Projects · Carbon Capture

Connah's Quay, Deeside, Flintshire, Wales·In developmentCarbon Capture

Connah's Quay Low Carbon Power (Uniper, HyNet)

  • StageDCO (EN010166) at Secretary of State decision stage; examination completed; decision due 9 Dec 2026
  • Next milestoneDCO decision (due 9 Dec 2026)
  • Last checked1 November 2026
Source: Planning Inspectorate, Connah's Quay Low Carbon Power (EN010166) →

What has changed on this project, and when

  • Next milestone: DCO decision (due 9 Dec 2026)2 November 2026 · previously: Contract award / FID
  • Stage: DCO (EN010166) at Secretary of State decision stage; examination completed; decision due 9 Dec 20262 November 2026 · previously: DCO application (EN010166) in examination, ExA first written questions Feb 2026