Frenchpark / Ballaghaderreen, Co. Roscommon·Under wayTransport

N5 Ballaghaderreen to Scramoge

  • StageUnder construction; Section 1 (Frenchpark Bypass, 7 km) opened 26 March 2026
  • ValueAbout €450 million
  • Next milestoneComplete remaining scheme; TII aims for completion next year (2027)
  • Last checked1 November 2026
Source: Transport Infrastructure Ireland →

What has changed on this project, and when

  • Next milestone: Complete remaining scheme; TII aims for completion next year (2027)2 November 2026 · previously: Complete remaining sections; full scheme completion in 2027
  • Stage: Under construction; Section 1 (Frenchpark Bypass, 7 km) opened 26 March 20262 November 2026 · previously: Under construction; Section 1 opened Mar 2026, remainder ongoing
  • Value: About €450 million2 November 2026 · previously: ~€450 million
  • Next milestone: Complete remaining sections; full scheme completion in 202729 September 2026 · previously: Complete remaining sections; full scheme opening 2026/2027