Projects · Housing & Development

Sunday's Well, Cork City·Under wayHousing & Development

St Kevin's Hospital, Cork

  • StagePhase 1 (97 homes) under construction; Phase 2 (170 homes) in further detailed design
  • Next milestonePhase 1 completion; Phase 2 construction tender
  • Last checked1 November 2026
Source: Land Development Agency →

What has changed on this project, and when

  • Next milestone: Phase 1 completion; Phase 2 construction tender2 November 2026 · previously: Phase 2 construction tender next; no completion date published as of October 2026
  • Stage: Phase 1 (97 homes) under construction; Phase 2 (170 homes) in further detailed design2 November 2026 · previously: Phase 1 under construction; Phase 2 in detailed design
  • Next milestone: Phase 2 construction tender next; no completion date published as of October 202627 October 2026 · previously: First homes delivered (2026/2027)
  • Stage: Phase 1 under construction; Phase 2 in detailed design27 October 2026 · previously: Active construction

More Housing & Development projects