← GridteamAI

Purchase access

This is part of the paid GridteamAI Quarterly Sector Report.

Purchase access — book@gridteamai.com

£295 single volume · £995/yr annual · Team £2,495 · Enterprise £4,995 · Corporate £9,995. Secure checkout coming soon; email to purchase today.

Buy · £295Annual £995/yr↓ Full report PDF · buy
GridteamAI · Quarterly Sector Report · Ireland series · IE001
Ireland Power & Grid — a €13.8bn network settlement, a data-centre connection reset, and a grid that cannot yet move its own wind
Series consistency · canonical Gap-series system
A4 · 210 × 297 mm · 3 mm bleed (not shown)
UK / Irish English · ~30 pp · v1.0 / Q3 2026
FRONT MATTERi · Cover · ink · full bleed
GridteamAI
Quarterly Sector Report
IE001
Power & Grid
by GridteamAI
IE · PR6 · Interconnection · Dispatch-down Republic of Ireland · 2026

Ireland Power
& Grid.

The connection bargain — Ireland’s grid reopens the door it can’t yet walk through.

gridteamai.com · book@gridteamai.com v1.0 · 2026 Consultancy-grade deliverable
05 — 06Executive summary · spread
Ireland Power & Grid · Executive summary05
00 · Executive Summary A two-page brief

Six observations summarise the twelve findings that follow.

In December 2025 the Commission for Regulation of Utilities did two things within a fortnight: it set the price control that governs five years of network spending, and it reopened grid access to the large electricity users it had effectively frozen out since 2021. On paper, the framework for Ireland’s electricity grid is now settled. In the wires, it is not.

Six observations stand out: the connection door has reopened on terms the grid cannot yet honour; the money has been committed (€13.8bn at PR6); the grid is losing wind to itself (11.3% dispatch-down, a constraint story); adequacy leans on hired gas and cables to Britain and France; the two biggest unlocking projects are the furthest behind; and the 80%-by-2030 arithmetic no longer closes on the current grid.

The consequence: for the rest of this decade, value on the Irish grid is decided by location and by firmness. The winners will not be the parties with the most megawatts; they will be the parties in the right place, with the firmest position, against an import-dependent and temporarily gas-backed system.

GridteamAI · Quarterly Sector Report · IE001Republic of Ireland · 2026
06Executive summary · continued

The frame is settled; delivery is the structural test.

Within a fortnight in December 2025 the CRU set the PR6 price control (€13.8bn to 2030, up from €7.6bn at PR5) and published its Large Energy User connection decision (CRU2025236), ending the de-facto Dublin freeze. A new large site above 10 MVA must now match 100% of its demand with new dispatchable generation, participate in the market, and source 80% of its power from new Irish renewables on a six-year glide path.

The interlock across the Ireland series is structural

The grid is the connections-side of an integrated picture: it interlocks with the data-centre load that drives it (IE002), the offshore wind consented but delayed (IE003), the long-duration storage not promised until end-2028 (IE004) and the nuclear-firmed French import that Celtic brings from 2028 (IE007). A renewable target missed by 2030 may be a generation problem, an interconnection problem, or a network-delivery problem — telling them apart is the analytical task.

The shape of this volume. § 1 sets out the headline figures. § 2 develops twelve findings, each confidence-annotated. A chapter-weight pull at p. 14 anchors the argument. § 3 decodes the connection bargain — the Large Energy User reset, ECP-GSS and PR6. § 4 sets out the pipeline, the projects and interconnection. § 5 decodes curtailment, storage and the 80%-by-2030 test. § 6 sets out recommendations, with a one-page tear-out at p. 25.

Executive summary · ends§ 1 · The headline figures · p. 07
09 · FIG. 1§ 1 · PR6 step-change · €7.6bn → €13.8bn
§ 1 · The headline figures09
Figure 1 · The PR6 step-changeCRU · 16 Dec 2025

A €13.8 billion network settlement — close to double PR5.

The PR6 baseline for 2026–2030 is €13.8bn, rising to €18.9bn under the high-demand scenario, against €7.6bn allowed at PR5. ESB Networks takes €11.4bn (distribution); EirGrid €2.4bn (transmission). Household network charges rise about €12–21 a year; a large user’s pass-through is materially larger.

NETWORK INVESTMENT · € BILLION · FIVE-YEAR ALLOWANCE05101520€7.6bnESB · €11.4BNEIRGRID · €2.4BN€13.8bn+82%€18.9bnHIGH-DEMANDSCENARIOPR5 · 2020–25PR6 BASELINE · 2026–30CRU DECISION · DEC 2025PR6 HIGH SCENARIOIF DEMAND RUNS HIGHPR6 nearly doubles the network allowance — €13.8bn baseline, +82% on PR5.Split €11.4bn ESB Networks · €2.4bn EirGrid · high-demand scenario €18.9bn.
Fig. 1 / §1

PR5 (ink) against the PR6 baseline (navy), split ESB / EirGrid; the hatched frame is the high-demand scenario. The money is settled; delivery is the test.

