The Wire · Rail

HS2 Ltd··ReleaseRail

HS2 slides first 55-metre span of new Saltley Viaduct into place

By Anthony at GridteamAI

Balfour Beatty VINCI installed a 55-metre steel span over the Birmingham to Derby lines at Saltley during the August bank holiday, moving it about 125 metres into position on self-propelled modular transporters. The span is the first of four phases of a taller replacement viaduct that will let HS2 trains pass beneath; the railway reopened on schedule on 1 September.

Our readInstalling the span within a bank-holiday possession and reopening on time is the interface delivery HS2 now needs to repeat three more times at Saltley.
Read the announcement at HS2 Ltd →