Projects · Renewables

East of Long Stratton, south of Great Moulton, South Norfolk·In developmentRenewables

East Pye Solar Project

  • StageDCO application accepted for examination (2 April 2026)
  • Next milestoneExamination of the DCO application, then recommendation to the Secretary of State
  • Last checked1 November 2026
Source: Island Green Power →

What has changed on this project, and when

  • Next milestone: Examination of the DCO application, then recommendation to the Secretary of State2 November 2026 · previously: Close of examination, set for 23 February 2027 in the draft timetable, then the Examining Authority's recommendation
  • Stage: DCO application accepted for examination (2 April 2026)2 November 2026 · previously: In examination (preliminary meeting 15 September 2026)
  • Next milestone: Close of examination, set for 23 February 2027 in the draft timetable, then the Examining Authority's recommendation13 October 2026 · previously: Six-month examination and Examining Authority recommendation
  • Stage: In examination (preliminary meeting 15 September 2026)13 October 2026 · previously: Accepted / in examination (accepted April 2026)