Welborne, north of Fareham, Hampshire·Under wayHousing & Development

Welborne Garden Village

  • StageM27 J10 improvement scheme for Welborne opening in phases ahead of schedule, first phase from 14 Sep 2026 (Hampshire CC, 3 Sep 2026); occupation capped at 1,160 homes until J10 is fully operational
  • Next milestoneJ10 eastbound and westbound on-slips to open in autumn 2026, giving full M27 access
  • Last checked1 November 2026
Source: Hampshire County Council, Mid-September phased opening for M27 J10 improvement scheme →

What has changed on this project, and when

  • Next milestone: J10 eastbound and westbound on-slips to open in autumn 2026, giving full M27 access2 November 2026 · previously: Improved M27 junction 10 due to open in 2026; no exact date published as of October 2026
  • Stage: M27 J10 improvement scheme for Welborne opening in phases ahead of schedule, first phase from 14 Sep 2026 (Hampshire CC, 3 Sep 2026); occupation capped at 1,160 homes until J10 is fully operational2 November 2026 · previously: First phase approved and under construction; M27 J10 works underway
  • Next milestone: Improved M27 junction 10 due to open in 2026; no exact date published as of October 202627 October 2026 · previously: First residents expected winter 2026