO secured Apr 2025; FEED completed Q1 2025; development funding approved (Jul 2026); pre-FID
  • Next milestoneFID, targeted in this Parliament, subject to project readiness and affordability
  • Last checked1 November 2026
Source: Energy-pedia, Viking CCS development funding approved →

What has changed on this project, and when

  • Next milestone: FID, targeted in this Parliament, subject to project readiness and affordability2 November 2026 · previously: Government business-model agreement / FID
  • Stage: Onshore pipeline DCO secured Apr 2025; FEED completed Q1 2025; development funding approved (Jul 2026); pre-FID2 November 2026 · previously: DCO granted Apr 2025; DESNZ Viking CCUS Development Fund grant agreed (CMA SAU report 15 Apr 2026); pre-FID