THE GRIDTEAMAI NUMBER · No. 1 · November 2026

The grid queue: 738 GW asked, 283 GW got a date

Before NESO's connections reform, projects adding up to 738 GW were queuing to connect to Great Britain's electricity grid, about four times the capacity the Clean Power 2030 plan needs. The reform, decided on 8 December 2025, gave 283 GW of generation and storage a dated connection offer and parked the rest. Here is where the queue stood, what came out of it, and what the register shows today. Every figure traces to a NESO, Ofgem or government document, dated.

Share on X

738 GW

The queue before reform

NESO, 8 July 2025. The same official series read 722 GW at the end of September 2024 and 739 GW in December 2024.

283 GW

Given a dated offer by the reform

NESO, 8 December 2025: 132 GW due by 2030, 151 GW due 2031 to 2035.

204 to 231 GW

What Clean Power 2030 needs installed, in total

DESNZ Clean Power 2030 Action Plan ranges, as totalled by NESO.

What was in the queue

The queue is the list of projects that hold a contract to connect to the transmission or distribution network but have not yet connected. It grew tenfold in five years. Government and Ofgem counted it at 722 GW at the end of September 2024, the Clean Power 2030 Action Plan put it at 739 GW that December, and NESO used 738 GW in July 2025 when it opened the reform's evidence window. Those three figures are the same count, taken on different days; they include demand projects and projects on the distribution networks as well as the transmission grid. Set against them, the whole of Great Britain's installed generation and storage was about 111 GW, and the Clean Power 2030 plan calls for 204 to 231 GW installed by the end of the decade. NESO's own phrase was "around four times Great Britain's projected need by 2030".

What the reform did

On 8 December 2025 NESO published the results of its "Gate 2 to Whole Queue" process. Projects that met the readiness test and fitted the 2030 and 2035 plans moved into a delivery pipeline with a dated offer: 132 GW aligned with Clean Power 2030, and a further 151 GW for 2031 to 2035, 283 GW in all, plus 99 GW of transmission-connected demand. Projects that were ready but not needed for the plan went to Gate 1, with no connection date: about 217 GW, of which batteries were 153 GW. More than 300 GW of the old queue did not move forward at all.

Table 1: The delivery pipeline by technology (GW)

Source: NESO press release, 8 December 2025, "Connections delivery pipeline by technology". Columns exactly as NESO published them.

TechnologyPrioritised for 2030Prioritised for 2035Gate 1 (not prioritised)
Battery storage34.548.7152.9
Offshore wind32.137.84.5
Solar29.929.135.9
Onshore wind13.14.813.4
Transmission-connected demand11.886.70.0
Long-duration storage4.64.54.6
Unabated gas4.21.83.8
Interconnectors3.69.71.2
Nuclear3.33.30.0
Low-carbon dispatchable power3.39.70.0
Non-GB generation1.81.80.0
Other (tidal, hydro, other)1.20.10.0
Total, generation and storage (demand row excluded)132151217

Gate 1 excludes projects that chose not to be prioritised and projects that did not apply. NESO's table columns sum to 216.3 GW; NESO's webinar deck states 217 GW. We print 217.

Where 738 GW ended up: 283 GW with a date, 217 GW withoutHorizontal stacked bars of GW by technology: prioritised for 2030, prioritised for 2035, and Gate 1 with no connection date. Values as in Table 1.Where 738 GW ended up: 283 GW with a date, 217 GW withoutPrioritised for 2030Prioritised for 2035Gate 1, no date0 GW50100150200Battery storage34.548.7152.9236.1Solar29.929.135.994.9Offshore wind32.137.874.4Onshore wind31.3Interconnectors14.5Long-duration storage13.7Low-carbon dispatchable power13.0Unabated gas9.8Nuclear6.6Non-GB generation3.6Other (tidal, hydro, other)1.3NESO, 8 December 2025. Chart: GridteamAI.Where 738 GW ended up: 283 GW with a date, 217 GW withoutWhere 738 GW ended up:283 GW with a date, 217 GW withoutPrioritised for 2030Prioritised for 2035Gate 1, no dateBattery storage34.548.7152.9236.1Solar29.929.135.994.9Offshore wind32.137.874.4Onshore wind31.3Interconnectors14.5Long-duration storage13.7Low-carbon dispatchable power13.0Unabated gas9.8Nuclear6.6Non-GB generation3.6Other (tidal, hydro, other)1.3NESO, 8 December 2025. Chart: GridteamAI.

Where it stands today

NESO has not revised the 283 GW. What has moved is the paperwork behind it. By 10 June 2026 NESO and the network companies had issued offers to 713 of the 1,223 projects due by 2030, worth about 37 GW. The deadline for the rest of the 2030 offers was moved to 31 October 2026, and the 2031 to 2035 offers to 31 January 2027, with Ofgem's agreement on 2 October 2026. Ofgem's September 2026 assessment of NESO's performance records that the queue was cut "from approximately 750 GW to 200-250 GW" but that the reform was not delivered on time.

The transmission register tells the same story from the bottom up. On 13 October 2026 it listed 1,840 unbuilt entries adding up to 604 GW of new transmission-connected capacity. Of that, 293 GW already carried a Gate 1 label, 15 GW a countersigned Gate 2 offer, and 296 GW no gate yet: an offer issued but not yet signed, or still to come.

604 GW

unbuilt capacity on the transmission register, 13 October 2026

293 GW

of it already labelled Gate 1

15 GW

with a countersigned Gate 2 offer so far

Table 2: Unbuilt transmission contracts by technology, 13 October 2026 (GW, number of entries)

Source: NESO TEC register, file dated 13 October 2026, entries with any status other than Built, new capacity summed. Transmission-connected and large embedded projects only; this register does not include distribution-only projects or demand.

