Green Hill Solar Farm

  • StageConsented (DCO granted 8 October 2026)
  • Next milestoneDischarge of requirements ahead of construction. No construction start date has been published.
  • Last checked1 November 2026
Source: Planning Inspectorate / GOV.UK (EN010170) →

What has changed on this project, and when

  • Next milestone: Discharge of requirements ahead of construction. No construction start date has been published.13 October 2026 · previously: Examination and Examining Authority recommendation
  • Stage: Consented (DCO granted 8 October 2026)13 October 2026 · previously: Examination closed (10 April 2026); recommendation submitted/awaiting Secretary of State decision

More Renewables projects