Projects · Oil & Gas
Sullom Voe, Shetland·Under wayOil & Gas
Sullom Voe Terminal Transformation
- StageNew stabilisation facility in progress; Shetland grid connection being assessed
- Next milestoneComplete new stabilisation facility; decision on Shetland grid connection
- Last checked1 November 2026
What has changed on this project, and when
- Next milestone: Complete new stabilisation facility; decision on Shetland grid connection2 November 2026 · previously: Complete stabilisation unit commissioning; grid connection
- Stage: New stabilisation facility in progress; Shetland grid connection being assessed2 November 2026 · previously: Stabilisation unit largely commissioned; workforce restructuring underway
More Oil & Gas projects
- Rosebank Field Development (Phase 1)West of Shetland, Faroe-Shetland Channel, Block 213/27, ~130 km NW of Shetland
- Jackdaw Field DevelopmentCentral North Sea, Block 30/2a, ~250 km E of Aberdeen (tie-back to Shearwater)
- Cambo Field Development (Phase 1)West of Shetland, Block 204/10, ~130 km W of Shetland (deepwater ~1,070 m)
- Pilot Field DevelopmentCentral North Sea, Block 21/27a (Licence P2244), ~150 km E/ENE of Aberdeen
- Selene Gas Field DevelopmentSouthern North Sea, Block 48/8b (Licence P2437), Sole Pit Basin, ~60 km off East Anglia
- Fotla Field DevelopmentGreater Britannia Area, Central North Sea, ~130-200 km NE of Aberdeen
- Kyla Field Redevelopment (Triton Area)Central North Sea, Block 29/2c, ~20 km SE of the Triton FPSO
- Ninian Hub DecommissioningNorthern North Sea, Blocks 3/3a & 3/8, ~120 km E of Shetland
- Open the Map Explorer at this projectThe map
- Browse checked projects by sectorEvery project page
- See this week's changes on the mapFollow a sector or a project
The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.