Cruiserath Road, Mulhuddart, Dublin 15·In developmentData Centres

AWS Mulhuddart campus (three data centres)

  • StagePermission granted with revised conditions on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction
  • Next milestoneConstruction start
  • Last checked1 November 2026
Source: An Coimisiún Pleanála →

What has changed on this project, and when

  • Next milestone: Construction start2 November 2026 · previously: Execute PPA; construction start
  • Stage: Permission granted with revised conditions on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction2 November 2026 · previously: Permission granted on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction
  • Stage: Permission granted on appeal by An Coimisiún Pleanála (19 December 2025, case 318180); pre-construction29 September 2026 · previously: Planning granted (Dec 2025); pre-construction

More Data Centres projects