A9 between Tomatin and Moy, around 15 miles south of Inverness, Highland·Under wayTransport

A9 Dualling: Tomatin to Moy

  • StageUnder construction
  • Value£296 million Scottish Government investment
  • Next milestoneTransfer of traffic onto the new northbound carriageway, then completion
  • Last checked1 November 2026
Source: Transport Scotland →

What has changed on this project, and when

  • Next milestone: Transfer of traffic onto the new northbound carriageway, then completion2 November 2026 · previously: Completion expected spring 2028
  • Value: £296 million Scottish Government investment2 November 2026 · previously: £296m Scottish Government investment (Balfour Beatty contract £185m)
  • Next milestone: Completion expected spring 202824 September 2026 · previously: Completion of dualling expected 2028
  • Value: £296m Scottish Government investment (Balfour Beatty contract £185m)24 September 2026 · previously: £185 million (Balfour Beatty contract)