Quarterly Sector Report · IE001§ 2 · Twelve findings · p. 10
09 — 10§ 2 · Six findings · 01 – 04 · 2×2 grid
§ 2 · Twelve findings on Ireland’s grid10
§ 2 · Twelve findings on Ireland’s grid2026 · sourced

Twelve findings. Each carries a confidence level.

HIGH — anchored to a named Irish primary source (CRU, EirGrid, CSO, SEAI). MEDIUM — direction of travel confirmed but a material figure is unpublished or contested. Every forward position is labelled as a projection.

Findings 01 – 12 · summary

  1. 01The connection door has reopened — on terms the grid cannot yet honour.
  2. 02A €13.8 billion network bill just landed at PR6 — close to double PR5.
  3. 03Data centres are now 22% of the country’s electricity, heading for a third.
  4. 04The lights stay on to 2027 on ~650 MW of temporary gas — €269 million of it.
  5. 05Ireland threw away one wind unit in nine — the grid, not the weather, is the reason.
  6. 06The connection queue got new rules under ECP-GSS — and still no published length.
  7. 07Ireland’s real adequacy plan is a cable to France — 700 MW from 2028.
  8. 08The single biggest hole in the network sits in judicial review until about 2031.
  9. 09Dublin is being rewired underground — at an undisclosed cost.
  10. 10The renewable auctions are delivering solar, not the wind the target needs.
  11. 11Battery storage is running at half the 2030 target, and the wrong shape.
  12. 1241.3% today, 80% by 2030 — the arithmetic no longer closes on the current grid.

Findings 01 – 09 follow in detail · pp. 11 – 13 · 10 – 12 carried on the § 6 matrix

Quarterly Sector Report · IE001§ 2
11§ 2 · Findings 01 – 03
§ 2 · Findings 01 — 03The connection reset · the €13.8bn bill · the data-centre load
Finding 01 · HIGH

The connection door reopened — on terms the grid may not meet.

For four years, connecting a large load in Dublin was, in practice, not an option — EirGrid’s 2021 assessment and the CRU’s direction CRU/21/124 tightened the criteria to a de-facto moratorium. The Large Energy User decision of 12 December 2025 (CRU2025236) ends it, and replaces it with a demanding condition: a new site above 10 MVA must provide new dispatchable generation or storage matched to 100% of its de-rated maximum import capacity, participate in the market, and source at least 80% of its annual demand from new Irish renewables on a six-year glide path. The difficulty is timing: the renewables and network capacity to satisfy the 80% condition are years away, so the plant that meets the self-generation requirement near-term is a gas or diesel generator. Ireland has told its biggest customers to clean up and, in the same breath, made more fossil generation the fastest way to comply.

Finding 02 · HIGH

A €13.8 billion network bill just landed.

On 16 December 2025 the CRU published the PR6 final determination — the revenue control deciding what the network companies may invest and recover between 2026 and 2030. The baseline is €13.8 billion, rising to €18.9 billion under the high-demand scenario; ESB Networks takes €11.4 billion, EirGrid €2.4 billion. Against the €7.6 billion allowed at PR5, this is an increase of roughly four-fifths — the clearest signal yet that the State has accepted the scale a decarbonising, data-centre-heavy grid requires. The risk now is not funding but execution: a network business can be given €11 billion and still fail to spend it on time, on the right assets, in the right places. Domestic network charges rise about €12 a year at the baseline and €21 under the high scenario; the pass-through to a large commercial or industrial user is materially larger and belongs in every operating model.

Finding 03 · HIGH

Data centres are now 22% of the country’s electricity.

No comparable economy carries a data-centre load this large relative to its grid. The CSO reported on 10 June 2025 that data centres used 22% of Ireland’s metered electricity in 2024 — 6,969 GWh of 31,903 GWh — up from 5% in 2015; in the Dublin region they are about half of all demand. EirGrid’s median forecast has the national share reaching 31% by 2034, with data-centre demand roughly doubling from 9.4 TWh in 2025 to 14.6 TWh. This is the demand-side pressure behind the connection reset, the emergency generation and the interconnection strategy at once. It is also why the grid question cannot be answered with a simple cap: the sector is deep, sticky foreign investment, and the same load that strains the network underwrites a large part of the tax base. The full anatomy of the sector is the subject of the companion report, IE002.

§ 2 · 01 – 03Findings 04 – 06 · facing