Projects · Power & Grid

Ballyadam converter station, Carrigtwohill, Co. Cork (subsea to Brittany, France)·Under wayPower & Grid

Celtic Interconnector

  • StageIn construction (Step 6); HVDC subsea cable burial and protection in Irish waters completed (Sep 2026)
  • Next milestoneCommissioning expected Q4 2028
  • Last checked1 November 2026
Source: EirGrid, Celtic Interconnector →

What has changed on this project, and when

  • Next milestone: Commissioning expected Q4 20282 November 2026 · previously: Energisation revised to spring 2028; remaining subsea cable installation through 2026-27
  • Stage: In construction (Step 6); HVDC subsea cable burial and protection in Irish waters completed (Sep 2026)2 November 2026 · previously: In construction (Step 6); AC route complete, DC route Phase 2 ~70%; commissioning now expected spring 2028
  • Value: Not disclosed (€530.7m EU Connecting Europe Facility grant awarded)2 November 2026 · previously: ≈€1bn+ project, incl. €530.7m EU Connecting Europe Facility grant (EirGrid)

More Power & Grid projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.