Projects · Flood & Coastal

Bridgwater, Somerset·Under wayFlood & Coastal

Bridgwater Tidal Barrier

  • StageUnder construction; moving to permanent reinforced concrete foundations (Oct 2026)
  • Value£249m (2024 business case; revised forecast pending)
  • Next milestoneBarrier superstructure construction due to begin early 2027
  • Last checked1 November 2026
Source: Somerset Council, Bridgwater Tidal Barrier Scheme: Design Efficiency Review →

What has changed on this project, and when

  • Next milestone: Barrier superstructure construction due to begin early 20272 November 2026 · previously: Construction of permanent barrier structures (Kier continuation contract)
  • Stage: Under construction; moving to permanent reinforced concrete foundations (Oct 2026)2 November 2026 · previously: active
  • Value: £249m (2024 business case; revised forecast pending)2 November 2026 · previously: £249m