Projects · Transport

A47/A11 Thickthorn interchange, south-west of Norwich, Norfolk·Under wayTransport

A47/A11 Thickthorn Junction improvement

  • StageUnder construction (Cantley Wood bridge beams lifted September 2026)
  • Value£216 million to £239 million (National Highways cost band)
  • Next milestoneA47 contraflow switch in October 2026 (westbound two lanes, eastbound one lane through to autumn 2027); Cantley Wood bridge due for completion this winter; completion 2028/29
  • Last checked1 November 2026
Source: National Highways →

What has changed on this project, and when

  • Next milestone: A47 contraflow switch in October 2026 (westbound two lanes, eastbound one lane through to autumn 2027); Cantley Wood bridge due for completion this winter; completion 2028/292 November 2026 · previously: Eastbound carriageway to one lane with westbound in contraflow from around October 2026 to July 2027; Cantley Wood bridge due winter 2026; completion 2028/29
  • Stage: Under construction (Cantley Wood bridge beams lifted September 2026)2 November 2026 · previously: Under construction
  • Value: £216 million to £239 million (National Highways cost band)2 November 2026 · previously: £216-239 million (National Highways cost band)
  • Next milestone: Eastbound carriageway to one lane with westbound in contraflow from around October 2026 to July 2027; Cantley Wood bridge due winter 2026; completion 2028/2924 September 2026 · previously: Contraflow switch October 2026; completion 2028/29