Projects · Data Centres

Kao Data campus, Harlow, Essex·In developmentData Centres

Kao Data Harlow campus expansion (KLON-03/04)

  • StageKLON-03 (17.6MW) announced Mar 2025; two further buildings planned (Sep 2025); Nebius 22MW ten-year lease signed
  • Next milestoneConstruction of KLON-03 and planning for further buildings
  • Last checked1 November 2026
Source: Kao Data, developer/operator record · reported DatacenterDynamics →

What has changed on this project, and when

  • Next milestone: Construction of KLON-03 and planning for further buildings2 November 2026 · previously: KLON-03 energisation; KLON-04 consent
  • Stage: KLON-03 (17.6MW) announced Mar 2025; two further buildings planned (Sep 2025); Nebius 22MW ten-year lease signed2 November 2026 · previously: KLON-03 under construction; further phases in planning
  • Status: In development2 November 2026 · previously: Under way
  • Value: Not disclosed2 November 2026 · previously: £1.7bn (Nebius UK deployment)

More Data Centres projects

The Wire is a free email every weekday morning. It brings you what regulators, government departments, network operators and developers have published, each item dated and linked to its source. Sign up and it lands in your inbox.