Projects · Renewables

Buckinghamshire, near East Claydon/Granborough (land around East Claydon substation)·In developmentRenewables

Rosefield Solar Farm

  • StageExamination closed; recommendation report in preparation
  • Next milestoneRecommendation to the Secretary of State due by 24 November 2026, with a decision due within three months after that
  • Last checked1 November 2026
Source: Planning Inspectorate (EN010158) →

What has changed on this project, and when

  • Next milestone: Recommendation to the Secretary of State due by 24 November 2026, with a decision due within three months after that27 October 2026 · previously: Close of examination and recommendation to Secretary of State (2026)
  • Stage: Examination closed; recommendation report in preparation27 October 2026 · previously: In examination

More Renewables projects