Middlewood Locks, Salford (near Salford Central)·Under wayHousing & Development

Middlewood Locks

  • Stage1,306 homes delivered; National Housing Bank funding for the 909-home Phase 4 agreed July 2026
  • Value£1bn
  • Next milestoneStart on site of the 909-home Phase 4, hoped for early 2027, with first homes available for occupation in 2030
  • Last checked1 November 2026
Source: Scarborough Group, developer/operator record · reported Construction Enquirer →

What has changed on this project, and when

  • Next milestone: Start on site of the 909-home Phase 4, hoped for early 2027, with first homes available for occupation in 20302 November 2026 · previously: Start on site of the 909-home Phase 4 targeted for early 2027, first occupations 2030
  • Stage: 1,306 homes delivered; National Housing Bank funding for the 909-home Phase 4 agreed July 20262 November 2026 · previously: Around half delivered, 909-home Phase 4 funded July 2026, start on site targeted early 2027
  • Next milestone: Start on site of the 909-home Phase 4 targeted for early 2027, first occupations 203020 October 2026 · previously: Start on site of the 909-home tower phase (2026)
  • Stage: Around half delivered, 909-home Phase 4 funded July 2026, start on site targeted early 202720 October 2026 · previously: Around half delivered; next 909-home tower phase funded July 2026