Projects · Oil & Gas

South Brae field, Central/Northern North Sea, Block 16/7a, ~270 km NE of Aberdeen·In developmentOil & Gas

Brae Alpha Decommissioning

  • StageStill producing; topsides decommissioning programmes at consultation draft (Rev 07, May 2026); CoP potentially as late as Q4 2027
  • Next milestoneOPRED approval of decommissioning programmes; cessation of production
  • Last checked1 November 2026
Source: TAQA Bratani (GOV.UK), Brae Alpha Topsides, Central Brae, West Brae and Sedgwick Decommissioning Programmes, consultation draft →

What has changed on this project, and when

  • Next milestone: OPRED approval of decommissioning programmes; cessation of production2 November 2026 · previously: Offshore heavy-lift removal campaign and onshore dismantling
  • Stage: Still producing; topsides decommissioning programmes at consultation draft (Rev 07, May 2026); CoP potentially as late as Q4 20272 November 2026 · previously: Platform still producing, CoP expected late 2026; Allseas removal contract signed Sep 2025; offshore heavy-lift removal slated 2028-2032
  • Status: In development2 November 2026 · previously: At tender

More Oil & Gas projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.