Little Island, Cork Harbour, Co. Cork·Under wayData Centres

Little Island data centre (former Mitsui Denman site), Cork

  • StageBuilding 1 fully constructed, fit-out outstanding (Mar 2025); grid connection agreement issued 18 Jul 2024; permission extended to 2027
  • Value€14.2m+ (building 1)
  • Next milestoneFit-out of building 1; second building
  • Last checked1 November 2026
Source: Irish Examiner, Little Island data centre permission extension →

What has changed on this project, and when

  • Next milestone: Fit-out of building 1; second building2 November 2026 · previously: Fit-out; second building
  • Stage: Building 1 fully constructed, fit-out outstanding (Mar 2025); grid connection agreement issued 18 Jul 2024; permission extended to 20272 November 2026 · previously: Building 1 shell complete, awaiting grid connection/fit-out; permission extended to 2027