Projects · Renewables

Near Scunthorpe (Manton/Gunness), North Lincolnshire·In developmentRenewables

Little Crow Solar Park

  • StageDCO granted 5 April 2022; non-material change approved 15 June 2023
  • Next milestoneConstruction start
  • Last checked1 November 2026
Source: Planning Inspectorate (EN010101) →

What has changed on this project, and when

  • Next milestone: Construction start2 November 2026 · previously: Commencement of construction / final investment decision
  • Stage: DCO granted 5 April 2022; non-material change approved 15 June 20232 November 2026 · previously: DCO consented (2022), pre-construction

More Renewables projects