TechnologyGWEntries
Battery storage188.1732
Solar (with or without storage)186.1526
Offshore wind96.8107
Gas41.930
Onshore wind (with or without storage)33.5314
Nuclear23.722
Onshore wind with solar18.464
Pumped storage10.817
Other4.828
Total604.11,840
When the contracts say they connectVertical bars of GW of unbuilt transmission contracts by contracted connection year, 2025 to 2039.When the contracts say they connectContracted by 20302031 and later0255075100 GW4.6202512.7202616.2202733.5202844.4202935.4203056.8203131.9203280.9203371.0203466.1203533.0203696.1203714.520385.12039NESO TEC register, 13 October 2026. Chart: GridteamAI. Earlier years total 2.0 GW.When the contracts say they connectWhen the contracts saythey connectContracted by 20302031 and later20254.6202612.7202716.2202833.5202944.4203035.4203156.8203231.9203380.9203471.0203566.1203633.0203796.1203814.520395.1Earlier years total 2.0 GW.NESO TEC register, 13 October 2026. Chart: GridteamAI.

Figures rounded to 0.1 GW; the years sum to 604.2 GW.

Scotland

Scotland holds 155 GW of the 604 GW: 82 GW in the north of Scotland (SSEN Transmission's area) and 73 GW in the south (SP Transmission's). Offshore wind is 36.5 GW of it, batteries 65 GW, onshore wind 26.5 GW, pumped storage 10.4 GW and solar 12 GW. The largest entries are the ScotWind and INTOG offshore wind farms, each with a connection date in the early 2030s and almost all still at the scoping stage, and a new generation of pumped-storage schemes in the Highlands.

Table 3: The ten largest unbuilt Scottish entries on the register, 13 October 2026

ProjectDeveloperAreaConnection siteMWContracted dateStatus
Machair Offshore Wind FarmScottishPower RenewablesSouthMachair offshore substation2,000Sep 2033Scoping
Marram WindMarramwind LtdNorthLongside 400kV2,000Oct 2033Scoping
Arven Offshore Wind FarmArven Offshore Wind Farm LtdNorthNorthern Shetland 400kV1,800Oct 2033Scoping
Glen Earrach pumped storageGlen Earrach EnergyNorthGlen Earrach 400kV1,800Oct 2035Scoping
North-East Offshore Hybrid AssetNational Grid Interconnector HoldingsNorthKintore1,800Jun 2037Scoping, Gate 1
HavbredeyHavbredey LtdNorthNew Dounreay 400kV1,500Oct 2033Scoping, Gate 1
OWPL WindfarmOffshore Wind Power LtdNorthBanniskirk 400kV1,500Dec 2030Scoping
Phoenix 1B Offshore Wind FarmMorven Offshore WindSouthnear Branxton 400kV1,500Oct 2033Scoping
Fearna pumped storage 2Fearna PSH LtdNorthFearna 400kV1,495Nov 2036Awaiting consents
Caledonia Offshore Wind FarmCaledonia Offshore Wind Farm LtdNorthGreens 400kV1,400Oct 2032Scoping

"North" is SSEN Transmission's area, "South" is SP Transmission's. Where a project appears in the register as two stages, the larger stage is shown. The full Scottish list is available from press@gridteamai.com.

Method and sources

  • The queue before reform: 722 GW is from the DESNZ and Ofgem open letter "Aligning grid connections with strategic plans", 5 November 2024 (correct at end-September 2024, transmission and distribution, including demand). 739 GW is from the Clean Power 2030 Action Plan, DESNZ, 13 December 2024. 738 GW is from NESO's press release "Clean energy projects to be prioritised in grid connections reform as evidence window opens", 8 July 2025. NESO's later documents say "over 770 GW" (August 2025) and "exceeding 800 GW" (October 2025); we use 738 GW because it is the figure NESO put against the Clean Power comparison.
  • The reform results: NESO press release "NESO implements electricity grid connection reforms to unlock investment in Great Britain", 8 December 2025, and the NESO webinar deck "Connections Reform Webinar: Delivery pipeline outcomes", 8 December 2025. The zonal detail is in NESO's "Connections Reform Detailed Results Data", December 2025.
  • Clean Power 2030 need: DESNZ, "Clean Power 2030 Action Plan: A new era of clean electricity", 13 December 2024, Table 1; the 204 to 231 GW total is NESO's sum of those ranges (NESO press release, 20 December 2024, repeated 8 December 2025).
  • Progress since: NESO press release "NESO and electricity networks issue offers to over half of energy projects needed by 2030", 10 June 2026; Ofgem, "Agreement to a further alternative timetable for issuing Gate 2 Phase 1 connection offers", 2 October 2026; Ofgem, "End-scheme assessment of NESO's BP3 performance", 2 September 2026.
  • Today's register: NESO Transmission Entry Capacity (TEC) register, file dated 13 October 2026, NESO Open Data Licence. We count entries whose status is not Built and sum the "MW Increase / Decrease" column. The register covers transmission-connected and large embedded generation and storage, not distribution-only projects or demand, so it is not the same count as the 738 GW. Gate labels appear in the register only once an offer is countersigned.
  • Technology groups in Tables 2 and 3 are ours: an entry listed as storage with solar is counted as solar; storage with onshore wind as onshore wind.

Cite as

GridteamAI, "The grid queue: 738 GW asked, 283 GW got a date", The GridteamAI Number No. 1, November 2026, gridteamai.com/numbers/grid-queue-2026, from NESO, Ofgem and DESNZ sources dated 2024 to 2026.

Next number: February 2027, the Contracts for Difference AR8 results decoded.