Projects · Health & Education Estates

St James's Hospital campus, Dublin 8·Under wayHealth & Education Estates

National Children's Hospital, Dublin

  • StageIn construction; completion and validation phase (over 2,850 of 5,728 rooms validated, March 2026); substantial completion will miss end-April deadline
  • Value€1.6bn incurred by NPHDB to end of February 2026 (including VAT)
  • Next milestoneNew substantial completion date awaited, followed by c.7-month commissioning before opening
  • Last checked1 November 2026
Source: NPHDB, Oireachtas committee evidence (official record) →

What has changed on this project, and when

  • Next milestone: New substantial completion date awaited, followed by c.7-month commissioning before opening2 November 2026 · previously: Substantial completion and handover of keys; opening c.7 months later
  • Stage: In construction; completion and validation phase (over 2,850 of 5,728 rooms validated, March 2026); substantial completion will miss end-April deadline2 November 2026 · previously: In construction, completion/validation phase
  • Value: €1.6bn incurred by NPHDB to end of February 2026 (including VAT)2 November 2026 · previously: €1.6bn incurred to Feb 2026; final cost above €2.24bn approved budget (RTE/Oireachtas)